Horden railway station


Horden is a railway station on the Durham Coast Line, located in the village of Horden, County Durham. The station opened on 29 June 2020, following a £10.55 million investment. It is the second station to have been located in the village, it having replaced an earlier station, located approximately further south, which closed in May 1964. Upon opening, it replaced Worcestershire Parkway as the newest station on the National Rail network.

History

The original station at Horden was opened by the North Eastern Railway on 1 April 1905. The station opened as part of the NER's project to build a new coastal line by linking together and on the routes of the earlier Londonderry, Seaham & Sunderland and Hartlepool Dock & Railway lines. This new line had been constructed primarily to avoid the steep gradients of the inland route at Seaton Bank and Hesleden Bank, but also provided access to the newly developed collieries of the Durham Coast.
A six-inch Ordnance Survey map from 1922 shows the station, along with a station hotel, located at what was then the southern end of the new settlement, which was built to house workers from the nearby Horden Colliery.
The new town of Peterlee was established in 1948, and is located about to the west of Horden; hence, at the time, Horden had been the closest railway station to the town. Despite the development of this new town, however, the station was recommended for closure, as part of the Beeching Report, and was duly closed on 4 May 1964, along with other remaining stations at and.

Reopening

It had been a long-held ambition of Durham County Council to reopen a station on the Durham Coast Line between Seaham and, to serve the communities of in the county's south east. The council investigated seven potential sites in the area, initially selected a site adjacent to the Sea View Industrial Estate in Horden as the most suitable for a new station. The site was located about to the north of the original station.
It was identified that one of the key benefits of reopening Horden, as opposed to any of the other closed stations on the Durham Coast Line was the station's close proximity to Peterlee, which has grown significantly since 1964. This allowed the potential for 61,000 residents to benefit from improved access to employment opportunities across the region. Durham County Council had applied for funding from the first round of the Department for Transport's New Stations Fund in 2013, but were unsuccessful at that stage.
In September 2016, Durham County Council the original plans were revised and a new preferred site was identified at South East View, Horden, and a public consultation was launched, in order to gauge the potential usage of a reopened station. This site is located about from the original station, significantly closer than the earlier proposal.
In July 2017, it was announced that the station would be built with a contribution of £4.4 million in funding from the second round of the New Stations Fund, with the remainder of the scheme's £10.5 million cost being covered by funding which has already been provided by Durham County Council and the North East Combined Authority. Network Rail submitted a planning application for the new station on 1 November 2018, and this was duly approved on 7 January 2019.
The first stage of construction work for this project, involving the creation of the station car park and adjacent bus stop, commenced on 28 May 2019. It was later followed by the construction of the station itself, as well as associated signalling and track realignment works, in the second stage. In late April 2020, having completed both platforms, the station's footbridge and associated ramps and stairs were installed by Story Contracting, using a 500 tonne crane. Following this, work progressed through mechanical, electrical and telecoms works and, finally, interface works between the station and car park.
The station opened on 29 June 2020. It had originally been expected to be open in March 2020, but this was later revised to May 2020. This May 2020 opening date was also missed owing to a requirement to adjust working practices in response to the COVID-19 pandemic.

Services

The station is served by an hourly service between Nunthorpe and Hexham, operated by Northern Trains.

Facilities

The station has two platforms, both of which have ticket machines, seating, waiting shelters, next train audio and visual displays and an emergency help point on both platforms. The platforms are linked by an accessible footbridge. There is a car park with 139 spaces, as well as facilities for drop-off, a taxi rank and a bus stop. The station is part of the Northern Trains penalty fare network, meaning that a ticket, or "promise to pay" notice is required prior to boarding.