The Culebra Cut, formerly called Gaillard Cut, is an artificial valley that cuts through the Continental Divide in Panama. The cut forms part of the Panama Canal, linking Gatun Lake, and thereby the Atlantic Ocean, to the Gulf of Panama and hence the Pacific Ocean. It is from the Pedro Miguel lock on the Pacific side to the Chagres River arm of Lake Gatun, with a water level above sea level. Construction of the cut was one of the great engineering feats of its time; the immense effort required to complete it was justified by the great significance of the canal to shipping, and in particular the strategic interests of the United States of America. Culebra is the name for the mountain ridge it cuts through and was also originally applied to the cut itself. From 1915 to 2000 the cut was named Gaillard Cut after US Major David du Bose Gaillard, who had led the excavation. After the canal handover to Panama in 2000, the name was changed back to Culebra. In Spanish the cut is known as the Corte Culebra and is also called the Snake Cut.
Construction
French work
The excavation of the cut was begun by a French venture, led by Ferdinand de Lesseps, which was attempting to build a sea-level canal between the oceans, with a bottom width of 22 meters. Digging at Culebra began on January 22, 1881. A combination of disease, underestimation of the problem, and financial difficulties led to the collapse of the French effort, which was bought out by the United States in 1904. The French had excavated some of material from the cut, and had lowered the summit from 64 meters above sea level to 59 meters, over a relatively narrow width.
American work
The United States took over on May 4, 1904. Under the leadership of John F. Stevens, and later George Washington Goethals, the American effort started work on a cut that was wider but not as deep, as part of a new plan for an elevated lock-based canal, with a bottom width of ; this would require creation of a valley up to wide at the top. A vast amount of new earthmoving equipment was imported, and a comprehensive system of railways was constructed for the removal of the immense amounts of earthen and rocky. Major David du Bose Gaillard, of the U.S. Army Corps of Engineers, joined the project at the same time as Goethals, and he was put in charge of the central district of the canal, which was responsible for all of the work between Gatun Lake and the Pedro Miguel locks — most notably, the Culebra Cut. Gaillard brought dedication and quiet, clear-sighted leadership to his difficult, complex task. The scale of the work was massive. Hundreds of large steam drills bored holes in which were planted tons of dynamite, which blasted the rock of the cut so that it could be excavated by steam shovels, most made by Bucyrus-Erie. Dozens of spoils trains took the spoil from the shovels to the landfill dumps, about away. In a typical day, 160 trainloads of material were hauled away from a cut. This workload on the railroads required some skillful co-ordination. At the busiest times, there was a train going inbound or outbound almost every minute. Six thousand men worked in the cut, drilling holes, placing explosives, controlling steam shovels, and running the dirt trains. They also moved and extended the railroad tracks as the work moved forward. Twice a day work stopped for blasting, and then the steam shovels were moved in to take the loose spoil away. More than 600 holes filled with dynamite were fired daily. In all, of dynamite were used. In some locations, about of dynamite were planted and detonated for a single blast.
Landslides
The excavation of the cut was one of the greatest areas of uncertainty in the creation of the canal, due to the unpredicted large landslides. The International Board of Consulting Engineers had mistakenly decided that the rock would be stable at a height of with a slope of 1 in 1.5; in practice, the rock began to collapse from that slope at a height of only. The misjudgment was in part due to unforeseen oxidation of the underlying ironstrata due to water infiltration, which caused weakening and eventually a collapse of the strata. Strain softening of the underlying shale layers of sedimentary units caused continuation of sliding as the strength of the slide post-failure was reduced. The first and largest major slide occurred in 1907 at Cucaracha. The initial crack was first noted on October 4, 1907, followed by the mass wasting of about of clay. This slide caused many people to suggest the construction of the Panama Canal would be impossible; Gaillard described the slides as tropical glaciers, made of mud instead of ice. The clay was too soft to be excavated by the steam shovels, and it was therefore largely removed by sluicing it with water from a high level. After this, the sediment in the upper levels of the cut were removed, resulting in less weight over the weak strata. Landslides continued to be a problem after the canal's opening, causing intermittent closures.
Completion
Steam shovels broke through the Culebra Cut on May 20, 1913. The Americans had lowered the summit of the cut from to above sea level, at the same time widening it considerably, and they had excavated over of material. Some of this material was additional to the planned excavation, having been brought into the cut by the landslides. Gaillard was promoted to colonel in 1913. One month later, on December 5, he died of a brain tumor in Baltimore, Maryland, and hence he did not live to see the opening of the canal in 1914. The Culebra Cut, as it was originally known, was renamed to the Gaillard Cut on April 27, 1915, in his honor. After the handing over of the canal to Panama in 2000, the old name Culebra Cut was reinstated.