Lennox Generating Station


Lennox Generating Station is a natural gas-fired station in Lennox and Addington County, Ontario, Canada. Owned and operated by Ontario Power Generation, it is situated on Highway 33 on the north shore of Lake Ontario, west of Bath, Ontario. It is the largest natural gas power station in Canada by installed capacity.
In the 1970s, Lennox was a solely oil-fired plant in an era of rising oil prices. Oil is delivered by tanker cars via a spur of the Montreal-Kingston-Toronto CN Rail line. From 1982 to 1987 the plant was placed in reserve to surplus power in Ontario. In 1997, the plant was converted to operate with either heavy oil or natural gas. In 2008, the plant obtained regulatory approval for an ozone generation system to control zebra mussel fouling of service water intake pipes.
As of 2007, Lennox represented 50% of Ontario installed generation capacity east of the Toronto zone. When operating at full capacity, the plant claims to be the largest user of natural gas in Ontario. The facility is operated solely at times of peak load; the base load for the Ottawa-Toronto region is supplied by Pickering and Darlington stations in Durham Region and by an asynchronous interconnection with Hydro-Québec which has served Ottawa since 2010.
It is common to operate on natural gas during the summer season and switch to oil in the winter, when demand is high for gas.

Description

The Lennox Generating Station consists of:
In 2012, Ontario's government announced an additional 900-megawatt TransCanada Energy natural gas plant to be built at the Lennox Generating Station site; the project was originally planned for Oakville, Ontario but the location was changed in 2010 as part of a controversial government decision to relocate it and another gas-fired power plant. While estimates vary, the additional costs to transport natural gas eastward and generated power westward are expected to represent hundreds of millions of dollars over the lifetime of the new generation plant; one report claims $675 million. The relocation of this proposed plant, and another proposed for Mississauga but displaced to Sarnia's Lambton Generating Station, were key political issues in 2011 and 2014 Ontario elections.
As of 2012, the site employed 160 people; an additional 25 permanent jobs will be added as a result of the 900MW expansion.

Emissions

YearEmissions
2004638,074
2005986,676
2006305,106
2007607,761
2008288,674
2009222,470
2010121,412
2011103,652
2012183,017