Line 1 of the Tianjin Metro runs from the north-west to the south-east of downtown Tianjin. It is in length with 32 stations.
The line started operations on 12 June 2006. It was rebuilt from the original Tianjin Metro line, which opened in 1976, but had to close down and undergo renovations in 2001 as part of the system's modernizing project. The line's color is red.

History

Construction began in 1970. The first section, spanning 3.6 km of track and 4 stations, which are named Xinhualu,, and stations, was completed by February 1976. The second section, with an additional 1.6 km of track and the and stations, was completed by 1980. After construction resumed, the total length was 7.4 km, with 8 stations, and service on the line began on 28 December 1984.
To cut construction costs, the authority used an abandoned canal bed to build part of the system. Thus the underground section is only 2–3 meters beneath the street surface, and was the world's shallowest metro. Years later, train frequency reduced and trains were commonly delayed. The rolling stocks themselves where dilapidated, with most seat covers torn off, and lights becoming dim. To change to a more modern and cleaner system in East Asia, a massive reconstruction, modernization and expansion plan was laid out in 2000. In preparation, the system was closed on 1 September 2001, with renovation totally started on 21 November after being delayed due to the terrorist attacks of 11 September. After introducing new rolling stocks, adding half-height platform screen doors and extending the line to, the line was completed at the end of 2005 and was re-opened on 12 June 2006.
In 2008, Station was temporarily closed for three years for the reconstruction of the Tianjin West railway station. It reopened on 1 July 2011.
In 2016, the at-grade station was closed.
On December 3, 2018, Shuanglin station was reopened as a new underground station.
On December 3, 2018, Line 1 also extended one station, from Shuanglin station to station.
On December 28, 2019, four stations on the eastern extension was opened.
The signal system was also replaced by the new ATO system, and the running stock was also overhauled.

Details

Alignment and interchanges

The line is underground between Qinjiandao and stations, as well as Shuanglin and Lilou. The other nine stations are elevated. All elevated stations are entirely covered by mixture of transparent & opaque corrugated sheets. The line passes through six districts, namely Beichen, Hongqiao, Nankai, Heping, Hexi and Jinnan. The whole journey takes about 50 minutes. The line is linked to other subway lines: 2 3 5 and 6. And interchanges to future lines will be available with line 4 7 8 10 and 11.

Concourse Level

All line 1 station concourses are equipped with a customer service center, ticket vending machines, automatic fare gates, and bank ATMs.

Platform level

For security and other reasons, all line 1 stations have platform-edge doors installed. TVs are installed that display travel tips, advertising, alerts, and waiting time for the next train.

Opening timeline

Stations (east to west)

Rolling Stock