Łódź Fabryczna railway station


Łódź Fabryczna is the largest and most modern railway station in the city of Łódź, Poland. It was originally constructed at the initiative of industrialist Karl Wilhelm Scheibler in 1865. In the old Polish classification of stations it was placed under the B category.
The station is located in the centre of Łódź. Trains depart frequently via Koluszki to, Kraków, Częstochowa, and Tomaszów Mazowiecki. It was closed on 16 October 2011 as a part of a major redevelopment project to build a new railway station and transport interchange and reopened on 11 December 2016.

History

Building of the Łódź – Koluszki railway line began on 1 September 1865 after authorization was obtained from Tsar Alexander II in July 1865. The new line linked Łódź with the Warsaw–Vienna railway which was finished in 1848. Rails were laid simultaneously from Łódź and from Koluszki.
The single-gauge railway line of the factory and Lodz was supposed to serve primarily freight transport, in particular for coal and raw materials for the production of the ventricle. its hasty launch on November 19, 1865, provided only this function. According to the decisions of the town authorities, two station tracks ended blindly before the Dzika street, where the composition of the coal was established. Passengers of the first goods-passenger trains, launched on June 1, 1866, probably used a provisional barrack between Widzewska St. and Dzika street, however, it was not possible to unambiguously confirm it. the DZFL board's report for 1866 states that the station building in Lodz, as well as other buildings on the line, were finished and put into flight in December of the same year. However, in previous studies, the year 1868 or later years appears as the date of construction of the station. Construction of the railway was the beginning of the creation of the Łódź Circle Line.
The track extended almost to ulica Sienkiewicza. In 1868 a new station was built designed by the Warsaw-based architect Adolf Schimmelpfennig. The partly two-storey building did not differ from the typical industrial architecture of railway stations of that period. In addition to the station at the station, brick buildings were erected: a warehouse, a steam engine, a pressure tower, a ramp, a landing, a one-story house and a wooden shed for wagons. Quite accurate plan of the city of Rudolf Micinski, made on the basis of measurements carried out since 1869 and dated on 1873, even shows the course of the tracks: from the main track at the height of Targowa street outlet left a single-track track, ending with the main track before Dzika street. In the area of Wodna Street, went to the right ending in front of Widzewska street, a track leading to the engine house, the station and the square next to it. A new station has already been marked on the plan, and in the place of the existing pre-race car park at Kilinskiego St. two small warehouses. In addition, the plan showed the building of the water station and probably a small engine resemble two machines, but they were not marked leading to a non-runway. A small building, probably residential, is on the set at the exit of Targowa Street. In 1874, the building of the engine house was extended to create two additional positions, and the station was begun to be expanded with a fourth class waiting room.
In the years 1875-1876, in order to pass a small steel bridge over the Kielskie street, a small viaduct was built, which is why in 1912 it was enlarged. It was a typical pedestrian tunnel under the embankment of the Trajmwajowa street. In addition, about 800m of additional tracks were laid, two checkpoints for the turnstiles were erected, a new coal yard and wagons' weight, a cargo ramp and for station employees, a 16-family residential building was erected on Targowa street 1a.
In the years 1877-1878, in the area of Zagajnikowa street, it was found to the south, along the edge of the copse, a lateral track to the plants of Karol Scheirbler, and at the crossing there was a house of the guard, marked on the north side of the tracks. Subsequent plans of the city from the 1880s seemed to ignore the dynamic changes taking place at the station where there was already a large, though only two-wheeled steam locomotive to six locomotives, adjacent to it a mechanical workshop from Kuznia, erected also in 1880, a three-track, a wooden carriage hall with a 'Vogele' shifter in front of the gates, numerous freight warehouses and exchange offices in the open squares.
The station was extended in 1930. In June 2012 the station was demolished to make way for the building of a new station below ground level.

Rebuilding

The modernization of the Łódź – Warsaw line includes building a new station below ground level, just north of the site of the former Łódź Fabryczna station. A ramp, leading to a new tunnel, begins immediately after Łódź Widzew station, and the tunnel itself starts near the site of Łódź Niciarniana station. Initially it was planned to change the name of the station to Łódź-Central or Central, but according to the latest plans, the station name will not change because it is too well associated with the current station.
The station was originally envisaged to service new high-speed trains that were to run on a new high-speed line, the 'Y' line, intended to link Warsaw via Łódź and Kalisz to Wrocław and Poznań. Due to the latest estimated cost of 10 billion Euro, the high-speed line was put on hold by Sławomir Nowak, the Ministry of Transport, Construction and Marine Economy at the time of the decision.
Moving Łódź Fabryczna below ground releases land for development near the city centre. A modern transport interchange is envisaged between PKP trains, MPK Łódź trams, buses and PKS coaches. The railway line is to be extended in a new cross-city twin-track tunnel to Łódź Kaliska railway station.
In November 2010 PKP PLK announced a list of five consortia that had been invited by the railway infrastructure manager to tender to build the underground station. Work was to be completed in 2014.
In 2013 the estimated cost of the project was given as ranging from 1.7 to 1.9 billion PLN and the completion date was unknown. Reconstruction works finished in December 2016 and the station has reopened.
The main Architect of the new station and multimodal hub is Ewelina Oskroba, an Architect specialized in stations and transportation. The new station has been designed to be passenger-friendly, with the possibility to accommodate large numbers of travellers commuting between the train station, bus station, tramways and public parking. Although the station is underground, it was designed since the beginning to have plenty of daylight. The station allows a fluid connection between the different sides of the city and does not create any barrier. One of the initial requests was to allow the construction of eight-storey office buildings over the future station.