Muja Power Station


Muja Power Station is a power station east of Collie, Western Australia. It has eight steam turbines served by coal-fired boilers that together generate a total capacity of 854 megawatts of electricity. The coal is mined in the nearby Collie Sub-basin.
The station was first commissioned on 21 April 1966. Currently four of the eight turbines are running. Muja has four 60 megawatts units, two 200 megawatts units and two 227 megawatts units. The four smallest and least efficient units, stages A and B, were closed in April 2007. In June 2008 it was announced that these older generator units would be recommissioned, due to a statewide natural gas shortage.
According to the National Pollutant Inventory, Muja Power Station is one of the biggest emitters of air pollution in Australia, including high emissions of beryllium, fluoride and particulate matter. Carbon Monitoring for Action estimates that, in 2009, Muja Power Station emitted of to generate of electricity.
In household consumer terms, this equates to of Carbon dioxide| emitted for each one kilowatt-hour, or, of electricity produced and fed into the electricity grid. That is, Muja Power Station emits slightly more per kilowatt-hour of electricity produced than nearby Collie Power Station and much more than Bluewaters Power Station based on estimates for the same year.

2012 explosion

In 2012 during the attempted recommissioning of stages A and B, an explosion occurred in unit 3 at the refurbished A B area due to corroded piping. A man was burnt, though the station continued to operate during the incident. An Australian Manufacturing Workers Union officer state secretary Steve McCartney had hailed the lack of casualties as "a miracle".

A & B Unit Mothballing

On 25 June 2013, after spending $250 million on the planned recommissioning of units A and B, Premier Colin Barnett announced work had been postponed indefinitely, citing that these older generators are "mothballed".
The Premier Colin Barnett has told Parliament no further work will be done on the generators for the time being, "The government has made a decision with respect to Muja A and B units; three and four continue to operate, units one and two are basically mothballed," he said.
In the following months the work was completed quietly and as of 2014 the Muja A and B units are used intermittently, primarily during summer peak times.
On 4 June 2017, the Labor government's energy minister Ben Wyatt again "confirmed the 52-year-old power station in Collie will be shut in September next year amid moves to retire more than 400 megawatts of generating capacity owned by Synergy." However, the 2018/19 state budget presented by Ben Wyatt for Western Australia in May 2018 allocates $48.1 million to work at Muja Stages C and D. This work includes "$6 million on the refurbishment of the Stage C Turbine and replacement of associated components" and "$4.2 million on an upgrade to electrical switchboards for Stages C and D."