HVDC Rihand–Delhi


The HVDC Rihand–Delhi is a HVDC connection between Rihand and Dadri in India, put into service in 1990.
It connects the 3,000 MW coal-based Rihand Thermal Power Station in Uttar Pradesh to the northern region of India. The project has an long bipolar overhead line. The transmission voltage is 500 kV and the maximum transmission power is 1,500 megawatts. The project was built by ABB.
On 24 June 1990, during the commissioning of the scheme, a complete quadrivalve of the Rihand converter station was destroyed, and the other two quadrivalves of the same pole badly damaged, by a fire which is believed to have started as a result of a loose connection on a grading capacitor. The fire was so intense that the valve hall was structurally damaged, and the affected converter was out of action for 18 months. Similar incidents on the Itaipu project in 1989 and the Sylmar Converter Station of the Pacific DC Intertie scheme in 1993 led to CIGRÉ publishing guidelines on the design of thyristor valves in order to reduce fire risks.
HVDC Rihand-Dadri crosses north of E. Manjhpati the HVDC Ballia-Bhiwadi. This is the first crossing of two independent HVDC lines in India and one of the few worldwide.

Sites

SiteCoordinates
Rihand Converter Station
Chak Chapki Grounding Electrode
HVDC Rihand-Dadri crosses HVDC Ballia-Bhiwadi
Dadri Converter Station
Nanva Ka RajPur Grounding Electrode