A2 autostrada (Poland)
The autostrada A2 in Poland, officially named Autostrada Wolności, is a motorway which runs from the Polish-German border in Świecko/Frankfurt, through Poznań and Łódź to Warsaw and, in the future, to the Polish-Belarusian border in Terespol/Brest. The motorway is a part of the European route E30 connecting Berlin and Moscow.
The motorway between German border and Warsaw was constructed in years 2001 – 2012 and is now complete. Most of the stretch from the border to Łódź is tolled, with fees being collected in toll booths across the motorway.
A2 does not formally run through Warsaw itself, instead turning into S2 Expressway. Eastwards from Warsaw, A2 is being gradually extended. The first segment of this section is the bypass of Mińsk Mazowiecki, which opened in August 2012. The second, long segment between Mińsk Mazowiecki and Warsaw, will be completed in 2020. The longest section from Mińsk Mazowiecki to Biała Podlaska is planned to be completed by 2024. The last segment to the Belarusian border might be completed by 2025, but the precise schedule will depend on government funding decisions.
Route
History of construction
The first highway planned along part of this route was a Reichsautobahn initiated by Nazi Germany to connect Berlin with Poznań. The construction of this highway, accelerated after Poznań was incorporated into Germany following the Invasion of Poland in 1939, was interrupted by the war and never finished, but traces of its earthworks were clearly visible on satellite photographs for decades afterwards, especially between the border with Germany and Nowy Tomyśl. Most of these traces have now disappeared as the modern motorway was built largely following the same route. A short stretch of the uncompleted highway between the border and Rzepin was finished as a dual carriageway road after 1945, in effect forming an extension of the German A 12 highway. Except for this stretch, the construction work was not continued in the decades after the war.New plans to build the A2 motorway were seriously formulated in communist Poland in the 1970s, possibly with the goal of completing it in time for the Moscow Olympics in 1980. Because of the economic crisis which hit the country in the late 1970s and continued throughout the 1980s, only a section from Września to Konin was opened in the 1980s. Construction of another stretch was started and then abandoned, leaving an interesting ruin informally named Olimpijka, which was in turn demolished around 2010 when building of the motorway resumed.
Intensive construction of the motorway started only in 2001 after the fall of communism in Poland in 1989. Out of the planned total length of, have been completed. A section of about has been fully open since 2004. This section is a toll road, with the exception of a short stretch through Poznań which serves as that city's bypass. An additional section from Konin to Stryków near Łódź was opened on 26 July 2006. A short bypass of Stryków, consisting of a 2 km extension of the A2 and a provisional single carriageway section of future motorway A1, was opened in December 2008, to ease the heavy traffic in that town generated when the motorway reached it.
As of winter 2009/2010, the plan was to finish the whole section between the border with Germany and Warsaw by the Spring of 2012, giving the Polish capital its first motorway connection to the European motorway network in time for the Euro 2012 football championships. That ambitious goal was jeopardised due to various difficulties encountered in finalizing the construction contracts and the delays that resulted. The section from Stryków to Warsaw was to be built in a public-private partnership, but the negotiations between the government and private companies interested in participating collapsed in February 2009 due to disputes over financing terms. It was then decided that this section of the motorway would be built using public funds alone. The new bidding process was started on 27 March, and the contracts for design and construction of the road were signed on 28 September. The section had been divided into 5 parts and so construction work began in 2010. The contractors were required to have the motorway open to traffic in time for Euro 2012. This goal was an ambitious one and ultimately proved challenging, given the possibility of unexpected delays during construction and the fact that the Chinese consortium abandoned the project less than a year later, so that new contractors had to be selected to replace it. The goal was to have this motorway stretch provisionally opened to traffic in time for Euro 2012, even if it's not fully completed, with various restrictions such as a lower speed limit to ensure safety. For a while it was not clear whether even this limited goal would be reached, but the motorway opened to traffic in June 2012 after very intensive construction work in the final few months.
In November 2011 construction of the stretch to the German border from Nowy Tomyśl had been completed. The road was opened to public traffic on 1 December. Toll plazas on this stretch of the highway weren't opened until May 2012 so use of the western section of the A2 was free of charge until then.
In May 2013, Interchange with S3 was opened to traffic. First stretch is between the interchange with the A2 motorway and the "Świebodzin North" interchange. In June 2013 S3 was extended further and opened to traffic to reach from the "Świebodzin South" interchange to the existing stretch of the S3 expressway at Sulechów. In July 2013 the elevated bypass of Świebodzin between the interchanges "Świebodzin North" and "Świebodzin South" fully opened to traffic thus fully extending the S3 from Szczecin to Sulechów.
Guarantee scandal
After COVEC withdrew from completing its construction of the A2, Bank of China was to pay a performance guarantee to the Polish government's roads organization GDDKiA. However, with Export-Import Bank of China, they refused to pay this; only Deutsche Bank honored its obligations under the court decision.Plans
The eastern section from Warsaw to the border crossing with Belarus at Kukuryki near Brest, about in length, is still largely in planning stages. The decision finalizing the route of this section was announced in December 2011, the exception having been a short section of A2 forming the bypass of Mińsk Mazowiecki which has been under construction since August 2009. It opened to traffic in August 2012. The section between Warsaw and Mińsk Mazowiecki is planned to be opened in 2020. The tenders for section between Mińsk Mazowiecki and Siedlce have been announced in 2019. The remaining section east of Siedlce is said to be planned for completion by 2025.It is worth noting that the A2 motorway doesn't actually run through Warsaw, as the inhabitants of the districts through which it was to pass have successfully blocked its construction. This outcome was somewhat unusual, since the corridor for the motorway has been reserved by the city planners since the 1970s and kept free of construction. Instead, the traffic will be rerouted through two express roads, of lower standard than the originally planned motorway. Paradoxically, one of these roads will run along the originally planned motorway corridor, so the residents who protested the construction will still end up with a busy road running through their districts, possibly even more inconvenient than the original road would have been. In the most affected area, the district of Ursynów, the express road will run in a tunnel, which will be built at considerable expense.