Guru Nanak Dev Thermal Plant
The Guru Nanak Dev Thermal Plant at Bathinda was one of the three thermal power stations in Punjab.
It was a medium-sized power station with four units that were begun to be built in early 1970s and completed in 1982. All total generate up to 460 MW of power that meets the mammoth irrigation needs of lower Punjab. Having generated electricity for 43 years to meet the power demand of punjab, the thermal shut down forever on September 27,2017.
The plant was named after the first guru and founder of Sikhism, Sri Guru Nanak Dev Ji.Capacity
It had an installed capacity of 440 MW. All four units ceased operations in September 2017
Unit No. | Generating Capacity | Commissioned on | Status |
1 | 110 MW | 1974 September | closed |
2 | 110 MW | 1975 September | closed |
3 | 120 MW | 1978 March | Closed |
4 | 120 MW | 1979 January | Closed |