IHNC Lake Borgne Surge Barrier


The Inner Harbor Navigation Canal Lake Borgne Surge Barrier is a storm surge barrier constructed near the confluence of and across the Gulf Intracoastal Waterway and the Mississippi River Gulf Outlet near New Orleans. The barrier runs generally north-south from a point just east of Michoud Canal on the north bank of the GIWW and just south of the existing Bayou Bienvenue flood control structure.
Navigation gates where the barrier crosses the GIWW and Bayou Bienvenue can be worked to reduce the risk of storm surge coming from Lake Borgne and/or the Gulf of Mexico. Another navigation gate has been constructed in the Seabrook vicinity, where the IHNC meets Lake Pontchartrain, to block a storm surge from entering the IHNC from the Lake.

Purpose

The Inner Harbor Navigation Canal surge barrier was authorized by Congress in 2006. The barrier is designed to reduce the risk of storm damage to some of the region's most vulnerable areas - New Orleans East, metro New Orleans, the 9th Ward, and St. Bernard Parish. This project aims to protect these areas from storm surge coming from the Gulf of Mexico and Lake Borgne.

Status

The project was funded by the American Recovery and Reinvestment Act of 2009. In April 2008, the Corps awarded a construction contract to Shaw Environmental & Infrastructure for the Lake Borgne Surge Barrier, making this project the largest design-build civil works project in Corps history. It is highly unusual for a civil works project to be designed and constructed simultaneously. The expedited process was necessary, however, given the compressed time frame for achieving the 100-year level of risk reduction in 2011.
In October 2008, the New Orleans District Commander of the U.S. Army Corps of Engineers signed the Tier 2 portion of the Individual Environmental Report, which investigated alternative alignments and designs within the location range identified by Tier 1 and explained the impacts of these alignments and footprints, construction materials and methods, and other design details. After the completion of the IER, a Notice to Proceed was issued to Shaw.
In December 2008, the Corps held a groundbreaking ceremony to mark the start of test pile driving. Construction of the barrier's flood wall began on 9 May 2009. On 21 October 2009 the last of the 1,271 main piles was driven.
On 29 August 2012, the barrier was used for the first time, to protect the city from Hurricane Isaac. By June 2013, all major construction had been completed.

Construction

The COE accomplished this project via the design-build delivery method. The main barrier consists of 1,271 concrete piles across and long, weighing 96 tonnes each. Behind those piles, steel piles are driven at an angle of 2 horizontal to 3 vertical. The steel piles are 288 feet long and are installed in two sections, with the lower 158-foot section driven and the upper 130-foot section fitted on top and welded in place. A precast concrete pile cap is placed on top of the steel batter piles and concrete plumb piles to join them.
Two gates were constructed in the Gulf Intracoastal Waterway navigation channel. One gate is closed with two sector gate leaves, the other gate with a barge swing gate, comparable to a caisson. In the Bayou Bienvenue navigation channel, a vertical lift gate was installed for use with recreational craft and shrimpers.

Features

CJ. MAHAN provided the detailed designs and drawings for