The railway was initially built for the contractors Balfour Beatty to move workers and materials during construction of the tunnel. It was originally intended as a temporary feature. Later, a decision was made to retain the railway for the delivery and despatch of materials and to assist with the maintenance of the tunnel.
Description of railway
The principal location on the railway was the factory area, where there were various facilities such as a locomotive and speeder shed. Some of the sidings here were of mixed gauge. The railway as a whole comprised a network of lines as follows:
Pier railway
The pier railway, built to enable construction materials to be brought in, ran from "base camp" to a pier on Loch Linnhe. It crossed over the West Highland Railway and the Mallaig Extension Railway of the LNER on separate bridges east of Mallaig Junction. Later, a decision was made to retain the pier railway for the delivery of alumina and despatch of the finished aluminium ingots. The original railway, however, was not on a suitable alignment as it passed through the proposed site for Inverlochy village and also it crossed the A82 roadon the level. Construction of a permanent pier railway commenced in 1927. It crossed the West Highland Railway on a bridge immediately west of Mallaig Junction. This bridge is still extant, although the embankment leading to it on the eastern side was removed in 2019. It had been the intention that the permanent pier railway would be worked by electric traction, supplied by overhead lines, but this was never implemented. In addition, the bridges and embankments were built wide enough for double track, but the line remained single track throughout its life.
Upper Works Railway
This was by far the longest part of the rail system, running for some from base camp to the valve shafts located by Loch Treig. The first part of the railway climbed steeply for at gradients of 1 in 30 or even 1 in 25. There were about 90 bridges on the line. Most of the bridges were originally timber trestles but all were subsequently rebuilt in steel using suitable scrap material from the factory. Near the middle point of the railway, at a location known as "central", there was a triangle for turning trains.
This was a short branch line that joined the Upper Works Railway close to base camp. It climbed to a height of. Wagons were hauled by an electric winch at the top of the incline, which had a maximum gradient of 1 in.
Branch to adit 10
This branch connected with the Upper Works Railway and was in length.
Branch to shaft/intake 7
This branch connected with the Upper Works Railway and was in length.
Treig–Laggan railway
This was a branch line some in length. Built in 1930, it ran from a junction with the Upper Works Railway to Laggan Dam on Loch Laggan. The branch crossed over the WestHighland Railway at Fersit on a 26-span timber trestle bridge. Much of the bridge was gradually filled in to form an embankment.
Branch to shaft C
This branch connected with the Treig–Laggan railway and was in length.
Closure
In October 1971, heavy rainfall caused part of the Upper Works Railway to be washed away, leaving a gap of around in the track. Following this event, the future of the railway had to be considered. At that time, the Forestry Commission was constructing many access roads in the area. It was therefore decided that further roads should be built, rather than repair the track. However, due to the length of time it took to achieve this, the railway continued to operate for a number of years. Two locomotives and two speeders had been stranded on the far side of the breach from the factory. The railway finally closed in 1977.
Current status
Following closure of the railway, most of the track was lifted, but the steel bridges were mostly left in place. Some odd lengths of track remain in place, particularly on some of the longer bridges. There has been talk of reopening part of the Upper Works Railway as a tourist attraction.