Barh Super Thermal Power Station


Barh Super Thermal Power Station or NTPC Barh is located in Barh in the Indian state of Bihar.
NTPC Barh is located barely four kilometres east of the Barh sub-division on National Highway-31 in Patna district. The project has been named a mega power project, and is owned by Indian energy company National Thermal Power Corporation.
The project has been contested as it is nearby Himalayan Range and needs stricter anti-pollution controls.
The 1,320MW Barh Stage-2 built by BHEL is operational while 1,980MW Barh Stage-1 is being built by Russian firm Technopromexport.
Bihar's share is 1183 MW from NTPC Barh.
The main power plant and the township is spread over an area of 1,186 acres. The legal possession of 1,186 acres of land has been acquired for setting up the main power plant and its township which includes 12 villages.
The then PM, Atal Bihari Vajpayee, had laid the foundation stone of the main plant of stage-1 of NTPC Barh on March 6, 1999. The formal inauguration of its site office and laying of the foundation stone of the training centre at the plant site was done in September 2003.

Project Cost

The plant is to produce 3,300MW of power at a cost of over Rs 26,000 crore.
The total approved cost of stage-1 has Rs 8,692.97 crore. The total approved cost of stage-2 plant is Rs 7,688.12 crore.

Capacity

Unit-1 of stage-2 commissioned in November 2013. Unit-2 of stage-2 commissioned in March 2015. The first unit of NTPC Barh is expected to start generation from December 2019 instead of the scheduled August 2020, while the second and third units of stage-I will be made operational in December 2020 and August 2021, respectively.
Inland Waterways Authority of India received bids in 2013 September for coal movement on 1620 km National Waterway 1 from Haldia to NTPC's Barh which is about 1000 km away.
StageUnit NumberCapacity EPC ContractorDate of CommissioningStatus
1st1660TechnopromexportTo start from December 2019. Delayed as Technoproexport is saying it has entered a loss-making contract and is asking for $570 million before it can fulfil its obligation to which NTPC objected.
1st2660TechnopromexportTo start from December 2020. Delayed
1st3660TechnopromexportTo start from August 2021.Delayed
2nd4660Bharat Heavy Electricals2013 NovemberRunning
2nd5660Bharat Heavy Electricals2015 MarchRunning
TotalFive3300

Boiler Balance Work Of Stage -I

Boiler Balance Work of Stage-I