Criticism of the Space Shuttle program


Criticism of the Space Shuttle program stemmed from claims that NASA's Shuttle program failed to achieve its promised cost and utility goals, as well as design, cost, management, and safety issues. Fundamentally, it failed in the goal of reducing the cost of space access. Space Shuttle incremental per-pound launch costs ultimately turned out to be considerably higher than those of expendable launchers.
By 2011, the incremental cost per flight of the Space Shuttle was estimated at $450 million, or $18,000 per kilogram to low Earth orbit. By comparison, the comparable Proton launch vehicle is said to cost as little as $110 million, or around $5,000/kg to LEO, despite not being reusable.
When all design and maintenance costs are taken into account, the final cost of the Space Shuttle program, averaged over all missions and adjusted for inflation, was estimated to come out to $1.5 billion per launch, or $60,000/kg to LEO. This should be contrasted with the originally envisioned costs of $118 per pound of payload in 1972 dollars.
It failed in the goal of achieving reliable access to space, partly due to multi-year interruptions in launches following Shuttle failures. NASA budget pressures caused by the chronically high NASA Space Shuttle program costs have eliminated NASA manned space flight beyond low earth orbit since Apollo, and severely curtailed use of unmanned probes. NASA's promotion of and reliance on the Shuttle slowed domestic commercial expendable launch vehicle programs until after the 1986 Challenger disaster.
Two out of the five spacecraft were destroyed in accidents, killing 14 astronauts, the largest loss of life in space.

Purpose of the system

"Space Transportation System" was created to transport crewmembers and payloads into low Earth orbits. It would afford the opportunity to conduct science experiments on board the shuttle to be used to study the effects of space flight on humans, animals and plants. Other experiments would study how things can be manufactured in space. The shuttle would also enable astronauts to launch satellites from the shuttle and even repair satellites already out in space. The Shuttle was also intended for research into the human response to zero-g.
The Shuttle was originally billed as a space vehicle that would be able to launch once a week and give low launch costs through amortization. Development costs were expected to be recouped through frequent access to space. These claims were made in an effort to obtain budgetary funding from the United States Congress. Beginning in 1981, the space shuttle began to be used for space travel. However, by the mid-1980s the concept of flying that many shuttle missions proved unrealistic and scheduled launch expectations were reduced 50%. Following the Challenger accident in 1986, missions were halted pending safety review. This hiatus became lengthy and ultimately lasted almost three years as arguments over funding and the safety of the program continued. Eventually the military resumed the use of expendable launch vehicles instead. Missions were put on hold again after the loss of Columbia in 2003. Overall, 135 missions were launched during the 30 years after the first orbital flight of Columbia, averaging approximately one every 3 months.

Costs

Some reasons for the higher-than-expected operational costs were:
Some researchers have criticized a pervasive shift in NASA culture away from safety in order to ensure that launches took place in a timely fashion, sometimes called "go fever". Allegedly, NASA upper-level management embraced this decreased safety focus in the 1980s while some engineers remained wary. According to sociologist Diane Vaughan, the aggressive launch schedules arose in the Reagan years as an attempt to rehabilitate America's post-Vietnam prestige.
The physicist Richard Feynman, who was appointed to the official inquiry on the Challenger disaster, estimated the risk to be "on the order of a percent" in his report, adding, "Official management, on the other hand, claims to believe the probability of failure is a thousand times less. One reason for this may be an attempt to assure the government of NASA perfection and success in order to ensure the supply of funds. The other may be that they sincerely believed it to be true, demonstrating an almost incredible lack of communication between themselves and their working engineers."
Despite Feynman's warnings, and despite the fact that Vaughan served on safety boards and committees at NASA, the subsequent press coverage has found some evidence that NASA's relative disregard for safety might persist to this day. For example, NASA discounted the risk from small foam chunk breakage at launch and assumed that the lack of damage from prior foam collisions suggested the future risk was low.

Shuttle operations

The Shuttle was originally conceived to operate somewhat like an airliner. After landing, the orbiter would be checked out and start being mated to the External Tank and Solid Rocket Boosters, and be ready for launch in as little as two weeks.
In practice, before the loss of Challenger, about half of the turnaround time after a mission was unplanned tests and modifications based on unexpected events that occurred during flight. The process usually took months; Atlantis set the pre-Challenger record by launching twice within 54 days, while Columbia set the post-Challenger record of 88 days. The Shuttle program's goal of returning its crew to Earth safely conflicted with the goal of a rapid and inexpensive payload launch. Furthermore, because in many cases there were no survivable abort modes, many pieces of hardware had to function perfectly and so required careful inspection before each flight. The result was high labor cost, with around 25,000 workers in Shuttle operations and labor costs of about $1 billion per year.
Some shuttle features initially presented as important to Space Station support have proved superfluous:
While the technical details of the Challenger and Columbia accidents are different, the organizational problems show similarities. Flight engineers' concerns about possible problems were not properly communicated to or understood by senior NASA managers. The vehicle gave ample warning beforehand of abnormal problems. A heavily layered, procedure-oriented bureaucratic structure inhibited necessary communication and action.
With Challenger, an O-ring that should not have eroded at all did erode on earlier shuttle launches. Yet managers felt that because it had previously eroded by no more than 30%, this was not a hazard as there was "a factor of three safety margin" Morton-Thiokol designed and manufactured the SRBs, and during a pre-launch conference call with NASA, Roger Boisjoly, the Thiokol engineer most experienced with the O-rings, pleaded with management repeatedly to cancel or reschedule the launch. He raised concerns that the unusually low temperatures would stiffen the O-rings, preventing a complete seal during flexing of the rocket motor segments, which was exactly what happened on the fatal flight. However, Thiokol's senior managers, under pressure from NASA management, overruled him and allowed the launch to proceed. One week prior to the launch, Thiokol's contract to reprocess the solid rocket boosters was also due for review, and cancelling the flight was an action that Thiokol management wanted to avoid. Challenger's O-rings eroded completely through as predicted, resulting in the complete destruction of the spacecraft and the loss of all seven astronauts on board.
Columbia was destroyed because of damaged thermal protection from foam debris that broke off from the external tank during ascent. The foam had not been designed or expected to break off, but had been observed in the past to do so without incident. The original shuttle operational specification said the orbiter thermal protection tiles were not designed to withstand any debris hits at all. Over time NASA managers gradually accepted more tile damage, similar to how O-ring damage was accepted. The Columbia Accident Investigation Board called this tendency the "normalization of deviance" – a gradual acceptance of events outside the design tolerances of the craft simply because they had not been catastrophic to date.
The subject of missing or damaged thermal tiles on the Shuttle fleet only became an issue following the loss of Columbia in 2003, as it broke up on re-entry. In fact, Shuttles had previously come back missing as many as 20 tiles without any problem. STS-1 and STS-41 had all flown with missing thermal tiles from the orbital maneuvering system pods.
This image from the NASA archives shows several missing tiles on the STS-1 OMS pods. The problem on Columbia was that the damage was sustained from a foam strike to the reinforced carbon-carbon leading edge panel of the wing, not the heat tiles. The first Shuttle mission, STS-1, had a protruding gap filler that diverted hot gas into the right wheel well on re-entry, resulting in a buckling of the right main landing gear door.

Risk contributors

An example of technical risk analysis for a STS mission is SPRA iteration 3.1 top risk contributors for STS-133:
  1. Micro-Meteoroid Orbital Debris strikes
  2. RS-25-induced or RS-25 catastrophic failure
  3. Ascent debris strikes to TPS leading to LOCV on orbit or entry
  4. Crew error during entry
  5. RSRM-induced RSRM catastrophic failure
  6. COPV failure
John Young and Jerry L. Ross were among those astronauts who believed that the shuttle was always an experimental craft, not an operational vehicle for routine spaceflight as President Ronald Reagan declared after STS-4. Rick Hauck said in 2017 that before STS-1 he saw an analysis estimating the risk of loss of the vehicle as one in 280, but an internal NASA risk assessment study released in late 2010 or early 2011 concluded that the agency had seriously underestimated the level of risk involved in operating the Shuttle. The report assessed that there was a 1 in 9 chance of a catastrophic disaster during the first nine flights of the Shuttle but that safety improvements had later improved the risk ratio to 1 in 90. In 1984 Reagan signed a National Security Decision Directive stating that the shuttle would not be "fully operational" until it could fly 24 missions a year, perhaps by 1988; the shuttle never flew more often than the nine missions of 1985, and averaged about six missions a year between 1988 and 2003.
Although many NASA astronauts criticized the payload specialist program in part because they did not believe less-trained outsiders were fully aware of the risks of spaceflight, full-time astronauts may not have been either. Charles Bolden was amazed to learn after the loss of Columbia that the "impenetrable" leading wing edges of the vehicle he flew for 14 years were less than an inch thick. NASA in October 1982 predicted 37 shuttle flights by early 1986, but Challengers loss was the 25th shuttle flight. Hauck, with much experience flying dangerous aircraft at the United States Naval Test Pilot School, said "If I knew in advance that one in twenty-five would fail, I would probably think twice about flying three out of the first twenty-six flights".

Retrospect

While the system was developed within the original cost and time estimates given to President Richard M. Nixon in 1971, the operational costs, flight rate, payload capacity, and reliability by the time of the February 2003 Columbia accident proved to be much worse than originally anticipated. A year before STS-1's April 1981 launch, The Washington Monthly accurately forecast many of the Shuttle's issues, including an overambitious launch schedule and the consequently higher-than-expected marginal cost per flight; the risks of depending on the Shuttle for all payloads, civilian and military; the lack of a survivable abort scenario if a Solid Rocket Booster were to fail; and the fragility of the Shuttle's thermal protection system.
In order to get the Shuttle approved, NASA over-promised its economies and utility. To justify its very large fixed operational program cost, NASA initially forced all domestic, internal, and Department of Defense payloads to the shuttle. When that proved impossible, NASA used the International Space Station as a justification for the shuttle. NASA administrator Michael D. Griffin argued in a 2007 paper that the Saturn program, if continued, could have provided six manned launches per year – two of them to the Moon – at the same cost as the Shuttle program, with an additional ability to loft infrastructure for further missions:
Some had argued that the Shuttle program was flawed. Achieving a reusable vehicle with early 1970s technology forced design decisions that compromised operational reliability and safety. Reusable main engines were made a priority. This necessitated that they not burn up upon atmospheric reentry, which in turn made mounting them on the orbiter itself a seemingly logical decision. However, this had the following consequences:
A concern expressed by the 1990 Augustine Commission was that "the civil space program is overly dependent upon the Space Shuttle for access to space." The committee pointed out, "that it was, for example, inappropriate in the case of Challenger to risk the lives of seven astronauts and nearly one-fourth of NASA's launch assets to place in orbit a communications satellite."
There are some NASA spin-off technologies related to the Space Shuttle program which have been successfully developed into commercial products, such as using heat-resistant materials developed to protect the Shuttle on reentry in suits for municipal and aircraft rescue firefighters.