Jinping-I Dam


The Jinping-I Dam also known as the Jinping-I Hydropower Station or Jinping 1st Cascade, is a tall arch dam on the Jinping Bend of the Yalong River in Liangshan, Sichuan, China. Construction on the project began in 2005 and was completed in 2014. Its power station has a 3,600 MW capacity to produce between 16 and 18 TW·h annually. Supplying the power station is a reservoir created by the 305-meter-tall arch dam, the tallest in the world. The project's objective is to supply energy for expanding industrialization and urbanization, improve flood protection, and prevent erosion.

History

Harnessing hydropower on the Jinping bend of the Yalong River has been in planning for decades. The length of bend around the Jinping Mountains is 150 km but the downstream part of the river on the opposite side is only separated by 16 km. Between that distance, there is an elevation drop of 310 m, creating an excellent situation for hydroelectricity production. Two projects were planned for the bend, the Jinping I and Jinping II with a combined capacity of 8,400 MW. Planning for the projects began in the 1960s under the former Sichuan and Shanghai design institutes along with the Ministry of Water Resources and Electric Power. They produced the "Reinvestigation Report on The Yalong River bend ". In July 1965, the Jinping Hydropower Engineering Headquarters was set up and designs for the Jinping 1 and Jinping 2 would progress with the East China Investigation and Design Institute.
Construction began on 12 November 2005. The dam began to impound its reservoir on 8 October 2012. First power was generated in 2013 with the remainder of the work to be completed by 2015. The rapid impounding has been linked to reservoir-induced seismicity by a Chinese geologist. Out of hundreds of small earthquakes during impoundment, three between 3.9MW and 4.58MW were recorded on 22 November 2013 on a nearby fault line.
The dam began to impound its reservoir on 8 October 2012 and the first two of six 600 MW generators became operational on 30 August 2013. The sixth and final generator was commissioned on 15 July 2014. The final generator for Jinping-II downstream was commissioned in November 2014.

Geography

The Jinping-I Dam is on the border of the Yanyuan and Muli counties in the Liangshan Yi Autonomous Prefecture of the Sichuan province. The Yalong River, which the dam controls, is the largest tributary of the Jinsha. For the project, approximately 7,500 inhabitants were expected to be relocated.

Design

The 305m tall and 568m long arch dam supplies the power station with water from a 7.7 billion m3 reservoir, of which 4.9 billion m3 is active or usable storage. The dam itself has a structural volume of 7.4 million m3. To control flooding, the dam is equipped with a controlled spillway on its crest with four gates and the capability to discharge up to. Five bottom outlets on the dam's orifice capable of discharging and a tunnel with a discharge capacity of with augment flood control as well. The power station will contain six 600 MW Francis turbines. Water discharged from the power station is then diverted downstream by the Jinping 2 Dam to the Jinping 2 Hydropower Station.