East West Metro Tunnel is an under construction underwater river tunnel of Kolkata Metro in Kolkata, West Bengal. The river tunnel is constructed underneath Hooghly river. Tunnel length is and width is. A 520m stretch of the tracks will go through a tunnel under the Hooghly river. The roof of the tunnel would be about 30 metres from the ground level. The tunnel will be completed in 2021. The tunnel will be the first under water river tunnel in India. The tunnel is used by East West Metro Line for metro rail service and constructed by Kolkata Metro Rail Corporation.
Construction
The section between Sealdah metro station and Mahakaran metro station was realigned due to the inability of GoWB to provide land on the surface along the original route. Even on the new alignment a station planned at Wellington had to be dropped as GoWB was unable to provide the required land on the surface. Work at Howrah Maidan have started in March 2016. The section between Howrah Maidan metro station and Esplanade metro station has been built by Afcons – Transtonnelstroy JV team, two tunnel boring machines from Herrenknecht are being used to dig the tunnel. This section passes through the Hooghly river for a distance of 520 meters. The section under the river is at a depth of 30 meters whereas the average roof to ground distance is 17 meters. The Howrah metro station on the west side of the river will be at a depth of 30 meters. Tunnelling started from Howrah Maidan side. On 23 May one of the TBM named Rachna completed the tunneling under the Hoogly river in 36 days. The other TBM named Prerna also completed the tunnelling work under the river on 21-June-2017. There were some concerns during tunnelling under Brabourne Road as the tunnel would pass within 100 meters of heritage structures and there were also many old and dilapidated buildings in this section. KMRC received permission from Archaeological Survey of India in June 2017. Residents and shops in the old building were temporarily shifted and the buildings were reinforced before construction of tunnel. Construction of tunnel till Mahakaran station was completed in November 2017. For the Mahakaran-Esplanade section tunnelling of one of the tunnel have been completed on 23 March 2018 the other tunnel have also been completed by April. In this sections also shops and residents of the buildings have been shifted in phased manner before tunnelling. The Esplanade - Sealdah section will be executed by ITD-ITD Cementation JV and was scheduled to start in May 2018. Work is being done at Howrah Maidan metro station 5490 meters of tunnel have been constructed between Subhash Sarovar and Sealdah. This section was constructed by ITD-ITD Cementation JV. All the cross passes between the two tunnels have also been completed. Track laying is being carried out in this section. Currently the tunneling work has been stopped due to collapse of building on 3 September 2019 over the Bowbazar area due to TBM hitting an aquifer.
Timelines
2009: Contract for building the underground section from Subhash Sarabor to Central Station awarded to ITD-ITD Cementation JV.
2009: Physical Construction of EW corridor starts.
2010: Contract for building the underground section from Central to Howrah Maidan awarded to Afcons.
2012: Realignment proposed to avoid shifting of 80 families from Bowbazar and hawkers from Brabourne Road.
2015: Realignment approved by Railways and JICA in between Sealdah to Howrah station.
2015: Subodh Mullick Square station, a key stop in the revised blueprint, done away with to avoid eviction of hawkers.
2017-March: Afcons nicknames the tunnel boring machine as Prerna and Rachna inspired from the names of daughter of their employee.
2017-May 23: First TBM completes tunneling the East bound tunnel under the Hoogly river.
2017-June 21: Second TBM completes tunneling the West bound tunnel under the river Hoogly.
2017-June: Permission received from Archaeological Survey of India for construction of tunnel within 100 meters of three heritage buildings.
2017-July: Tram depot at Esplanade shifted to facilitate construction of Metro Station.
2017-July: People from 11 buildings in Brebourne Road evacuated in phased manner when the TBM's passes below these old buildings.
2017-August: Mini-bus stand at Mahakaran shifted to facilitate the construction of underground station.
2017-December: Tunnelling between Mahakaran station and Esplanade station on going.
2018-March 23: First TBM named Prerna reaches Esplanade station completing the section from Howrah Maidan to Esplanade. This tunnel will be used by Howrah bound tunnel.
2018-Apr 5: Second TBM named Rachna completes boring of second tunnel between Howrah Maidan and Esplanade station.
2019-Apr 14: Tunneling stopped due to lack of muck cars, and needed to be upgraded. Work started again after 5 days.
2019-Jun 23: TBMs Rachna & Prerna, after being parked at Curzon Park for few months, are finally being taken out.
2019-July 3: Both the TBMs are successfully taken out and loaded on trailers. With this, Rachna and Prerna's journey of tunneling under a river comes to an end.