Emerald Solar Park


Emerald Solar Park is a photovoltaic solar power station near Emerald in Queensland, Australia. It was developed by RES Australia who then sold it to Lighthouse Solar Fund. It delivers up to 72MW of electricity to the National Electricity Market. The entire production of the solar farm is contracted to be supplied to Telstra.

Construction

Construction of the solar park began in October 2017. The prime contractor for construction was RCR Tomlinson under an EPC arrangement. RCR went into administration in November 2018 just prior to facility completion and full production was delayed until February 2019. ENcome Energy Performance have been appointed as O&M contractor with RES Group as Asset Managers.