Ion rapid transit


Ion, stylized as ION, is an integrated public transportation network in the Regional Municipality of Waterloo in Ontario, Canada. It is operated by Keolis and is part of the Grand River Transit system, partially replacing GRT's Route 200 iXpress bus service. The section of Route 200 serving Cambridge has been renamed "Ion Bus". The first phase commenced operations on June 21, 2019, between the north end of Waterloo and the south end of Kitchener. A future extension of light rail to the downtown Galt area of Cambridge is planned but construction may not begin on that line until 2025.
In 2009, an Environmental Assessment began to create a proposal of electrically-powered light rail transit through Kitchener and Waterloo, and adapted bus rapid transit from Kitchener to Cambridge. On June 24, 2009, Regional Council voted to approve the project, subject to funding from higher levels of government, which was in turn approved by council on June 15, 2011. This was followed by a community building strategy to guide development, identify key destinations, and strengthen regional connections. The strategy, led by Urban Strategies Inc. of Toronto, consulted hundreds of individuals and stakeholders from Cambridge, Kitchener, and Waterloo.
Construction began in August 2014 and service was expected to begin in late 2017; however, because of delays in the manufacture and delivery of rolling stock, the introduction of the light rail service was significantly delayed. The total cost of the system was estimated at $818 million, but in December 2017, the overruns were estimated to total approximately $50 million. The Province was expected to provide $25 million of that amount.

Etymology

According to the Region of Waterloo, the Ion network is named after the atom, which it describes as being “always in motion”.

History

In 2004, the Regional Municipality began an Individual Environmental Assessment to study the feasibility of constructing a rapid transit line to provide higher-order public transit service to the Region and to encourage more compact urban growth along the corridor.
The EA took a broader approach to studying possible routes and stations for the rapid transit line, examining several options such as utilizing existing tracks/roads and constructing new facilities. In keeping with legislation, the Environmental Assessment also examined ten possible transport technologies, including monorails and subways.
The EA as planned consisted of three phases:
Phase 1: Determine a preferred transportation strategy from options such as road expansion, improved conventional transit, and rapid transit. Phase 1 was completed in July 2006.
Phase 2:
Phase 3: Design an implementation plan for the rapid transit system.
In June 2008, the Province of Ontario announced a new expedited Transit Project Assessment Process. In August 2008, the Region notified the Ministry of the Environment to advise that the it would transition from the Individual Environmental Assessment to the expedited process. For that reason, Phase 3 of the Individual EA would not be completed.
On June 24, 2009, Regional Council approved the initiative and continued discussions with Provincial and Federal governments to obtain funding for the $790-million project. Light Rail Transit was short-listed as the technology for the new rapid transit system. The Region decided on a staged approach, building light rail from Conestoga Mall to Fairview Park Mall, passing through Uptown Waterloo and Downtown Kitchener on the way. Adapted Bus Rapid Transit would be built from Fairview Park Mall to Ainslie Street terminal in Cambridge utilizing shoulder bypass lanes along Highways 8 and 401 during heavy traffic where speeds are often 40 km/h or less. As of June 2019, there is still no specific timeline for replacing the aBRT service to Cambridge with light rail.

Approved light rail system

On June 24, 2009, Regional Council approved LRT as the technology for rapid transit in Waterloo Region. Regional Council also approved a recommendation to implement the system in stages because ridership, development potential and capital and operating costs vary along the route.
The light rail system was approved by Regional Council with a vote of 15–1. Cambridge mayor Doug Craig cast the dissenting vote. Other Cambridge-area representatives joined Craig in voting against subsequent motions on the service's staging, feeling that running only buses to that city does them a disservice.
The Province of Ontario had promised to fund up to two thirds of the cost of the construction of a light rail or bus rapid transit system in Waterloo Region.
However, in the summer of 2010, actual funding commitments from higher levels of government for the combined LRT and aBRT system were announced: $300 million from the province of Ontario, and $265 million from the federal government. The provincial figure was disappointing to supporters, as the provincial government had previously promised to pay 2/3 of the cost. Regional council debated funding the remaining $200–300 million required for the project to go ahead as planned.
During public consultation for the project, concerns related to the light rail proposal focused on its relative service infrequency when compared with rapid transit systems in other cities ; the projected service frequency will be approximately 7.5 minutes. In addition, a light rail line would be limited by the narrow main streets of key downtown areas. A feasible proposal raised by the Region for dealing with this challenge would be to have light rail vehicles share space with traffic within core areas, somewhat resembling the traditional streetcar networks of many European cities, and of nearby Toronto. A bus rapid transit line would also face the challenge of the cramped core areas, and thus would also likely share space with traffic in core areas.
In late 2011, planning was well underway and preparations were being made. In October, a property on Dutton Drive in Waterloo, bordering the rail-line corridor where the LRT is planned to be installed, was purchased to serve as a maintenance and storage yard for the system's LRVs. The site, which was purchased for $6 million, will contain three buildings: the largest is and will house the operations centre and a repair shop; one will include a washing system; and the third is a wayside maintenance building that will house the repair truck fleet.

Vehicles

On July 10, 2013, it was reported that a deal was finalized with Metrolinx to join its contract with Bombardier Transportation for the purchase of 14 Flexity Freedom LRVs to form the system's initial fleet, with an option to purchase up to 14 more as the need arises.
A further report on July 12, 2013 stated that the region would be purchasing 14 LRVs, with an option to buy 16 more.
The 14 vehicles are estimated to cost $92.4 million, an average of $6.6 million per vehicle. The cost breakdown is:
Each 30 metre long, 30 tonne, vehicle has 56 seats and a standing capacity of 144 passengers. The body is constructed of five sections, in an accordion-like configuration to allow for making sharp turns. It can be driven from either end. The top speed is 88 km/h but the average travel speed is unlikely to exceed 50 km/h.
The vehicles are numbered with a three digit unit number in the 5xx series beginning with 501. This fleet number is displayed prominently on the end modules of each vehicle followed by a single letter to denote which end module the fleet number is on. The vehicles are being used for testing at the maintenance facility and all 19 km of the completed track.

Vehicle delivery and testing

Production of the new vehicles was expected to begin in 2015 with the first to be delivered no later than August 2016 and all vehicles were to be received by the end of 2016. On April 13, 2016, it was reported that Bombardier had informed the transit authority that delivery of the vehicles would be delayed.
The region entered a joint agreement with Metrolinx and Bombardier in July 2013 for 14 LRVs, as well as an option to buy up to 14 more. Under the original agreement, the first vehicle was to be delivered no later than August 2016, and the 14th by December 2016.
On May 20, 2016, Bombardier announced that to avoid further delays it would shift construction of the vehicles for the Ion system from its Thunder Bay plant to another plant in Kingston, Ontario.
The first vehicle, number 501, arrived in Waterloo Region on February 24, 2017. However, it was not ready for testing as its operating software was incomplete. By mid-March 2017, the second to fifth vehicles were seen by a CTV reporter as under construction in the Kingston plant. Testing of vehicle 501 was scheduled to commence in May 2017 on the line between Northfield Drive and Silver Lake.
In early April 2017, the Region expected to receive a second LRV in June or July, but that was postponed to late August or early September. By the beginning of October 2017, the second LRV had arrived. The schedule then called for delivery of another each 15 days, for a total of 14 by year end. The year end target was missed.
On November 7, 2017, unpowered vehicle testing began on the tracks between Northfield Drive and Erb Street. An LRV was towed to check track clearances including along station platforms and to ensure continuous pantograph contact with the overhead electrical wiring.
On December 19, 2017, GrandLinq had its first successful test of a Flexity Freedom running under its own power at the Ion maintenance facility. The two-hour test was done at the speed of and "apparently went quite well", according to Coun. Tom Galloway. In 2018, testing beyond the maintenance facility was scheduled to start. By this date, Waterloo Region had three LRVs on site, which is the minimum number required to do an adequate test of the system.
A CBC report on December 21, 2017, indicated that the fourth vehicle was expected to be delivered before year end. Six others were in final production and four were still in the assembly process. After the fourth vehicle was received in January, the first one was returned to Kingston for some additional work. At that time, five others were being tested by Bombardier. According to the schedule, the fourteenth and last LRV was expected to be delivered in February 2018 with full LRT service expected to start in spring 2018; however, this later became a June final delivery, with service start in December, then later to June 21, 2019. The final LRVs were delivered on December 6, 2018.
At a Regional council meeting on May 8, 2019, it was announced that the service would launch the following month, on June 21, 2019; service across all of Grand River Transit, both LRT and bus, was to be free of charge for eleven days, until Canada Day.

Facilities

The Ion fleet is stored and maintained at the Ion Operations, Maintenance and Storage Facility located on Dutton Drive in Waterloo.
The design of each of the stops was focused on an 'anchor wall', a square panel subdivided into smaller tiles of glass, ceramic or stone; each station has a unique wall design based on the surrounding architecture, landmarks and social character.

Operations

Ion light rail vehicles are in service between 5am and 1am daily with a frequency of every 8 minutes during rush hours and every 10 to 15 minutes at other times. The route is properly known as 301 Ion Light Rail.
The maximum operating speed of Ion light rail vehicles is along city streets and along railway rights of way. However, in areas where there is high pedestrian traffic, the operating speed will be as low as. The trip from Conestoga Mall to Fairview Park Mall is scheduled take about 46 minutes for an average speed of about. As a comparison, the average speed of Toronto's light rail Line 5 Eglinton will be and the average speed of subway Line 2 Bloor–Danforth is. Note that while Ion operates completely on the surface, Line 5 is half underground, and Line 2 is completely road-separated.
At street intersections, Ion light rail vehicles do not use the traditional automotive green-yellow-red traffic signals for road traffic, but rather the traditional two-aspect transit signals that show a vertical white bar for "go" and a horizontal white bar for "stop". Ion light rail vehicles have transit signal priority at intersections.
Where a street crosses the Ion tracks located either along a railway right of way or along the side of a cross road, the crossing is protected by traditional railway crossing signals: drop gates, flashing red lights and a bell. Crossings so protected are at Northfield Drive, Bearinger Road, Columbia Street, University Avenue, Seagram Drive and Erb Street in Waterloo, and at Ottawa Street, Mill Street, Hayward Avenue, Block Line Road, Courtland Avenue and Wilson Avenue in Kitchener.

Freight trains

Freight trains from CN use the shared portion of the Waterloo Spur between 1am and 5am when Ion light rail vehicles are not in operation. After crossing King Street, northbound freight trains join the northbound Ion track at Caroline Street, cross over to the southbound Ion track just north of Erb Street and then continue north on the southbound track until just south of Northfield Drive. Southbound freight trains take the reverse path. Since freight cars are wider than the LRVs, there are gauntlet tracks at most of the Ion stations along the Waterloo Spur to keep freight trains from striking the station platforms. To further protect station platforms and also to protect the Ion catenary system, there is a safety system to detect oversized freight cars and automatically stop the train using derailers. The detectors are located at Willow Street and just north of Northfield Drive.

Route

The route approved by Regional Council travels in a mix of on-road and off-road configurations. On December 2, 2017, the Kitchener-Waterloo Record reported the local economy had already been stimulated through the construction of new buildings near the route, in both Kitchener–Waterloo and Cambridge.

Phase 1

On-road sections keep the LRVs in dedicated lanes that do not mix with general traffic.
In February 2017, after limitations in the original route design came to light, a new preliminary preferred route plan was published. This would no longer use the CPR line south of Fairway; instead, it would travel to the east of it, along the River Rd extension and across Hwy 8; along King St into the Sportsworld area and under Hwy 401; along Shantz Hill Rd into Preston, and crossing the Speed River on a dedicated bridge.
The subsequent plan, rejected by Cambridge City Council in July 2017, indicated that the track would take Eagle St toward Hespeler, but to avoid conflicts with rail corridors and reduce traffic impacts at Eagle/Pinebush, would travel along the freight spur to Hespeler Rd. As previously, Hespeler Rd would be followed toward the Delta intersection, but to avoid traffic impacts it would veer east along the rail corridor behind Norfolk Ave, then transition to an abandoned railway corridor behind Grantham and Beverly Sts, before coming into downtown Galt near the Ainslie Terminal. More detailed rendering of the route became available in October 2019, indicating elevated sections would be used to cross Fairway Road, the Grand River, Fountain Street and the Speed River, and the CP Rail line by Eagle Street.

Staging

The Region approved a staged implementation plan for its rapid transit system:
Stage 1 – Implementation of LRT north of Fairview Park Mall and adapted Bus Rapid
Transit south of Fairview Park Mall, including:
The stage 1 route is long.
Stage 2 – Completion of a light rail transit system from Fairview Park in Kitchener to Ainslie Street in Cambridge. Commencement of Stage 2 to follow completion of Stage 1 as closely as possible.

Bids

Out of the seven groups that showed an interest in the project, by December 18, 2013, three consortiums had submitted bids to design, build, finance, operate and maintain the Ion system:
The winning bid was selected at a committee meeting on March 4, 2014. GrandLinq is the preferred bidder. The final approval of the GrandLinq bid came at a full council meeting on March 19, and financial close was made May 9.

Construction

The Region reiterated that Stage 1 rail service would start in "early" 2018.
Because Stage 2 was still years away in March 2017, Grand River Transit was providing rapid transit between Fairview Park Mall and the Ainslie Street Transit Terminal using iXpress buses. Adapted versions would become available in the near future for the Ion bus. Other stops are at Hespeler Road at the Delta, Can-Amera, Cambridge Centre, Pinebush, and Sportsworld. The rapid transit vehicles use bus-only lanes at Pinebush, Munch and Coronation to minimize slowdowns at times of heavy traffic. Following the launch of light rail stage 1, the Ion bus provides a direct link to that system. This bus route is properly known as 302 Ion Bus. That service, termed "adapted bus rapid transit" runs in shared traffic lanes for most of the route, and fares are collected on board. It therefore does not meet the BRT Standard definition of bus rapid transit. No firm estimates had been published as to the possible start of light rail service to Cambridge but a report in early July 2017 suggested that construction would not begin until 2025.

Design

The stations have been built to be the length of two LRVs; however, as only single vehicles are anticipated to be required initially, the major station facilities were only built for a single vehicle length at start. This consists of a cantilevered glass canopy over a mostly open waiting area; enclosures were built at most stations to provide some shelter. Each station is also recognizable by a 'feature wall', a square installation near the end of the platform that carries a distinct colour scheme and pattern. The wall face is a series of large tiles in glass, ceramic or stone; at some stations, all tiles are the same, while others feature a unique pattern. Each wall features illuminated Ion and GRT logos, as well as the station's name set in Clearview. A second wall and canopy can be installed at the opposite end of each platform, and are planned to be erected when two light rail vehicle cars become the norm.
There are ten public art installations within the Ion corridor with artworks at Conestoga, Research and Technology, Grand River Hospital, Kitchener Market, Mill, Block Line and Fairway. A further piece, Fabric of Place by Lilly Otasevic consisting of a panel with imaging representing the fabric of the community, is used as a barrier along the Ion track in Waterloo behind the Albert McCormick Community Centre, on Parkside Drive. Waterloo Region budgeted $875,000 for the artworks.

Stations

StationLocationNotesCoords
West of Conestoga MallMajor transit interchange with connections to GRT and iXpress bus services
Rail corridor at Northfield Dr
Rail corridor near bend in Wes Graham WayNear the David Johnston Research and Technology Park
University of Waterloo main campusacross from Davis Centre along Ring Road / Laurel Trail
Rail corridor at Seagram DriveNear Wilfrid Laurier University and Waterloo Park
Rail corridor at King StNorthbound only
Caroline St south of Willis WaySouthbound only
King St at Allen St
King St at Pine StIn front of Grand River Hospital; near Kitchener–Waterloo Collegiate
King St at Victoria StTransit hub will provide connections to GO Transit, Via Rail, Greyhound and Coach Canada services
Duke St at Young StNorthbound only; near Kitchener City Hall
Charles St at Gaukel StSouthbound only; near Victoria Park
Frederick St at King StNorthbound only
Charles St at Queen StSouthbound only
Charles St at Cedar StNear the Kitchener Farmer's Market and Cameron Heights Collegiate Institute
Charles St at Borden Ave
On the rail line by Ottawa St at Mill St
Courtland Ave at Block Line RdNear St. Mary's High School
West of CF Fairview ParkSouthern terminus linked by Bus Rapid Transit to the Ainslie St. Transit Terminal; Park and Ride facility

Politics

The project has attracted vocal support and opposition.

Support

In May 2009, a Facebook group named "I Support Light Rail Transit in the Region of Waterloo" was created, and boasted over 1,600 members. Shortly after its creation, the group creator and other LRT supporters formed the "Tri-Cities Transport Action Group". According to its website, TriTAG supports LRT as a needed method of shaping development, meeting future capacity needs, protecting the environment, and providing the most economical solution for transportation in the Region. Six months after founding, TriTAG launched an email campaign to allow supporters of LRT to email their MPs, MPPs, and other government officials such as the federal and provincial Ministers of Transportation. Within a few days, thousands of emails had been sent. For the 2010 Regional Budget, TriTAG and its supporters presented to the Regional Budget Committee regarding various areas of transportation funding. While the focus was not on LRT, the delegates spoke about the importance of proper transportation infrastructure on a successful LRT system. TriTAG has continued their support of the project into the bid stage in 2014; a notable contribution is a video outlining the landmarks and amenities that the route will access. Proponents have asserted that the region's plans for rapid transit will be an essential component of planning and rationally controlling the Region's growth.
A report in late 2017 indicated that the new Ion system was responsible in part for a predicted building boom in the core of Kitchener, much of it located near LRT stations. An estimated $1.2 billion in building permits for 20 new developments was expected by March 2018, adding 1,000 apartments and 1,800 condominium units. According to the City, the anticipated development was a "mixture of high-density residential buildings with ground-floor retail, and office buildings with ground-floor retail". Half of the projects would be extensive in size. A report in the Waterloo Region Record of December 29, 2017 indicated that "since Ion was approved in 2009, the region has issued $2.4 billion in building permits within the LRT corridor." Rod Regier, Commissioner of Planning, Development and Legislative Services for Waterloo Region, commented on the increase in building permits. "My back-of-the-envelope estimate is that the private sector developers have invested almost double the full cost of the Ion itself in the transit corridor. That for me is really astonishing," he said.

Opposition

A group opposed to the rapid transit proposal, called "Taxpayers for Sensible Transit", was formed in June 2009. According to its website, T4ST opposes LRT as being a proposal too big and too expensive for the region, which will hurt businesses and the local economy. Taxpayers for Sensible Transit did not present a position regarding transportation and transit funding for the 2010 Regional Budget.
In September 2013 Doug Craig, the mayor of Cambridge, called for the examining the cost of cancelling the light rail line.
He justified this examination due to doubts by Toronto politicians over its light rail line.
On November 19, 2013, it was reported that Craig was working to "extricate" Cambridge from any obligation to pay for the line connecting it to Kitchener, while, at the same time, trying to argue for connecting Cambridge to Toronto, via a GO line.
The first candidate to announce his run for Mayor of the City of Waterloo in the 2014 election, local media personality Dave MacDonald, was running on a primarily anti-LRT platform.
In March 2014, just as the Region was preparing to give final approval to the construction contract, a group titled "Coalition Stop Waterloo LRT" filed a legal injunction against the project, claiming it did not meet planning guidelines and should be stopped. A court decision on March 18 dismissed the motion, but did not rule out further legal review. It later emerged that the only citizen directly associated with the filing coalition was local businessman Jay Aissa.
Ann Tucker of the Ontario Superior Court dismissed the suit on March 19, 2014.
In July, Aissa announced that he was dropping further legal challenges, and instead would take a political option to oppose the project, running against incumbent Regional chairman Ken Seiling. Seiling was re-elected Chairman with 58.4% of the vote.
After publication of the February 2017 route plan, some citizens of Cambridge, particularly in the Preston area, were strongly objecting to the route, especially the section planned for Shantz hill and certain residential areas. City Council particularly objected to the Shantz Hill Road to Hespeler Road section and passed a motion in early July 2017 instructing staff to advise the Region of this and to request that alternatives be explored.