Kajang–Seremban Highway


The Kajang–Seremban Highway, KASEH , or LEKAS Highway, is an expressway in Malaysia connecting Kajang, Selangor to Seremban, Negeri Sembilan. The speed limits on the expressway are 80 km/h and 110 km/h .

Overview

The expressway is designed to pass through Semenyih, Pajam, Mantin, Temiang and link to the Seremban Inner Ring Road. It serves as an effective traffic dispersal for the highly congested Kajang in Selangor to Seremban in Negeri Sembilan besides the North–South Expressway Southern Route and the Kuala Lumpur–Seremban Expressway.
The Kilometre Zero of the expressway starts right after the Exit 1804 Kajang Perdana Interchange which connects the expressway with the E18 Kajang Dispersal Link Expressway and the Kajang Bypass near Kajang, Selangor.

History

The project was approved by the government in 1997 and the construction of the expressway began on 2002; however, the financial problems faced by the original concessionnaire, Kajang–Seremban Highway Sdn. Bhd. had forced the construction works to be delayed. The project was revitalized in November 2006 after a takeover by a new concessionnaire, Lebuhraya Kajang-Seremban Sdn. Bhd., which 50% of the stake was held by IJM Corporation Berhad and the rest of the stake was held by the original concessionnaire, Kajang–Seremban Highway Sdn. Bhd. This project was scheduled for completion by December 2009.
The phase 1 of the expressway connecting Kajang South to Pajam was officially opened on 23 August 2008. The main subcontractor was WCT, which then subcontracted the beam-manufacturing to Mudajaya. As a normal procedure to make users familiarize with the highway, the highway will be toll free for a month from opening.
The highway system was extended with the opening of Mantin toll plaza on 31 December 2008. Again, the main subcontractor was WCT, and the beam-manufacturer was Mudajaya. Most of the shorter beams like the Ms and Inverted Ts were manufactured at Mudajaya's production plant in Ijok, Selangor, whilst the longer and more "treacherous" I-beams were produced on the site itself. As per normal practice, the route was toll free until 30 January 2009.
On 1 March 2010, the Setul and Ampangan Interchange has been opened for traffic.

Features

Pajam Incident

On 27 September 2007, at around 11.45 pm., eight massive I-20 beams collapsed in a domino fashion at BR 7, just about a kilometre from the Pajam Interchange. There were no casualties. In the three months following the incident, the contractor constructed a 4 km. public by-pass road circumnavigating the BR 7 launch site, from the Federal Route FT3265, to the Pajam Interchange, then onto the Pajam Toll Plaza, and coming out again at FT3265 nearer to the town of Nilai, recast the eight I-20 beams, and then re-launched them. There were no public funds involved in the repair work, and all costs were borne by the contractor.
The BR 7 is now in service, and forms part of the LEKAS Highway.

Other events

The Kajang–Seremban Highway from 2 March 2016 only accepts electronic toll payment only. This is the first closed toll expressway to phase out the closed toll system.

List of interchanges