Hotgi Junction railway station


Hotgi Junction is a railway junction station under Solapur Railway Division of Central Railway zone of Indian Railways located at Hotgi, suburb of Solapur.

History

In 1881 the Bombay Eastern Deccan Railway was under construction with William Michell the Engineer-in-Charge. This line immediately upon opening became the Bijapur Branch of the Southern Mahratta Railway.
The Southern Mahratta Railway was founded in 1882 to construct a metre gauge railway between Hotgi and Gadag, one of the "famine lines" set up with a guarantee.

Established

The Hotgi railway station was opened in 1884, when the Southern Mahratta Railway started to build meter gauge railway line between Hotgi and Gadag in 1882, which was completed in the year 1884.

Development

Gadag-Hotgi Rail Doubling is sanctioned in the year 2014-15 Doubling for part length of this project, i.e. from Hotgi-Kudgi is taken up under Customer Funding Model. For this purpose NTPC have deposited Rs.946 cr. with Railway.
New Crossing station @ Kudgi with 4 lines for giving connectivity to NTPC was commissioned on 29.01.2017.
Work is in progress in the section between Minchinal-Lachyan is targeted for commissioning during 2017–18.

Services

It connects to Solapur Junction on north-west direction, Gulburga and Wadi Junction on South-East direction, Bijapur and Gadag Junction on south direction.

Lines

The Hotgi-Gadag railway line was metre gauge and converted to broad gauge in stages. The conversion was finally completed in December 2008. Now Hotgi is connected to Hubli and Hospet by direct trains. Bangalore-Solapur train now runs via Bijapur and Hotgi.