Chennai High Speed Circular Transportation Corridors is an urban road transit in the form of elevated concentric beltways planned for the city of Chennai. The beltways are envisaged as an elevated 2-tier system with design speed of 80 km/h. The top tier is a 2-lane dedicated corridor for the Chennai BRTS system. The second tier is a 4-lane road for 4-wheelers.

Beltways

4 beltways have been proposed which covers a distance of 107.795 km. A connectivity corridor is also proposed to integrate the beltways with the ECR elevated expressway.

Beltway 1

Beltway 1 is the outermost beltway encompassing an area of 167 km2. It is formed by the following corridors.
This beltway encompasses an area of 52 km2. It is formed by the following corridors.
This beltway encompasses an area of 30 km2. It is formed by the following corridors.
The beltway 4 is formed by the following corridors.
  1. Already under construction by NHAI

    Corridor Details

These 4 beltways can be broken down into 9 corridors.
NameTypeAlong/AcrossFromToviaLength Cost in INR crores StatusDeveloped byCompletion
Adyar CorridorElevated 2-tier CorridorSouthern Banks of Adyar RiverThiru-vi-ka BridgePorurNandambakkam15.8451430ProposedAdyar Poonga Trust2013
Port-Maduravoyal CorridorElevated CorridorBanks of Cooum RiverChennai PortMaduravoyal191655/2090Under ConstructionNHAI2012
Chennai Bypass CorridorFully access-controlled at grade 4-lane corridor with 2-lane elevated BRTS corridor along the medianTambaramManaliMaduravoyal32CompleteNHAI2010
North Buckingham Canal CorridorElevated CorridorWestern Bank of Buckingham Canal, Wall Tax Road, Poonamallee High Road, Flag Staff RoadManali Oil Refinery Road War MemorialChennai Central12.3740ProposedAdyar Poonga Trust
Central Buckingham Canal CorridorElevated CorridorWestern Bank of Buckingham CanalSwami Sivananda SalaiRadhakrishnan Salai2.860170ProposedAdyar Poonga Trust
Connectivity CorridorElevated CorridorECR Elevated Expressway, Santhome bypass road, Santhome High Road, Greenways RoadRadhakrishnan SalaiThiru-vi-ka BridgeForeshore Estate5.140350ProposedAdyar Poonga Trust
Mambalam Canal CorridorElevated CorridorMambalam CanalAdyar CorridorG.N. Chetty RoadAnna Salai, South Usman Road, Venkatnarayana Road, Theyagaraya Road5.000195ProposedAdyar Poonga Trust
Inner Ring Road CorridorAt-grade 8-lane CorridorInner Ring RoadJafferkhan BridgeKoyambeduAshok Nagar5.9525At-grade corridor coz of elevated corridor 2 of Chennai Metro that is under construction along the same alignment.Adyar Poonga Trust
East Coast Elevated ExpresswayElevated CorridorEast CoastLight HouseECRBesant Nagar9.7430* ProposedTamil Nadu State Highways2013
Entire HSCTC107.7955400#

* Revised cost during tender process
# Excluding cost of Chennai Bypass Corridor

Chennai Port - Maduravoyal Corridor 19 km

This 19 km corridor is implemented under Phase-VII of National Highways Development Project by NHAI. The pre-construction work has already begun.

Chennai Bypass Corridor 32 km

The Chennai bypass Corridor is a 32 km fully access controlled at-grade corridor. A 2-lane elevated BRTS corridor is proposed along the median of the Phase II of this expressway. The corridor is under construction.

Adyar Corridor 15.845 km

Section I
Section II
Section I
Section II
Section III
Section IV
This is 9.7 km elevated expressway along the east coast of Bay of Bengal from Light House, Chennai to East Coast Road via Besant Nagar.

Interchanges

A total of 15 interchanges has been proposed along the HSCTC alignment of which 3 are already under construction by NHAI. A 3-tier interchange at Irumbuliyur is already functional.

Adyar Corridor Interchanges (6)

2008

January:
November:
28 May:
31 May:
3 June:
16 June:
12 August:
26 August: