Lamu Port and Lamu-Southern Sudan-Ethiopia Transport Corridor
Lamu Port-South Sudan-Ethiopia-Transport Corridor project, also known as Lamu corridor is a transport and infrastructure project in Kenya that, when complete, will be the country's second transport corridor. Kenya's other transport corridor is the Mombasa - Uganda transport corridor that passes through Nairobi and much of the Northern Rift. Some basic LAPSSET infrastructure has been built. The construction of LAPSSET's main components is currently ongoing with construction of the first berth at Lamu Port completed in October, 2019 .. Although the project is not formally stalled, its short to medium term success looks increasingly unlikely. Insecurity and political instability in Kenya are mostly to blame for this, as are more commercially viable alternative pipeline options through Tanzania or Ethiopia. The low oil prices since 2015 also affect LAPSSET's commercial prospects.
Background
The project will involve the following components:- A port at Manda Bay, Lamu
- Standard gauge railway line to Juba and Addis Ababa, the South Sudanese and Ethiopian capitals respectively.
- Road network
- Oil pipelines
- Oil refinery at Bargoni
- Three airports
- Three resort cities
The timeline of the project is not clear, including when it started and when it should be finished. Some projects like the Isiolo-Merille projects began in 2007. At the peak of the project, between 2013 and 2018, it is expected that the Kenyan government will be spending about 6% of the country's Gross Domestic Product or 16% of its annual budget on the project. The project is in turn expected to contribute an additional 3% increase in Kenya's GDP by 2020.
The aim of the project is to cut over-dependence on Kenya's main port of Mombasa as well as open up Kenya's largely under-developed northern frontier, through creation of a second transport corridor.
Key towns in the project are Lamu and Isiolo in Kenya, Juba in South Sudan and Addis Ababa in Ethiopia.
Institutionalisation of the project
The LAPSSET Corridor Project is the first single integrative infrastructure Project the Government has initiated and prepared under Vision 2030 Strategy Framework without external assistance. The project endeavors to deliver a Just and Prosperous middle income Kenya by the year 2030.Kenya is spearheading the development of Lamu Port-South Sudan-Ethiopia-Transport Corridor Project to strengthen the country's position as a gateway and a transport and logistics hub to the East African sub-region and the Great Lakes region to facilitate trade, promote regional economic integration and interconnectivity between African countries. The project is managed by the LAPSSET Corridor Development Authority, which is domiciled under the Presidency.
Mandate of LAPSSET Corridor Development Authority
In March 2013, the LAPSSET Corridor Development Authority was established through the Presidential Order Kenya Gazette Supplement No. 51, Legal Notice No. 58, The LAPSSET Corridor Development Authority Order 2013 to plan, coordinate and manage the implementation of the Lamu Port-South Sudan-Ethiopia Transport Corridor Project. The Authority is domiciled in The Presidency in accordance with the Constitution of Kenya 2010. The LCDA is headed by Mr. Silvester Kasuku, MBS, CMILT, Director General/ Chief Executive Officer and Amb, Dr. Francis Muthaura, EGH, Chairman of the Board of the Authority. The functions of the Authority are as follows:- i. Plan, coordinate and sequence LAPSSET Corridor projects in collaboration with implementing ministries and agencies;
- ii. Coordinate implementation of LAPSSET Corridor projects across implementing ministries and agencies;
- iii. Provide leadership, direction and guidance in operations and implementation of the LAPSSET Corridor;
- iv. Ensure implementation of all decisions and resolutions of the government;
- v. Mobilize funds to project components using a variety of resources including budgetary resources from government, donor loans, infrastructure bonds and private finance;
- vi. In collaboration with National and County government department, build the capacity of LAPSSET Corridor towns to manage urban growth resulting from LAPSSET Corridor investments;
- vii. Promote the competitiveness and use of the LAPSSET Corridor for the transport of goods and people; and
- viii. Provide a forum for all stakeholders of the LAPSSET Corridor.
LAPSSET Corridor Projects
The Corporation is mandated to manage the development of the following infrastructure project components which are key Transport, Energy and Communication investments;- 1.Lamu Port at Manda Bay
- 2.Standard Gauge Railway Line from Lamu – Isiolo - South Sudan – Ethiopia
- 3. Highways from Lamu – Isiolo - South Sudan – Ethiopia
- 4.Crude Oil Pipeline from Lamu – Isiolo – Nakodok/Nadapal, and Product Oil Pipeline from Isiolo – Moyale – Addis Ababa
- 5. International Airports at Lamu, Isiolo, and Turkana ;
- 6.Resort Cities at Lamu, Isiolo and Lake Turkana
- 7.Merchant Oil Refinery at Isiolo.
- 8. Services related infrastructure Project Components namely;
- *a. Malindi – Garsen Road
- *b. High Grand Falls Multipurpose Dam
- **i. Water Supply
- **ii. Power Supply; and
- *c. Fibre Optic Cable / Communication
- *d. Other generated and attracted investments in commercial and manufacturing sectors along the LAPSSET Corridor.
Already both local and international agricultural investors are keen on taking investment opportunities in this area and respective County Governments within the corridor have started receiving enquiries from some of the interested investors.
The LAPSSET Program therefore presents an investment opportunity that may be considered by the private sector investors including Pension, Insurance and saving Funds among other investors.
Economic Viability of LAPSSET Program
Project studies that were completed in 2011 on the LAPSSET Corridor project components showed great economic viability with most of the project components registering High Economic Internal Rates of Return of between 17% and 23.4% compared to acceptable industry minimum standard of 10% for infrastructure projects as shown in Table 1 below.Table 1: LAPSSET Corridor Project Components with accompanying cost implications
Services
Note 1: Both all and each project components are judged as viable in view of national economy as EIRRs computed are more than 12%, which is opportunity cost.
Note 2: Cargoes are generated by the Corridor itself. Higher figures than the above table can be realized.
From the statistics provided, it is therefore evident that if the government structured the projects into bankable bundles, it would attract private sector investors to participate and invest in the projects.
Cost of LAPSSET Program
The seven key infrastructure project components of the LAPSSET Corridor Program require substantial amounts of resources with a budget estimate of US$24.5 billion, equivalent to KES 2 trillion at current exchange rates in construction costs. It is estimated that Lamu Port with its 22 berths alone will cost approximately US$3.1 billion, the Railway US$7.1 billion while the crude oil pipeline will cost a further estimate of US$3 billion for Lamu to Lokichar trunk line alone.Indeed, the figures indicated above are of no mean task and cannot be left to the Government’s limited resources alone. The Government has prioritised the participation of private sector in the development of LAPSSET Corridor infrastructure through infrastructure bonds and equity participation among other money market instruments. There is already significant private sector interest being registered towards the implementation of these project components hence the need has arisen for the government to structure and package bankable projects that are investor ready for uptake by private sector.
Status of implementation of LAPSSET corridor projects
The government undertook ground breaking for the LAPSSET Corridor Program at Lamu Port site on 2 March 2012, after which it commenced construction activities of various infrastructural facilities and services aimed at progressing implementation of LAPSSET Corridor Project. The ongoing construction works for various project activities are summarized below.Lamu Port
LAPSSET Corridor Project is on course and so far construction activities for various facities at Lamu Port site are ongoing with progress for Lamu Port Building and Port Police and security facilities having achieved a completion rate of 95%.- i) Port Building: 95% complete.
- ii) Police Station: 95% complete.
- iii) Design review ongoing for the first three berths, with construction to begin in July 2014
- iv) The physical development plan and survey for the Port area has been completed.
LAPSSET Highway Component
The LAPSSET highway component has been categorized in sections as indicated below:- Lamu – Garissa - 250 km
- Garissa – Isiolo - 423 km
- Isiolo – Moyale - 505 km
- Isiolo–Nadapal - 721 km
Isiolo – Marsabit – Moyale, A2
Isiolo – Merille (136 km)
The Isiolo – Merille River Road, constitutes the first section of the 505 km road from Isiolo to Moyale which is part of the road linking Tunduma in Southern Tanzania with Addis Ababa in Ethiopia.The project construction works are complete. This project was funded by the African Development Bank at a cost of KES 6,318,130,428.27.
Merille River – Marsabit (121 km)
This road constitutes the second section of the 505 km road from Isiolo to Moyale and Addis Ababa in Ethiopia. The road begins at Merille River and runs in a northerly direction and terminates at Marsabit. The construction works for this section has progressed at 10% having commenced in January 2013 and is scheduled for completion by January 2016 and is being funded by the European Union. The project will cost a total sum of KES 13.73 billion.Marsabit – Turbi (123 km)
The road begins in Marsabit at the junction with the road C82 and runs in a northerly direction and terminates in Turbi constituting the third section of the 505 km road from Isiolo to Moyale and Addis Ababa in Ethiopia. The construction works for this section has progressed to 47.4% having commenced in April 2011 and is being funded by the African Development Bank and is expected to be completed by March 2014. The project will cost a total sum of KES 13 billion.Turbi – Moyale (125 km)
Construction works have progressed to 11.5% completion having commenced in October 2012 for a period of 36 months. This section is being funded by the African Development Bank and is expected to be completed in December 2015.In addition to the above the Government of Kenya and the Government of South Sudan, working together with the World Bank recently completed feasibility studies and detailed engineering designs for the Lokichar - Nadapal – Torit - Juba Road whose construction works will begin soon once finances are mobilised. This road project does present an opportunity for private sector participation.
Furthermore, the Government of Kenya is currently considering mechanisms for participation by private sector investors to deliver the Lokichar - Isiolo - Garissa - Lamu Road and Lamu - Garsen Road through Engineering, Procurement, Finance and Construct. Delivery of the road provides immediate road connection between Lamu Port and Juba and Addis Ababa.
- i. Lamu – Garissa, Garissa – Isiolo and Isiolo - Ginyang for EPC mode
- ii. Isiolo – Moyale : Construction work is ongoing with;
- *Isiolo – Merile section at 100% completion.
- *Merille – River Marsabit Construction works ongoing at an advanced stage
- *Marsabit – Turbi Construction works ongoing at an advanced stage
- *Turbi – Moyale Construction works ongoing at an advanced stage
- iii. Kitale – Lodwar – Nadapal Road : Designs are 95% complete.
- iv. Garsen – Lamu Road : Design reviews complete. Awaiting mobilization of resources for construction.
Crude Oil Pipeline
Electric Power Supply
In addition to the above the Government has prioritised the provision of appropriate infrastructural service aimed at supporting the massive investments planned for the LAPSSET Corridor. The Government has just completed the electric power connection for the Lamu Port of 220 kV transmission line from Rabai through Malindi and Garsen to Lamu.Construction of electric power transmission line has commenced to deliver electric power connection to key LAPSSET Corridor areas such as Garissa, Isiolo and Turkana. Already construction of 132 kV transmission line from Seven Folks/Kindaruma to Garissa is ongoing; construction of 132 kV transmission line from Mount Kenya region to Isiolo is ongoing. Plans for the construction of 400 kV transmission line from Lake Turkana to Suswa are at an advanced stage while plans are ongoing for the construction of 220 kV line from Garsen to Garissa.
- Rabai – Lamu 220 kV Transmission Line completed
- Garsen 220 kV Transmission Line to commence soon
- Lake Turkana – Suswa 400 kV Transmission Line to commence
- Lamu – Garissa – Isiolo – Lokichar 220 kV Transmission Line planned
- Kindaruma – Garissa 132 kV Transmission line to complete construction by Dec 2014
- Masinga – Isiolo 132 kV Transmission line to complete construction by Dec 2014
- Kamburu – Isiolo 220 kV Transmission Line to complete Construction by Dec 2014
Airports
Provision of airport facilities will strengthen buildup of air transport and logistics services along the corridor in readiness for the construction of the three international airports at the three locations in the future.
Kenya Civil Aviation Authority has already made plans to establish air transport safety, security and surveillance facilities and services to strengthen air transport and logistics in northern Kenya.
Manda Lamu Airport
The government recently completed lengthening of Lamu Manda Island Airport runway from 1.1 km to 2.3 km. Improvement works are already complete for the airport terminal building. Preparations are at an advanced stage towards the construction of a parallel taxiway and aircraft apron area to improve capacity of the airport. These improvements will enhance the capacity of Manda Lamu Airport that already has a strong scheduled flights clientele.Isiolo Airport
The Government has completed construction works on the 1.2 km Isiolo Airport runway. Construction works are currently ongoing for Airport Terminal Building which is scheduled for completion by end of 2014. Kenya Airports Authority has made plans to operationalise the airport once facilities are in place by mid 2014.Provision of Social Infrastructure, Services and Security
In addition to the ongoing physical works in to planned projects along the LAPSSET Corridor, the Government has commenced a comprehensive plan for the provision of social infrastructure and services so as to give LAPSSET Project a deserving human face. Panning for these social infrastructure and services will ensure that schools, health centres, towns, water and sanitation services, security services and other social amenities are provided at an optimal level to make LAPSSET Corridor areas secure, desirable, liveable and working environment and a place to nurture Kenya’s future generations.Recent developments in the LAPSSET corridor project area
Since conclusion of the LAPSSET study, oil discoveries have been made in the Turkana area in Kenya with current recoverable crude oil reserves estimated at 600 Million Barrels.With these developments, the original plan and design for the crude oil pipeline has to be reviewed to accommodate these new discoveries. The Pipeline will now evacuate crude oil from Lokichar Oil fields in Kenya, Lake Albert Oil fields in Uganda and oil fields in South Sudan. As such considerations are being made to commence construction of crude oil pipeline from Lokichar to Lamu Port to evacuate Kenyan oil as more preparations are made to complete negotiations on the construction of joining crude oil pipelines from Uganda and South Sudan oil fields.
In this event, the Lokichar to Lamu crude oil pipelines will be the trunk crude pipeline to accommodate crude oil from Uganda and South Sudan. Crude oil terminal tank farms will therefore be built at Lokichar and Lamu to manage the logistics of pumping crude oil through the pipeline as well as into the loading into ships for export. As a result, the governments of South Sudan and Kenya are preparing for the admission of the Uganda Crude Oil Pipeline component into the LAPSSET Corridor Crude Oil Pipeline Project.
As a way forward, the tripartite Heads of State Infrastructure Summit held in Uganda on 20 February 2014, agreed to allow Kenya to proceed with the Expression of interest for the development of the crude oil pipeline between Lamu and Lokichar oil fields to evacuate Kenyan oil as well as prepare for the construction of connecting lines from South Sudan’s and Ugandan Oil fields.
In order to support the development of the crude oil pipeline, the Government has identified the need to simultaneously construct the Lamu-Lokichar Road alongside the pipeline. As an early delivery strategy, the Ministries of Energy and Petroleum as well as Transport and Infrastructure have adopted an integrated approach for the development of the crude oil pipeline and the road from Lamu-Lokichar.
Participating countries
Participating countries include:Funding
Lamu Port and Manda Bay
Lamu Port is expected to consist of 32 berths when complete, will cost US $3.5 billion and be 1,000 acres in size. The port will be a deep water port at 18 metres depth.From bids requested by the Kenyan Government, the first phase of the port will include 3 deep water berths with a capability of handling ships with a deadweight capacity of up to 100,000 tonnes. The port will be built at Manda Bay and is expected to be operational starting December 2012.
A consortium of companies led by China Communications Construction Company was reported to have won the bid for construction of the first three berths at Lamu port. The cost of the project is valued at KES 41 billion. CCCC is associated with China Road and Bridge Corporation which has historically secured lots of road construction and other tenders in Kenya.
Standard gauge railway line to Juba
A railway line will run from Lamu to Juba, a distance of, and will be capable of handling trains with speeds of up to per hour for passenger trains, and perhaps per hour for freight trains. This will be at an estimated cost of $7.1 billion and is to be completed by 2015.By 2030, the railway line is expected to handle 30 daily trains to Juba and 52 to Addis Ababa.
Road network
LAPSSET road projects will run from Lamu to Isiolo and onwards to Juba and Addis Ababa through Moyale. This will be a 2 lane highway and will be at a cost of $1.4 billion.The road from Lamu will pass through Hola and Bura to Garissa. From Garissa, the main branch will run to Isiolo while a second branch will run off to Mwingi and Matuu for exploitation of coal in the Kitui Basin. Isiolo will be linked to Nairobi through one route, to Nakodok, near Lokichogio via another and to Moyale via the third route. Southern Sudan will be in charge of constructing a route from Nakodok to Juba while Ethiopia will construct a road from Moyale to Addis Abbaba
Isiolo – Moyale Road
Construction and upgrading of the Isiolo – Merille road which is part of LAPSSET commenced in 2007 and the road was finished in 2011. The road was upgraded into a 2 lane tarmac road. Construction of the Marsabit – Turbi road, also part of LAPSSET, commenced 29 August 2011, with an expected delivery date of 4 April 2014.Moyale – Addis Ababa road
Construction of the 193 km Ageremariam-Yabelo-Mega already began.Oil pipeline
The Oil Pipeline is expected to cost $4 billion. The crude oil pipeline will run from Lamu to South Sudan and Addis Ababa.Construction was originally expected to begin by end of 2013 once feasibility studies contracted to German company ILF were complete. South Sudan is optimistic of transporting its first oil via the pipeline in 2014 if construction begins immediately after completion of feasibility studies.
Oil refinery
A proposed oil refinery in Lamu will cost $2.5 billion and is expected to refine 120,000 barrels of oil a day.Three resort cities
Proposed resort cities at Lamu, Isiolo and Lokichogio on the shores of Lake Turkana will cost $1.2 billion.Isiolo Resort City
The Isiolo resort city is to be established under a public private partnership at a cost of KES 18.9 billion. In 2012, the Isiolo County Council was asked to set 6,500 acres of land aside for establishment of the resort city. The site is located at Kipsing Gap, 20 kilometres west of Isiolo town.The site was identified by Japanese Port Consultants after a nine-month feasibility study. The consultants also developed a conceptual design for the resort city with more than 10 preliminary models of the city. The plans include rules on land usage and guidance on private sector and local community involvement. The plans also cater for growth and development of the city for the next 20 to 30 years.
Under Kenya's new constitution, it will be mandatory for the government to get consent from the locals before commencing with the project. Residents will be compensated for the acquisition. The local council will then acquire the land title and make money from leasing out the land and charging rates.
The city will be situated between Katim hill and Oldonyo Degishu hill. Neighbouring game parks and national reserves include Lewa Wildlife Conservancy in the south, Buffalo Springs and Shaba National Reserve to the North, Samburu Game Reserve and Ewaso Ng'iro River to the West. The area also boasts a wide variety of plants and animals, including the big five, leading to it also being known as the Jewel in the crown.
Kipsing Gap was picked in preference of Kulamawe and Archers Post due to security, accessibility, cultural diversity, natural diversity, wildlife, water availability, electricity, sewer system among other factors.
In January 2012, 32 councillors led by chairman Adan Ali and Town Clerk Morris Ogolla and legislators, professionals, women group leaders were briefed by government officials on the importance of the resort city.
Attractions will include three star to six star hotels, a local art and craft museum, theatres, conference centres and cultural events.
LAPSSET Development Authority
President Mwai Kibaki, through a special gazette notice, announced the formation of the authority on 1 April 2013 with the task of managing the project on behalf of Kenya's government. The authority shall be headquartered in Nairobi and have offices in Lamu, Isiolo, Lokichogio, Marsabit and Moyale. A director general will head the 11 member board that will include five state officials, private sector representatives and a chairman appointed by the president.The authority will push for public private partnerships to help in implementation of the project.