Barcelona Metro line 10


Line 10 is the name of one of the two branches of the Barcelona metro line 9, currently under construction and to be operated by TMB. Like Line 9 and Line 11, it will be an automatic train operation metro line.

Overview

The line will link the Zona Franca with Badalona, through Barcelona proper, sharing most of the area covered by L9. L9/10 will be the deepest and longest line in the network. Originally expected to be ready by 2008, ongoing problems with its construction are going to delay its completion until as late as 2025.
The line is currently operated in two sections, North and South, similarly to line 9.

Northern section

The section from Gorg to Bon Pastor opened on 18 April 2010, and the section from La Sagrera to Bon Pastor opened 26 June 2010. This section is operated as L10 Nord.

Southern section

On 8 September 2018 the section between Foc station and the junction with the main route of line 9 at Can Tries-Gornal opened to the public, with the exception of the stations at Ildefons Cerdà and Provençana. The opening of these two stations was deferred to 2019, with the rest of the line on the viaduct through the Zona Franca proper opening between 2022 and 2025. Trains on this section operate between Foc and Collblanc stations, as the line from Collblanc to Zona Universitària is single track and does not have sufficient capacity for both L9 and L10 to run. This section is operated as L10 Sud.
Provençana station opened to the public on 2 March 2019 followed by Ciutat de la Justícia on 24 November 2019.