Dwarka Expressway


Northern Peripheral Road or NH 248-BB, commonly known as Dwarka Expressway is a long, under construction, 8-lane, controlled-access highway connecting Dwarka in Delhi to Gurugram in Haryana. The expressway will take off from Km 20 of NH-48 at Shiv Murti in Mahipalpur in Delhi and terminate at Km 40 of NH-48 near Kherki Daula Toll Plaza in Gurugram in Haryana. The NPR has been planned as an alternate road link between Delhi and Gurgaon, and is expected to ease the traffic situation on the Delhi-Gurgaon Expressway. The expressway was initially planned to be long and was expected to open by 2012 but land acquisition issues delayed the project.
Entire project, costing INR 7,500 crore was planned in 2006, contract was awarded in 2011. Of the original 18 km project, 14 km were completed by 2016. Several more kilometer project routes was added to the scope of the project as an extension. Various parts of the project remained delayed due to land acquisition and tree transplantation hurdles, resulting in the intervention from the Prime Minister's office in November 2018 to resolve the pending issues. Subsequently, the land for the 10 km section was handed by the Haryana and Delhi, AAI and HSVP were in the process of expediting the resolution in December 2018.
One of the cause of delay was due to NHAI's need for the land from DDA to transplant 13,000 trees from the route alignment, which in November 2018 Delhi's Chief Minister Arvind Kejriwal agreed to provide promptly along with other necessary clearances. In December, Haryana too handed over the land for 10 km route to NHAI and was in process of handing over the remaining land for the 4 km route by 31 December 2018. Earlier in January 2018, AAI too had agreed to sell their land to NHAI for the route falling on their land. Put together all of this takes care of the land needed for the entire route from various parties i.e. AAI, DDA and HSVP.

History

The Northern Peripheral Road was envisaged as an alternate route for connecting Dwarka and Gurgaon in 2006. It would have been 18 km long, signal-free road, with 14 km in Gurgaon and rest in Delhi. A 3.2 km long Central Peripheral Road was planned to connect it to Southern Peripheral Road at Kherki Daula on NH-48. Land acquisition started in 2007-08. The construction contract was given to JSR Construction Private Ltd and India Bulls Private Ltd in April 2011 and the completion date was set to be 31 March 2012. The Punjab and Haryana High Court disposed of the petitions in May 2015. In June 2016, the project was acquired by National Highways Authority of India and road was renamed National Highway 248-BB. By that time, 14 km stretch of the expressway with six lanes had been completed. The scope of the project was expanded and the proposed Central Peripheral Road and 6.3 km long section of Urban Extension Road-II were included as part of the expressway. But construction couldn't be started immediately as HUDA was not able to hand over land to NHAI due to the matter of allotment of alternate plots to oustees being heard in Punjab and Haryana High Court. On 28 May 2018, the High Court directed HUDA to allot alternate houses to 72 oustees, holding General Power of Attorney or Special Power of Attorney, within two weeks and thus allowing the authority to demolish remaining houses and hand over the land to NHAI.

Route and construction

This 29 km long project, 18.9 in Gurugram and 10.1 km in Delhi, is expected to be completed by May 2021. Work on Haryana portion can commence as of Dec 2018. Delhi has provided the land but yet to provide the forests clearance as of December 2018. Route alignment and phases/packages of this expressway being built by NHAI are as follows:
This stretch will be 5.3 km long starting from Shiv Murti at NH-8 and ending at the approach of the Rail under Bridge near Sector 21, Dwarka. 3.5 km of this will be a deep tunnel running under the runway, which will cost INR1000 crore.
Status in May 2018 - tendering: Tender will be awarded by December 2018 with target completion date of May 2021.
This 4.2 km long stretch will be between Km 5.3 at the Rail under Bridge and Km 9.5 at the Delhi Haryana border on the expressway.
This stretch will be 10.2 km long between Km 9.5 to Km 19.5 of the expressway. The road will pass through Sectors 102, 103, 104, 105, 106, 109, 110, 111, 112 and 113 in Gurugram. Since this section has continuous intersection of sector roads, most of the stretch will be constructed as elevated dual carriageway of 4 lanes each. The service roads will run beneath the main carriageway and will be elevated at all major junctions. The crossroads will also be depressed with underpasses at all major junctions. It will cost INR 1,333 crore and tenders have been awarded already.
This 8.77 km stretch will start from Rail over Bridge at Basai and end at a cloverleaf interchange near Kherki Daula at Km 40 of the NH-48, thus including the route originally planned for the CPR. As per NHAI website, this eight-lane Expressway will be constructed on EPC Mode at a cost of Rs 1047.007 crore. The 8.76 km stretch will be constructed by M/s Larsen and Toubro Ltd. The project consists of an 8-lane elevated structure for the main carriageway of Dwarka Expressway, Trumpet Interchange for Manesar Road and Cloverleaf interchange with NH-8-SPR intersection. The completion period of the project is two years with a maintenance period of four years. Under the project, a minor bridge will be widened, additional ROBs, five VUP, six Bus Bays with Bus Shelter will be erected and four Junction Improvements will be carried out. Status: Construction commenced in December 2018 after the entire land was handed over to NHAI by the HSVP in December.
An east-to-west running new 4-lane shallow 1.5 km tunnel costing INR350 crore being built from north-to-south as part of Dwarka Expressway to Terminal 3 of Indira Gandhi International Airport. Vasant Kunj, IIT, Munirka and Mehrauli. It will benefit commuters from the Vasant Kunj, IIT Delhi, Munirka and Mehrauli.
Status in Jan 2018 - land sale agreed: AAI agreed to sell the required land to NHAI at market price. In April 2018, NHAi announced they will award the contact in May 2018 which will be completed within 3 years i.e. May 2021.

Route alignment

The route alignment to the west of Gurugram is as follows: