The Peachliner, formally the Tōkadai Shin-kōtsū Peach Liner was a people mover in the city of Komaki, Aichi Prefecture, Japan. It operated from 1991 until September 30, 2006, when it became the first people-mover system in Japan to cease operations.

History

The planning of the line started in 1971 along with the planning of Tōkadai New Town, a planned city outside Komaki designed for 54,000 people. The decision to choose a people mover system was made in 1974, with a projected ridership of 43,000 passengers per day and a budget of 24.5 billion yen, and a second stage to Kōzōji planned. However, in 1978, the town's planned size was cut down to 47,000 people and the ridership estimate was cut to 23,000 ppd. Construction started in 1981 based on this estimate.
In 1984, the town's design was again downsized to 40,000 people and the ridership to 20,000 ppd. A decision was also made to operate the line manually instead of in fully automated mode. The line was opened on March 25, 1991, charging ¥300 for an end-to-end trip, but by this time the ridership projection had been cut to just 12,000 passengers per day.
However, between 1991 and 2004 the line only averaged 2,670 passengers per day, amounting to only 6% of the original estimate and 22% of the opening-day projection. The maintenance of the line required some 11.5 billion yen per year, a tenth of Tokadai New Town's budget and, compared to construction costs of 31.3 billion yen, the equivalent of rebuilding the line from scratch every three years. According to calculations by the local chapter of the Japanese Communist Party, the building of the line had increased the original sale prices of apartments in the area by approximately one million yen.
In 2005, the option of converting the line to use Toyota's experimental IMTS technology was considered, but this was rejected by Aichi Prefecture in November as it was too difficult and risky. The decision to close the line was made in December, and the line ceased operating on September 30, 2006.
, the Peachliner's track is still in place, though totally unused.

Operator

The Peachliner was operated by :ja:桃花台新交通|Tōkadai Shin-kōtsū. Stock in this third-sector company is held by Aichi Prefecture, the city of Komaki, Nagoya Railroad, and others.

Data

Stations

Komaki and Komakihara Stations remain in service on the Nagoya Railroad Komaki Line.