Nuclear decommissioning


Nuclear decommissioning is the process whereby a nuclear facility is dismantled to the point that it no longer requires measures for radiation protection.
The presence of radioactive material necessitates processes that are potentially occupationally hazardous, expensive, time-intensive, and present environmental risks that must be addressed to ensure radioactive materials are either transported elsewhere for storage or stored on-site in a safe manner.
The challenge in nuclear decommissioning is not just technical, but also economical and social.
Decommissioning is an administrative and technical process.
It includes clean-up of radioactive materials and progressive demolition of the facility.
Once a facility is fully decommissioned, no radiological danger should persist.
The costs of decommissioning are generally spread over the lifetime of a facility and saved in a decommissioning fund.
After a facility has been completely decommissioned, it is released from regulatory control and the plant licensee is no longer responsible for its nuclear safety.
Decommissioning may proceed all the way to "greenfield" status.

Definition

Nuclear decommissioning is the administrative and technical process whereby a nuclear facility such as a nuclear power plant, a research reactor, an isotope production plant, a particle accelerator, or uranium mine is dismantled to the point that it no longer requires measures for radiation protection.
The progressive demolition of buildings and removal of radioactive material is potentially occupationally hazardous, expensive, time-intensive, and presents environmental risks that must be addressed to ensure radioactive materials are either transported elsewhere for storage or stored on-site in a safe manner. Decommissioning may proceed all the way to "greenfield status". Once a facility is decommissioned no radioactive danger persists and it can be released from regulatory control.

Options

The International Atomic Energy Agency defines three options for decommissioning:
The decommission of a nuclear reactor can only take place after the appropriate licence has been granted pursuant to the relevant legislation. As part of the licensing procedure, various documents, reports and expert opinions have to be written and delivered to the competent authority, e.g. safety report, technical documents and an environmental impact study.
In the European Union these documents are the basis for the environmental impact assessment according to Council Directive 85/337/EEC. A precondition for granting such a licence is an opinion by the European Commission according to Article 37 of the Euratom Treaty. Article 37 obliges every Member State of the European Union to communicate certain data relating to the release of radioactive substances to the Commission. This information must reveal whether and if so what radiological impacts decommissioning – planned disposal and accidental release – will have on the environment, i.e. water, soil or airspace, of the EU Member States. On the basis of these general data, the Commission must be in a position to assess the exposure of reference groups of the population in the nearest neighbouring states.

Cost

In the United States, the NRC recommends that the costs of decommissioning should be spread over the lifetime of a facility and saved in a decommissioning fund. Repository delay seems to be effective in reducing NPP decommissioning costs.
In France, decommissioning of Brennilis Nuclear Power Plant, a fairly small 70 MW power plant, already cost €480 million and is still pending after 20 years.
Despite the huge investments in securing the dismantlement, radioactive elements such as plutonium, caesium-137 and cobalt-60 leaked out into the surrounding lake.
In the UK, decommissioning of the Windscale Advanced gas cooled reactor, a 32 MW prototype power plant, cost €117 million.
A 2013 estimate by the United Kingdom's Nuclear Decommissioning Authority predicted costs of at least £100 billion to decommission the 19 existing United Kingdom nuclear sites.
In Germany, decommissioning of Niederaichbach nuclear power plant, a 100 MW power plant, amounted to more than €143 million.
New methods for decommissioning have been developed in order to minimize the usual high decommissioning costs.
One of these methods is in situ decommissioning, meaning that the reactor is entombed instead of dismantled.
This method was implemented at the U.S. Department of Energy Savannah River Site in South Carolina for the closures of the P and R Reactors.
With this tactic, the cost of decommissioning both reactors was $73 million.
In comparison, the decommissioning of each reactor using traditional methods would have been an estimated $250 million.
This results in a 71% decrease in cost by using ISD.
In 2004, in a meeting in Vienna, the International Atomic Energy Agency estimated the total cost for the decommissioning of all nuclear facilities.
Decommissioning of all nuclear power reactors in the world would require US$187 billion; US$71 billion for fuel cycle facilities; less than US$7 billion for all research reactors; and US$640 billion for dismantling all military reactors for the production of weapons-grade plutonium, research fuel facilities, nuclear reprocessing chemical separation facilities, etc.
The total cost to decommission the nuclear fission industry in the World was estimated at around US$1 trillion.

Decommissioning funds

In Europe there is considerable concern over the funds necessary to finance final decommissioning. In many countries either the funds do not appear sufficient to cover decommissioning and in other countries decommissioning funds are used for other activities, putting decommissioning at risk, and distorting competition with parties who do not have such funds available.
In 2016 the European Commission assessed that European Union's nuclear decommissioning liabilities were seriously underfunded by about 118 billion euros, with only 150 billion euros of earmarked assets to cover 268 billion euros of expected decommissioning costs covering both dismantling of nuclear plants and storage of radioactive parts and waste. France had the largest shortfall with only 23 billion euros of earmarked assets to cover 74 billion euros of expected costs.
Similar concerns exist in the United States, where the U.S. Nuclear Regulatory Commission has located apparent decommissioning funding assurance shortfalls and requested 18 power plants to address that issue. The decommissioning cost of Small modular reactors is expected to be twice as much respect to Large Reactors.

International collaboration

Organizations that promote the international sharing of information, knowledge, and experiences related to nuclear decommissioning include the International Atomic Energy Agency, the Organization for Economic Co-operation and Development's Nuclear Energy Agency and the European Atomic Energy Community. In addition, an online system called the Deactivation and Decommissioning Knowledge Management Information Tool was developed under the United States Department of Energy and made available to the international community to support the exchange of ideas and information. The goals of international collaboration in nuclear decommissioning are to reduce decommissioning costs and improve worker safety.

List of inactive or decommissioned civil nuclear reactors

A wide range of nuclear facilities have been decommissioned so far. The number of decommissioned nuclear reactors out of the List of nuclear reactors is small. As of 2016, 150 nuclear reactors were shut-off, in several early and intermediate stages, but only 17 have been taken to fully "greenfield status". Some of these sites still host spent nuclear fuel in the form of dry casks embedded in concrete filled steel drums.
Several nuclear engineering and building demolition companies specialize in nuclear decommissioning, which has become a profitable business. More recently, construction and demolition companies in the UK have also begun to develop nuclear decommissioning services. Due to the radioactivity in the reactor structure, decommissioning takes place in stages. Plans for decommissioning reactors have a time frame of decades. The long time frame makes reliable cost estimates difficult and cost overruns are common even for "quick" projects.
As of 2017, most nuclear plants operating in the United States were designed for a life of about 30–40 years and are licensed to operate for 40 years by the US Nuclear Regulatory Commission. The average age of these reactors is 32 years. Many plants are coming to the end of their licensing period and if their licenses are not renewed, they must go through a decontamination and decommissioning process.
CountryLocationReactor typeOperative lifeDecommissioning
phase
Dismantling
costs
AustriaZwentendorfBWR 723 MWeNever activated due to referendum in 1978Now a technics museum
BelgiumSCK•CEN – BR3,
located at Mol, Belgium
PWR 25 years
Decon completed
European pilot project
BulgariaKozloduy
Units 1, 2, 3, 4
PWR VVER-440
Reactors 1,2 closed in 2003,
reactors 3,4 closed in 2006
De-fuelling
CanadaGentilly
Unit 1
CANDU-BWR
250 MWe
180 days
"Static state" since 1986stage two:
$25 million
CanadaPickering NGS
Units A2, A3
CANDU-PWR
8 x 542 MWe
30 years
Two units currently in "cold standby"
Decommissioning to begin in 2020
calculated:
$270–430/kWe
ChinaBeijing HWWR 10 MWe 49 years
SAFSTOR until 2027proposed: $6 million for dismantling
$5 million for fuel remotion
FranceBrennilis:fr:HWGCR|HWGCR 70 MWe12 years
Phase 3
already spent €480 million
FranceBugey
Unit 1
UNGG
Gas cooled, graphite moderator
1972–1994postponed
FranceChinon
Units 1, 2, 3
Gas-graphite
postponed
FranceChooz-APWR 300 MW24 years
Fully decommissioned – Greenfield
FranceSaint-LaurentGas-graphite1969–1992Postponed
FranceRapsodie at
Cadarache
Experimental
Fast breeder nuclear reactor

40 MWe
15 years
1983: Defuelling
1987: Remotion of neutron reflectors
1985–1989: Decontamination
of sodium coolant
Accident when cleaning residual sodium in vessel with ethyl carbitol
The removed activity is estimated to around 4800 TBq.
600 TBq in 1990 still contained in 1ry vessel

The dose burden from 1987 to 1994 was 224 mSv.

RAPSODIE reached IAEA level 2 of decomm in 2005

STAGE 3 is planned in 2020
FrancePhénix at
Marcoule
Experimental
Fast breeder nuclear reactor

233 MWe
36 years
Defuelled
estimated for the future:
$4000/kWe
FranceSuperphénix at
Creys-Malville
Fast breeder nuclear reactor
11 years
Defuelled
2) Extraction of Sodium
Pipe cutting with a robot
estimated for the future:
$4000/kWe
East GermanyGreifswald
Units 1, 2, 3, 4, 5, 6
VVER-440
5 x 408 MWe
Reactors 1–5 closed in 1989/1990,
reactor 6: finished but never operated
Immediate
dismantling
~ $330/kWe
East GermanyRheinsberg
Unit 1
VVER-210
70–80 MWe
24 years
In dismantling
since 1996
Safstor
~ $330/kWe
East GermanyStendal
Units 1, 2, 3, 4
VVER-1000
Never activated
Not radioactive

West GermanyGundremmingen-ABWR
250 MWe

11 years
Immediate
dismantling
pilot project
IndiaRajasthan Atomic Power Station
Unit 1
PHWR 100 MWe 44 years
IraqOsiraq/Tammuz
Unit 1
BWR 40 MWe
Nuclear reactor with weapons-grade plutonium production capability
Not radioactive: never supplied with uranium
ItalyCaorsoBWR
840 MWe
3 years
SAFSTOR: 30 years
€450 million
+ €300 million
ItalyGarigliano BWR
150 MWe
Closed on March 1, 1982SAFSTOR: 30 years
ItalyLatina Magnox
210 MWe Gas-graphite
24 years
SAFSTOR: 30 years
ItalyTrino VercellesePWR Westinghouse,
270 MWe

SAFSTOR: 30 years
JapanFukushima Dai-ichi
Unit 1
BWR 439 MWeNovember 17, 1970 - March 11, 2011Since 2011 Tōhoku earthquake and tsunami of March 11

Hydrogen explosion
Estimated at ¥10 trillion for decontaminating Fukushima and dismantling all reactors in Japan and considering long time damage to environment and economy, including agriculture, cattle breeding, fishery, water potabilization, tourism, loss of reputation in the world
.
JapanFukushima Dai-ichi
Unit 2
BWR 760 MWeDecember 24, 1973 - March 11, 2011
JapanFukushima Dai-ichi
Unit 3
BWR 760 MWeOctober 26, 1974 - March 11, 2011
JapanFukushima Dai-ichi
Unit 4
BWR 760 MWeFebruary 24, 1978 - March 11, 2011Since March 11, 2011
Reactor defueled when tsunami hit
Damage to spent fuel cooling-pool
JapanFukushima Dai-ichi
Unit 5
BWR 760 MWeSeptember 22, 1977 - March 11, 2011Planned decommissioning
Cold shutdown since March 11, 2011
JapanFukushima Dai-ichi
Unit 6
BWR 1067 MWeMay 4, 1979 - March 11, 2011Planned decommissioning
Cold shutdown since March 11, 2011
JapanFukushima Daini
Unit 1
BWR 1067 MWeJuly 31, 1981 - 11 March 2011Planned decommissioning
Cold shutdown since March 11, 2011
JapanFugenAdvanced thermal reactor

165 MWe
1979 – 2003Cold shutdown
JapanTokai
Unit 1
Magnox 160 MWe1966 – 1998Safstore: 10 years
then decon
until 2018

¥93 billion
North KoreaYongbyonMagnox-type
20 years

Deactivated after a treaty
SAFSTOR: cooling tower dismantled
NetherlandsDodewaardBWR Westinghouse
58 MWe
28 years
Defuelling completed
SAFSTOR: 40 years
RussiaMayak
PUREX plant for
uranium enrichment
Several severe incidents
RussiaSeversk
Three plutonium reactors
Plant for uranium enrichment
Two fast-breeder reactors closed,
after disarmaments agreements with USA in 2003.
SlovakiaJaslovské Bohunice
Units 1, 2
VVER 440/230
2 X 440 MWe

SpainJosé CabreraPWR
1 x 160 MWe
38 years
Defueled
Dismantling
Objective: green field in 2018
217.8 million
SpainSanta María de Garoña
BWR/3
1 x 466 MWe
1966 - 2013Defueled
. Asked for renewal of license that was denied energy-politically from the government. Is in decommissioning state
SpainVandellós
Unit 1
UNGG
480 MWe
18 years
Incident:
fire in a turbogenerator
SAFSTOR: 30 years
Phases 1 and 2: €93 million
SwedenBarsebäck
Units 1, 2
BWR 2 x 615 MWReactor 1: 24 years 1975 – 1999
Reactor 2: 28 years 1977 – 2005
SAFSTOR: demolition will begin in 2020The Swedish Radiation Safety Authority has assessed that the costs for decommissioning and final disposal for the Swedish nuclear power industry may be underestimated by SKB by at least 11 billion Swedish crowns
SwitzerlandDIORITMWe CO2-Gas-heavy water
Decommissioned
SwitzerlandLUCENS8,3 MWe CO22-Gas-heavy water

Incident: fire in 1969
Decommissioned
SwitzerlandSAPHIR0,01–0,1 MWe
39 years

Decommissioned
UkraineChernobyl-4
RBMK-1000
1000 MWe
hydrogen explosion,
then graphite fire
ENTOMBMENT
Past: ?
Future: riding sarcophagus in steel
United KingdomBerkeleyMagnox
27 years
SAFSTOR: 30 years
around $2600/kWe
United KingdomBradwellMagnox
2 x 121 MWe
1962–2002SAFSTOR: 30 years
around $2600/kWe
United KingdomDounreay: DMTR
Fast-neutron reactor1958 - 1969Demolition conract awarded December 2018
United KingdomDounreay: DFR
Loop-type fast breeder.
14 MWe.
1959 - 1977Defueling
United KingdomDounreay: PFR
Pool-type fast breeder cooled by liquid sodium, fueled with MOX.250 MWe.1974 – 1994

Delays and reliability problems before reaching full power.
Remotely operated robot 'Reactorsaurus' will be sent in to decontaminate equipment as too dangerous a task for a human. Control panel has been earmarked for an exhibition at London Science Museum.
United KingdomSellafield-CalderhallMagnox
4 x 60 MWe
first nuclear power station.
August 27, 1956 – March 31, 2003 The first reactor had been in use for 47 years.SAFSTOR: 30 years
.
around $2600/kWe
United KingdomChapelcrossMagnox
4 x 60 MWe
1959 – 2004SAFSTOR: 30 years
around $2600/kWe
United KingdomWinfrith-Dorset
Research area of
the UKAEA
SGHWR
100 MWe
Operated from
1958 to 1990.
All nine reactors mostly dismantled
United StatesCrystal River 3
PWR
860 MWe
33 years

Plant scheduled to restart in April 2011, but the project encountered a number of delays. After repairs, additional delamination began to occur in adjacent bays. Duke Energy announced in Feb-2013 that the Crystal River NPP would be permanently shut down.
From 2015 to 2019 in defueling.
expected SAFSTOR 2019–2067

Decommissioning Periods ; Duration

Period 1: Planning and Preparations 2.08 y.

P. 2a: Dormancy w/Wet Fuel Storage 4.12 y.

2b: Dormancy w/Dry Fuel Storage 17.39 y.

2c: Dormancy w/No Fuel Storage 30.39 y.

P. 3a: Site Reactivation & D. Prep 1.50 y.

P. 4a: Large Component Removal 1.45 y.

4b & 4c: Systems Removal & Building Remediation 2 y.

Period 4f: License Termination 0.75y.

Period 5b: Site Restoration 1.50 y.
~$1,2 billion
United StatesDresden
Unit 1
BWR
207 MWe
18 years
Defueled in safety in 1998
now in SAFSTOR
Fuel in on-site dry-casks.
United StatesFort St. Vrain GS
HTGR

380 MWe
12 years
Immediate Decon$195 million
United StatesRancho Seco NGS
PWR 913 MWe12 years
SAFSTOR: 5–10 years
completed in 2009

Fuel in insite long-term dry-cask storage
$538.1 million
United StatesThree Mile Island
Unit 2
PWR 913 MWe1978-1979
Core fusion incident
Post-Defuelling
Phase 2
$805 million
United StatesShippingport
BWR 60 MWe25 years
Decon completed
dismantled in 5 years
$98.4 million
United StatesSan Onofre NGS Unit 1
PWR 436 MWe Westinghouse Electric Corporation25 years
Reactor dismantled and used as a storage site for spent fuel.
United StatesSan Onofre NGS Units 2, 3
2 x PWR 1,075 MWeUnit 2: 1983 – 2013
Unit 3: 1984 – 2013

In 2011, Edison finished replacing the steam generators in both reactors with improved Mitsubishi ones, but the new design had several problems, cracked, causing leaks and vibrations.
Permanent shutdown – DECON
soon defueling
2014 cost forecast:
$3.926 billion
to $4.4 billion
United StatesPiqua NGS
OCM reactor 46 MWe2 years
ENTOMB
United StatesTrojan
PWR 1,180 MWe16 years
SAFSTOR
United StatesYankee Rowe
PWR 185 MW31 years
Decon completed – Demolished
$608 million with $8 million per year upkeep
United StatesMaine YankeePWR
860 MWe
24 years
Decon completed – Demolished in 2004
$635 million
United StatesVermont YankeeBWR 620 MWe
42 years
Defueling
~$1.24 billion
United StatesExelon –
Zion
Units 1, 2
2 x PWR 1040 MWe
25 years
SAFSTOR-EnergySolutions

$900–1,100 million
United StatesPacific Gas & Electric
Humboldt Bay
Unit 3
BWR 63 MWe13 years

On July 2, 1976, Humboldt Bay Power Plant Unit 3 was shut down for annual refueling and to conduct seismic modifications. In 1983, updated economic analyses indicated that restarting Unit 3 would probably not be cost-effective, and in June 1983, PG&E announced its intention to decommission the unit. On July 16, 1985, the U.S. Nuclear Regulatory Commission issued Amendment No. 19 to the HBPP Unit 3 Operating License to change the status to possess-but-not-operate, and the plant was placed into a SAFSTOR status.Unknown – Closure date: December 31, 2015

Decommissioning of ships, mobile reactors, and military reactors

Many warships and a few civil ships have used nuclear reactors for propulsion. Former Soviet and American warships have been taken out of service and their power plants removed or scuttled. Dismantling of Russian submarines and ships and American submarines and ships is ongoing. Marine power plants are generally smaller than land-based electrical generating stations.
The biggest American military nuclear facility for the production of weapons-grade plutonium was Hanford site, now defueled, but in a slow and problematic process of decontamination, decommissioning, and demolition. There is "the canyon", a large structure for the chemical extraction of plutonium with the PUREX process. There are also many big containers and underground tanks with a solution of water, hydrocarbons and uranium-plutonium-neptunium-cesium-strontium. With all reactors now defueled, some were put in SAFSTOR. Several reactors have been declared National Historic Landmarks.