The Midland Railway found that with the boom in railway traffic during the last decade of the 19th century the pressure on railway routes was intense with the volume of passenger and goods traffic increasing. This problem was present in all parts of the UK - though the Midlands, especially the Main Line to Manchester and Liverpool, was particularly crowded. The London and North Western Railway and the Great Northern Railway owned the Main Line to Manchester, which meant that the Midland's trains had the lowest priority. The Midland joined with the Manchester, Sheffield and Lincolnshire Railway company to form the Sheffield and Midland Railway Companies' Committee with the intention of building a "new line" that would bypass the main line, and give priority to their own trains, thus speeding up the service. Various routes were tried, including the "Manchester South District Railway Company" from Heaton Mersey to Chorlton-cum-Hardy. However, congestion continued.
To relieve the congestion through Stockport Tiviot Dale a new line, to be called the "New Mills and Heaton Mersey Railway", was authorised by Act of Parliament in 1898. The plan was to create a railway line that would take four tracks, and most bridges and cuttings were constructed with this width in mind.
Location
Despite being named after Disley, the tunnel runs under High Lane and Disley. The New Mills and Heaton Mersey Railway line goes underground where the Middlewood Way, crosses the line, about 1/4 mile north of the A6 in High Lane. The tunnel passes under a housing estate, the Macclesfield Canal, Disley golf course and finally the Peak Forest Canal, just before emerging at Disley, meeting the Hope Valley line.
Construction
The construction method used was to drive the tunnel bore from both ends, while also sinking 11 shafts from the top of the hill along the path of the railway. Work began in 1900, and the miners worked both directions from each shaft, which allowed 24 simultaneous working faces. Ten of the shafts were later used for ventilation, and are still in use - they are visible as large blue brick towers following the line of the tunnel. The Midland Railway purchased the land above the tunnel in order to sink the shafts - boundary markers made of old rails, with the initials "M.R.", remain along the line of the tunnel. A surface standard gauge contractors line was set up, using steam locomotives and a "steam navvy", following the subterranean path of the tunnel.
The construction of the tunnel brought a small army of navvies into the area. They were housed in temporary villages at New Mills and Wybersley, and in specially-built houses near the Rising Sun pub in Hazel Grove, which still exist, and are known as the "Navvy Mansions". A church made of tin was erected at Wybersley, where the Midland Railway had a local administration office. Three hundred of the navvies' children attended the local schools.
Operation
The first section of the line opened in 1901 from Heaton Mersey to Cheadle Heath where a large station was built to serve Stockport. The second section from Cheadle Heath to New Mills South Junction opened to passenger traffic on 1 July 1902. A local passenger station at Hazel Grove was constructed, but this closed in 1917 as the main purpose of the line was express trains. The line was fast, with trains reaching 100 mph along the track. In 1959 a train recorder timed a Britannia Class locomotive, the Iron Duke, doing 89 mph between Cheadle Heath and Didsbury. In 1973, a freight train was derailed inside the tunnel due to a broken rail. Recovery of the wagons took about a week.