Fehmarn Belt Fixed Link
The Fehmarn Belt Fixed Link is a planned immersed tunnel that is proposed to connect the Danish island of Lolland with the German island of Fehmarn, crossing the wide Fehmarn Belt in the Baltic Sea, providing a direct link between northern Germany and Lolland, and from there to the Danish island of Zealand and Copenhagen, becoming the world's longest road and rail tunnel, potentially a major connection between central Europe and Scandinavia, and shortening the travel time between Lolland and Fehmarn from 45 minutes by ferry to 10 minutes by car and seven minutes by train. The electrified high-speed rail will be capable of reaching 200 km/h.
The tunnel will replace a heavily traveled ferry service from Rødby and Puttgarden, currently operated by Scandlines, a route known in German as the Vogelfluglinie and in Danish as Fugleflugtslinjen.
Fehmarn is connected with the German mainland by the Fehmarn Sound Bridge, and Lolland is connected by a tunnel and bridges with Zealand via the island of Falster, which in turn is connected with the Swedish mainland via the Øresund Bridge. Although there is also a fixed connection between Zealand and Germany, via the Great Belt, Funen, and Jutland, the Fehmarn Belt Fixed Link would provide faster and more direct road and rail route from Hamburg to Copenhagen, Sweden, and Norway, comprising a four-lane motorway and two electrified rail tracks.
Bridge proposal
Initially, a bridge was proposed. Feasibility studies had been carried out in the late 1990s, and from as early as 2000 German and Danish transportation engineers were actively planning a fixed link bridge across the Fehmarn Strait, carrying both a four-lane highway and two electrified rail tracks. This solution was for years regarded the most likely scheme and detailed plans were drawn up. The Fehmarn Belt bridge was originally expected to be completed by 2018,However, in late 2010, after further feasibility studies, the Danish project planners declared that an immersed tunnel would instead present fewer construction risks and would cost about the same.
The bridge would have been about long, comprising three cable-stayed spans. The four pillars in the substructure of the bridge would probably have been about tall, with vertical clearance about above sea level, allowing ocean-going ships to pass beneath it. The design of the bridge links was being carried out by the Dissing+Weitling company for its aesthetical features and by the COWI and Obermeyer companies for their civil engineering aspects. The proposed design would have carried four motorway lanes and two railway tracks.
Tunnel solution
Although originally conceived as a bridge, Femern A/S announced in December 2010 that a tunnel was preferable, and the tunnel idea received support from a large majority of the Danish parliament in January 2011. By 2012, therefore, the completion date had been pushed back to 2021, and in 2014 was estimated to be 2024, and then in 2015 delayed further to 2028.In February 2015, the draft bill for the construction was introduced to the Danish parliament, and the Danish government submitted an application for DKK 13 billion in EU grants, supported by Germany and Sweden. In June 2015, €589m of EU funding was awarded to Denmark by the European Commission under its Connecting Europe Facility scheme, allowing the tunnel project to go ahead. In March 2017 the operating company announced the sign-up of subcontractors for the project.
in the Danish–German motorway system On 13 December 2018, the European Court ruled in favour of Scandlines in case T‑630/15 regarding state aid.
The Commission has claimed on September 28, 2018, that there has been no unlawful aid. Action regarding this has been brought before court in January 2019, case number T-7/19.
Project
This project is comparable in size to that of the Øresund Bridge or the Great Belt Bridge. According to a report released on 30 November 2010 by Femern A/S, the company tasked with designing and planning the link between Denmark and Germany, the corridor for the alignment of the link has now been determined and will be sited in a corridor running east of the ferry ports of Puttgarden and Rødbyhavn.The Fehmarn Belt Fixed Link and its double-tracks will shorten the rail journey from Hamburg to Copenhagen from four hours and 58 minutes to three hours and 15 minutes. According to current plans there will be one passenger train and two freight trains in each direction per hour. Hence, there will probably be congestion and delays on the German side of the bridge, with this much traffic, if the track widening is delayed. The highway between Copenhagen and Hamburg is already a motorway except for in Germany. The rest is a two-lane expressway. The highway will be widened to a motorway except where it meets the Fehmarn Sound bridge.
Financing
When the Danish Folketing ratified the project in March 2009, its cost was estimated at 42 billion DKK. This cost included €1.5 billion for other improvements such as electrifying and improving of railway from single-track to double-track on the Danish side. In 2011 this was increased to a total of €5.5 billion. On top of this there will be cost of at least €1 billion for the German rail connection which will be paid by the German government. An expected EU subsidy of between €600 million and €1.2 billion will be given. Construction estimates cover the period from 1 April 1998 until the opening of the fixed link in 2021, a timing which has been postponed.The Fehmarn Belt Fixed Link will be financed by state-guaranteed loans, which will be paid by the road and train tolls. Denmark will be solely responsible for guaranteeing the funding of the project at an estimated cost of 35 billion kroner or and German participation will be limited to the development of the land-based facilities on the German side. The government of Denmark will own the fixed link outright, will be allowed to keep tolls after the loans have been repaid, and will enjoy any employment opportunities at the toll station. The fees are also planned to pay for the Danish railway upgrading.
On the German side, the road will be upgraded to four lanes and the railway to double track and, according to the treaty, paid by the German tax payers rather than by user tolls.
The European Union has designated this project as one of the 30 prioritised transport infrastructure projects and will support the project with a contribution, probably around 5–10%, amounting to an expected €600 million to €1.2 billion. The project is expected to have 5% rate of return for Europe.
New Storstrømmen and Fehrmarn Sound links
New links at the Fehmarn Sound and Storstrømmen are planned. According to the 2008 Danish–German treaty, the bridges did not have to be replaced, and the double-track railway construction in Germany may be delayed by up to seven years. But a replacement of the Storstrøm Bridge has been contracted and is slated for completion in 2022, while the Schleswig-Holstein state government announced in 2013 it envisioned the construction of a new Fehmarn Sound link or an upgrade of the current Fehmarn Sound Bridge, since it considered the current bridge – with two lanes for road traffic and one track for rail traffic – to be a bottleneck for the German hinterland connection. On 3 March 2020, the German Federal Ministry of Transport, the State of Schleswig-Holstein and Deutsche Bahn announced that a new 1.7 km long immersed Fehrman Sound Tunnel with four road lanes and two rail tracks, costing approximately 714 million euros, will be built by 2028, while the current bridge will be preserved for pedestrians, cyclists and slow road traffic.Railway axis Fehmarn Belt
The Fehmarn Belt Tunnel's railway is the central section of the 'Railway axis Fehmarn Belt', which is Priority Project 20 of the Trans-European Transport Network that seeks to establish a high-speed rail line Copenhagen–Hamburg. In the north, it connects to the Øresund Bridge/Drogden Tunnel and the Nordic Triangle railway/road axis, and in the south to Bremen and Hanover. The full line currently under construction consists of several new railways to be built and old railways to be upgraded to achieve at least a maximum speed of 200 km/h on all sections:- Copenhagen–Ringsted Line, opened on 31 May 2019, currently operating at 180 km/h, upgrading to 250 km/h in 2023
- Sydbanen, new tracks to be laid by 2021, to be electrified to reach 200 km/h by 2024
- Fehmarn Belt Tunnel, 200 km/h, to be completed in 2028
- Puttgarden–Lübeck railway, to be electrified to reach 200 km/h up from the current 160 km/h. The new Fehmarn Sound Tunnel is part of this section.
- Lübeck–Hamburg railway, to be upgraded to reach 200 km/h
Tunnel characteristics
The Fehmarn Belt will be crossed by an immersed tunnel, at the planned, it will be the longest ever constructed, and will surpass the Marmaray Tunnel of the Bosphorus, Turkey. On 30 November 2010, Denmark's Femern A/S project manager announced it had selected immersed tunnel design submitted by the Ramboll, Arup, and TEC consortium. According to the senior project managers, as well as being the world's longest immersed tunnel, it will be the world's longest combined road and rail tunnel; the world's longest under water tunnel for road; the deepest immersed tunnel with road and rail traffic; and the second deepest concrete immersed tunnel. The size of the project is about five times the tunnel part of the Øresund Link between Denmark and Sweden, currently the longest immersed concrete tunnel.
The deepest section of the Fehmarn Belt Trench is and the tunnel sections will be about high, thus the dredging barges will need to be capable of reaching depths of over. Dredging will produce a trench some wide and deep. These parameters give a total of some of soils to be dredged. Conventional dredging equipment can only reach to a depth of about. To excavate the middle portion of the Fehmarn trench – deeper than below the water's surface – will likely require grab dredgers and trailing suction hopper dredgers.
The proposed tunnel would be long, deep below the surface of the sea, and would carry a double-track railway. Arguments brought forward in favour of a tunnel include its starkly reduced environmental impact, its independence from weather conditions, as crosswinds can have considerable impact on trucks and trailers, especially on a north–south bridge. A bored tunnel was deemed too expensive.
The precast concrete tunnel sections will have a rectangular cross-section that is about wide and high, containing four separate passageways, plus a small service passageway: There will be separate Northbound and Southbound tubes for vehicles, each wide, each with two travel lanes and a breakdown lane; while the Northbound and Southbound passageways for trains will be wide each and about high; the service passageway will be wide; the standoff space between each "tube" will vary, but the overall width will be. The single-level, sectional arrangement of the two road and rail tubes side-by- side – with the road West and the railway East – coincide with the arrangement of the existing road and rail infrastructure and requires no weaving to connect.
Project history
- On 29 June 2007 an interim agreement was reached in Berlin between the Danish and German authorities to proceed with the construction of the fixed link. Details provided by Danmarks Radio stated that the Fehmarn Belt Fixed Link would run from a point about east of Rødby in Denmark to Puttgarden on the island of Fehmarn which was already connected by bridge to the German mainland. Construction would start in 2015 and was expected to be completed by the end of 2021.
- On 3 September 2008, the ministers of transportation from Denmark and Germany, Carina Christensen and Wolfgang Tiefensee, signed the treaty for the construction of the Fehmarn Belt Fixed Link at a ceremony held in Copenhagen. On 26 March 2009 the construction was ratified by the Danish parliament, and the German parliament approved the scheme on 18 June 2009.
- In December 2010, it was announced that a tunnel would be used rather than a bridge, as this would present fewer construction risks than a cable-stayed bridge that would be pushing the limits of the technology. The cost and the construction time would be roughly the same.
- In January 2011, a large majority of the parties in the Danish Parliament voted to support a tunnel solution. However, national approval procedures in both countries needed to be completed and, in Germany, this involved the application for a plan approval process. In Denmark, the project would require the passage in parliament of a Construction Act.
- On 16 December 2011, the German government announced it was postponing development of the railway link to the Fehmarn Tunnel until after 2015. According to a report in Der Nordschleswiger, German Traffic Minister Peter Ramsauer had decided to reduce planned government investment in new infrastructure in Germany by 25 per cent due to the economic crisis. It was not immediately clear what effect the postponement would have on the overall Fehmarn Belt Fixed Link project.
- In October 2013, the tunnel company applied to German authorities for approval according to environmental law and other laws of Germany and EU. This was rejected in 2015 because new legislation that appeared in the meantime wasn't accounted for.
- On 25 February 2015, the bill for the Construction Act for the Fehmarnbelt link was introduced in the Danish parliament.
- On 26 February 2015, the Danish Ministry of Transport submitted an application for an EU grant of DKK 13 billion for the project's construction phase. The application was accompanied by letters of support from the Swedish Minister for Infrastructure, Anna Johansson, and the German Transport Minister, Alexander Dobrindt. In addition, the German state government of Schleswig-Holstein as well as a wide range of business organisations from the Danish, Swedish, and German sides sent statements supporting the application. EU finally approved DKK 6.92 billion in total for the tunnel and the connecting Danish railway, around 15% of the cost. Further support can be expected for the German connecting railway and in general after 2021.
- On 13 June 2016, the tunnel company applied again to German authorities for approval, based on an updated application of 11,000 pages adopted to new legal principles that appeared since last application. It is expected that this process is ended in 2018. It expected that two further years will be spent in court processes, since political objectors have stated they will appeal the authority approval.
- On 28 December 2018, the German authority decided to approve the project.
- On 6 February 2019, Femern A/S received German plan approval for the tunnel. This has been appealed to the Federal Administrative Court by political objectors.
- February 2019: DB Netz AG submits a document to the BMVI detailing variants of the rail connection to the tunnel. The approval process for the railway will need approval by the German national parliament.
- In March 2019 Femern A/S decided on government request to start large preparatory work on land, such as building a factory for concrete tunnel elements., in anticipation of a positive German court decision later.
- On 3 March 2020, the German Federal Ministry of Transport, the State of Schleswig-Holstein and Deutsche Bahn announced that a new 1.7 km long immersed Fehrman Sound Tunnel with four road lanes and two rail tracks, costing approximately 714 million euros, will be built by 2028, while the current Fehmarn Sound Bridge, which was at risk of becoming a bottleneck, will be preserved for pedestrians, cyclists and slow road traffic.
- On 30 April 2020 it was announced by Femern A/S that work is scheduled to begin in 1 January 2021, although it is possible this will be delayed due to the effects of the global Covid-19 pandemic. Femern has already begun a number of preconstruction activities at Puttgarden, Germany.
Criticism
There have been objections from local people in Germany, both from those fearing the loss of jobs in connection with the present busy ferry traffic, and from environmental protectionists who believed that wildlife would suffer from the construction of the originally conceived bridge, and that residents would suffer from the increase in traffic, especially the planned freight trains which would move from the present Greater Belt–Schleswig route.
Despite an offer to help offset the costs of the tunnel by the Danish Cyclists' Federation, it is not planned to include a cycle path.
Social concerns
Detractors believe that the construction of the fixed link and the resulting shift of cargo transport away from the existing ferry would mean a radical decrease in ferry operation and the loss of jobs. At the same time, employment connected to construction works would be only short-term. Furthermore, it is claimed that the project might be economically unjustified, as predictions of passenger traffic and goods transport may be overestimated and there is a considerable risk that the investment will not be recouped. Some suggest that the original plans were drawn up during the Cold War and that since then traffic flow has changed profoundly, meaning that construction of a fixed link is no longer justified.There is also criticism on the increase of noise for some residents and visitors when moving the freight train traffic from the Jutland-Schleswig route to this route. These critics have been the loudest and they have been able to get a realignment of the planned railway route.