Oyapock River Bridge
The Oyapock River Bridge spans the Oyapock River, linking the cities of Oiapoque in Amapá, Brazil and Saint-Georges-de-l'Oyapock in French Guiana, France. The bridge is cable-stayed, with two towers rising to a height of and a length of. There are two lanes for vehicles with a total width of and a pedestrian sidewalk with a width of. The vertical clearance under the bridge is.
Its construction was completed in August 2011. However, due to delays in the construction of Brazilian checkpoint facilities, the bridge was not open to traffic for many years.
The inauguration ceremony of the bridge finally took place on 18 March 2017. Starting from 08:00 on 20 March 2017, the bridge has been open to members of the public.
The bridge is toll-free and is accessible to both private cars and pedestrians. On the French side, there is a border checkpoint staffed by three governmental agencies: the Border Police, Customs and the Directorate for Food, Agriculture and Forestry. The border checkpoint is open during the periods of 08:00 - 12:00 and 14:00 - 18:00 on weekdays, and 08:00 - 12:00 on Saturdays. The border checkpoint is shut on Sundays and Brazilian public holidays.
Until the Brazilian border outposts are completed, only passenger vehicles are permitted access. As the Brazilian side of the bridge is not staffed, travellers arriving in Brazil should stop at the offices of the Federal Revenue Service and the Federal Police in Oiapoque to regularise their entry.
With the bridge open to traffic, it is now possible to drive from Cayenne to Macapá, the capital of the Brazilian state of Amapá, although parts of the BR-156 federal highway on the Brazilian side are yet to be paved.
History
Though the bridge was officially announced in 1997, it was only after nearly 10 years of stalling and talks that a model of the bridge between France and Brazil was finally unveiled by French president Nicolas Sarkozy and Brazilian president Luiz Inácio Lula da Silva on February 14, 2008.The site chosen for the positioning of the bridge required a length of, which includes a span of approximately over water, and valued at .
Construction of the bridge was undertaken by a partnership between EGESA and the Consórcio Metropolitano de Transportes - CMT, both of which are headquartered in Brasília. The Professor Carlos Augusto Bittencourt Foundation - FUNCAB was hired to oversee the environmental engineering of the project, so that the construction of the bridge does not harm the natural environment. The bridge is part of the Guianese Shield Hub of the Initiative for the Integration of the Regional Infrastructure of South America. The construction of this bridge came after the signing of an international treaty between France and Brazil in July 2005. Furthermore, the connection between Route N2 and BR-156 is yet another initiative undertaken under the scope of the Brazilian government's PAC infrastructure project.
The Route BR-156 was conceived as development factor and a national security initiative.
In the words of Walter do Carmo pioneer, entrepreneur and engineer actively involved on the project, "the federal highway BR-156 was planned to establish the terrestrial junction between the Amazon River Basin, south of Macapá and Oyapock River Basin in northern Brazil's border with French Guyana."
This bridge is the first land crossing along the border between France and Brazil, and indeed it is the first terrestrial crossing between French Guiana and of its neighbors in northern South America. Currently, there is a good ferry that crosses the Maroni River between French Guyana and Suriname that links Albina, in Suriname, with Saint-Laurent-du-Maroni in French Guyana. It is also possible to travel from Albina to Georgetown by highway; it is planned to build a bridge between Suriname and Guyana, replacing the current ferry. Onwards to Venezuela, one can only travel by sea, but a road link is planned. In this case, it will be possible to drive from Macapá to Venezuela and Colombia with only one ferry crossing.
Though the Oyapock Bridge was to be inaugurated in early 2012, it remained closed as the road on the Brazilian side was not completely paved. As of April 2013, the opening was scheduled for the end of 2013, but as of January 2015 the bridge had still not opened due to delays in the construction of the Brazilian customs facility, and no opening date was forecast. Another reason for the delayed opening of the bridge, as identified by Brazilian Senator João Capiberibe, was the lack of reciprocity pertaining to the visa requirements for Brazilian and French nationals entering each other's territory. In 2014, the Brazilian and French governments reached an agreement allowing residents of Oiapoque in Brazil and Saint-Georges-de-l'Oyapock in French Guiana to apply for a local border crossing card, enabling them to visit each other's city visa-free for up to 72 hours. The local border crossing card has a maximum validity of 2 years and contains a biometric chip; it can be used to cross the border without having to present a Brazilian passport. The arrangement came into effect on 1 January 2015 and, as of 1 October 2015, over 200 cards had been issued to Brazilian citizens resident in Oiapoque. According to the French government, the Brazilian government was 'largely satisfied' with this arrangement.
Even though the Brazilian checkpoint had not yet been completed and full visa waiver reciprocity had not yet been achieved, due to pressure from the French government, the bridge was inaugurated on 18 March 2017 in the presence of officials from Brazil and French Guiana. The French Minister of Ecology, Sustainable Development and Energy, Ségolène Royal, was originally due to attend the inauguration ceremony, but in the end was not present. The official reason for her absence at the inauguration ceremony was that her Brazilian counterpart would not be present, but local media suggested that the actual reason was the various protests she faced during her visit in French Guiana, which led her to cut short her visit in the overseas department and fly back to Paris on 17 March 2017.
As of March 2017, it is expected that the Brazilian checkpoint will be completed and operational by September 2017, at which point there will be a 'full' opening of the bridge.