Pebble Mine
Pebble Mine is the common name of a very large porphyry copper, gold, and molybdenum mineral deposit in the Bristol Bay region of Southwest Alaska, near Lake Iliamna and Lake Clark. As of August 2020, mine developers are seeking federal permits from the U.S. Army Corps of Engineers, the U.S. Coast Guard and the Bureau of Safety and Environmental Engineering. State permitting will follow and developers expect it to take up to three years.
Background
Geography
The Pebble prospect is in a remote, wild, and generally uninhabited part of the Bristol Bay watershed. The nearest communities, about distant, are the villages of Nondalton, Newhalen, and Iliamna. The site is southwest of Anchorage, Alaska.Pebble is approximately north of, and upstream of, Lake Iliamna. The deposit area is characterized by relatively flat land dotted by glacial ponds, interspersed with isolated mountains or ranges of hills rising one or two thousand feet above the flats. Pebble is under a broad flat valley at about above sea level dividing the drainages of Upper Talarik Creek and the Koktuli River.
Upper Talarik Creek flows into Lake Iliamna, which flows through the Kvichak River into Bristol Bay. Waters in the Koktuli River drain into the Mulchatna River, a tributary of the Nushagak River which empties into Bristol Bay at Dillingham. Water from Lake Clark, approximately east of Pebble, flows down the Newhalen River to Lake Iliamna.
Geology
Regional
The Kahiltna terrane is interpreted to represent a sediment trough formed on the landward side of the Wrangellia volcanic arc terrane, prior to collision of Wrangellia with Alaska. The Wrangellia and Kahiltna terranes docked to Alaska in the Cretaceous Period. This part of the Kahiltna terrane is dominated by Late Triassic basalt, andesite and sedimentary rocks overlain by Jurassic-Cretaceous andesitic turbidites. Cretaceous granitic intrusive activity was widespread in the Kahiltna terrane. Tertiary volcanic and sedimentary rocks, and Quaternary glacial deposits, developed over the older rocks.The Lake Clark fault, or a splay, probably lies within of the Pebble deposits and possibly much closer. The Lake Clark fault is a major right-lateral strike-slip crustal feature, considered to be a westward expression of the Castle Mountain fault. The actual ground trace of the fault and its splays are unknown in the Pebble area, due to extensive ground cover. A 2007 report indicates that magnitude 7.1 quakes occur on the fault on a 700-year cycle. The Lake Clark fault several hundred miles to the north is sub-parallel to the Denali fault and considered to be of similar nature. A magnitude 7.9 quake struck the Denali fault in 2002.
The subduction zone of the Aleutian Trench lies approximately south of Pebble. This zone was the source of the 1964 Good Friday earthquake of magnitude 9.2.
The ore body
A contiguous body of ore is known as Pebble West where mineralization locally extends to the surface and as Pebble East where it is deeply buried. Pebble holds mostly low-grade ore, requiring a large-scale operation to economically recover it.The Pebble deposit is hosted in porphyritic granodiorite to tonalite of Upper Cretaceous age intruded into deformed sedimentary rocks of the Jurassic to Cretaceous Kahiltna flysch terrane.
The copper ore is a calc-alkali porphyry copper-gold-molybdenum deposit. The ore body extends from the surface to at least depth. In the western part of the orebody, mineralization occurs in a complex of several small granodiorite cupolas, diorite sills, older intrusions, breccias, and sediments. The western part of the deposit is locally exposed at the surface; thin gossans are developed and oxidation reaches in depth. The orebody extends eastward across a fault contact, at depth. East of the fault mineralization occurs in abundant sills and in the intruded sediments. Farther east, and deeper, the sills coalesce into a deeply buried granodiorite pluton. Mineralization and ore continue into the pluton. The eastern part of the deposit was eroded when it was exposed at the surface millions of years ago. It has since been buried by a thickening-to-the-east wedge of post-mineralization-age Tertiary sedimentary and volcanic sedimentary rocks.
The age of mineralization at Pebble was reported in 2001 to extend for several million years between 86 million years ago and 89.5.
Metallic minerals identified at Pebble include pyrite, chalcopyrite, molybdenite, and bornite, along with minor covellite, chalcocite, digenite and magnetite.
Reserves
In 2008, Pebble was estimated to be the second-largest ore deposit of its type in the world in terms of the value of the contained metal, slightly smaller than Indonesia's Grasberg Mine, which contains more metal in a smaller amount of ore than Pebble. Estimates have grown throughout the history of the project.In February 2010, a resource estimate, based on a total of 509 drillholes and at a 0.3% copper equivalent cutoff, reported the combined Pebble deposit mineral resources of East and West comprise:
- 5.94 billion tonnes of ore as "measured and indicated mineral resources" grading 0.78% CuEQ, containing 55 billion pounds of copper, 67 million ounces of gold and 3.3 billion pounds of molybdenum; and
- 4.84 billion tonnes of ore as "inferred mineral resources" grading 0.53% CuEQ, containing 25.6 billion pounds of copper, 40.4 million ounces of gold and 2.3 billion pounds of molybdenum.
By dollar value, slightly more than half of the value is from copper, with the remainder split roughly equally between gold and molybdenum. Byproducts of silver, rhenium, and palladium metals would also be recovered.
Fisheries
Bristol Bay is home to the world's largest salmon run. All five Eastern Pacific species spawn in the bay's freshwater tributaries. Commercial fisheries include the world's largest sockeye salmon fishery. The Kvichak River has the single largest red salmon run in the world. The Kvichak drains from Lake Iliamna, which is downstream of the deposit. Along with herring and other fisheries, salmon account for nearly 75% of local jobs.Sport fishing is another important local industry. Many lodges cater to sport fishermen exploiting the salmon and trout populations in the freshwater tributaries. Freshwater species include humpback whitefish, Dolly Varden trout, Arctic grayling and Rainbow trout.
Seasonal subsistence harvesting of salmon and year-round subsistence harvesting of freshwater fish is a critical part of life for rural residents, most of whom live downstream of the mine site.
Human populations
The Pebble site is within Lake and Peninsula Borough, about 1,600 inhabitants as of United States Census, 2010, adjacent to the Bristol Bay Borough of about 1000 inhabitants and the Dillingham Census Area, 4,800 inhabitants. Some 7,500 people live largely rural lifestyles within or near the area downstream of the Pebble site. The populations of Lake Clark National Park and other parts of the Bethel Census Area are upstream of the site or in a different watershed.The populations in the area rely heavily on wild resources for subsistence, harvesting moose, caribou and salmon. Wild resources play an important part in the region's cultural heritage.
Alaska Native Culture: There are more than 30 Alaska Native Tribes in the region that depend on salmon to support their traditional subsistence ways of life, in addition to other inhabitants and tourists in the area. “If the Pebble mine is developed, the subsistence culture of thousands of people who live in the Bristol Bay region will be threatened”
History
Discovery
In 1987 Cominco Alaska Exploration collected mineralized surface samples at the Pebble site from color anomalies visible from aircraft. Geologist Phil St. George was credited with the discovery. He led early exploration efforts, drilling out the first half billion tons of the deposit. The first two exploration holes were drilled in 1988; in 1989 twelve more drill holes, soil sampling, and geophysical surveys indicated that the Pebble West occurrence was part of a large copper porphyry system. CAE continued drilling and other work through 1992, with a second drill campaign in 1997, with the resource doubled from 500M short tons to 1B short tons.In 2001, Northern Dynasty Minerals, Ltd. optioned the property from Teck Cominco, the successor to CAE's parent company. Northern Dynasty Minerals began exploration in 2002, which continued through 2013. In 2005, Northern Dynasty discovered the Pebble East deposit and acquired 100% ownership of the Pebble mining claims.
Project funding
In 2008, $140 million was budgeted and approximately of additional drilling was completed.In 2009, $70 million was budgeted, to complete a preliminary feasibility study, or "prefeasibility" study, and to prepare the project for permitting.
In 2010, $73 million was budgeted towards the pre-feasibility report, environmental studies, and various administrative and community-relations work. Applications for development and operations permits were not planned until after 2010.
For 2011, $91 million was budgeted to complete the pre-feasibility study, leading to permit applications in 2012. Environmental and engineering studies including of drilling to decide on mine design and a complete environmental baseline.
Project particulars
Project ownership
The land is owned by the State of Alaska. Pebble Mines Corp. holds mineral rights for of the area, an area that includes the Pebble deposits, as well as other, less explored, mineral deposits. A sequence of mining companies and partnerships have owned the Alaska mining claims at and around Pebble since the initial claim staking by Cominco in 1987.Pebble Limited Partnership : The Pebble Limited Partnership was once one of the largest multinational mining corporations made up of London-based Anglo American, along with Northern Dynasty Minerals, a junior mining company headquartered in Canada. After a few investors walked away, Northern Dynasty was the only company left seeking development.
The Pebble Limited Partnership is now 100% owned by The Northern Dynasty Partnership, which is a wholly owned Canadian-based subsidiary of Northern Dynasty Minerals, Limited.
Three of the world's largest mining companies purchased shares of Northern Dynasty or became partners in the Pebble Limited Partnership through obligations to fund exploration and development. All have since divested their interests.
Mitsubishi Corporation sold its 9.1% interest in Northern Dynasty Minerals in 2011.
Anglo American, a London-based mining company, struck a deal with Northern Dynasty to earn a 50% interest in a newly created Pebble Limited Partnership, the other 50% belonging to Northern Dynasty; between 2007 and 2013 Anglo American spent over half a billion dollars on the project. In December 2013 Anglo American walked away from the project, losing its 50% interest, which reverted to Northern Dynasty Minerals Limited.
Rio Tinto Group, through its wholly owned subsidiary Kennecott Utah Copper purchased, for 87 million dollars, a 9.9% ownership of Northern Dynasty Minerals Limited in July, 2006, and in 2007 doubled that to 19.8% ownership, for an additional 94 million dollars. In April 2014, the Rio Tinto Group gifted its shares, worth only approximately 18 million by then, to two Alaskan charitable foundations.
Northern Dynasty is one of several public mining companies controlled by Hunter Dickinson, a Vancouver-based Canadian mining corporation.
All but one of Hunter Dickinson Corporation's board members are also on the Northern Dynasty board. Most of the senior management of Northern Dynasty also hold senior management positions at Hunter Dickinson Corporation.
As reported on February 13, 2019, Kopernik Global Investors beneficially owns 6.17% of Northern Dynasty Minerals, which is an increase of 11% in their ownership stake from their prior reported position reported in February, 2018. Based on filings, Kopernik has held a position in NAK since at least as early as 2015, when they owned 19.99%.
Economics
Pebble is the largest known undeveloped copper ore body in the world, measured by either the amount of contained metal or the amount of ore.Northern Dynasty estimated that Pebble contains over $300 billion worth of recoverable metals at early 2010 prices.
A report released by Northern Dynasty in 2011 predicted profits for mine owners from a large-scale open-pit mine at Pebble, given appropriate assumptions about construction costs, scale, lifetime, metal prices over that lifetime and the mine design plan.
The study assumes a slurry pipeline will deliver ore concentrate from the mine to a new port on Cook Inlet, and that trucks will haul ore concentrates to Cook Inlet.
The plan expected the mine to return the initial capital investment in 3.2 years, employ over a thousand people for the first 25 years and provide a lifetime 23.2% pretax internal rate of return. The expected pretax cash flow was approximately $2 billion per year for much of the mine life and significantly more during the later years. The report states that 58% of the ore resource will remain at year 45.
Permits
Northern Dynasty has applied for water rights permits to Upper Talarik Creek and the Koktuli River for use in mining. Altogether, Northern Dynasty has applied for rights to about of ground and surface water per year, about four times the annual throughput of drinking-quality water at the Anchorage Waste and Wastewater Utility.In April 2017 Northern Dynasty reported that it had received notice of approval of a Miscellaneous Land Use Permit from the Alaska Department of Natural Resources for ongoing activities at Pebble.
Studies
Site-specific baseline data and scientific studies of potential environmental and social effects have been and are being conducted by the project operators and their consultants. These studies address water quality and other concerns. Among these are:- quantification of Acid mine drainage - the chemical stability and weathering products of the tailings generated by the mine, as well as of the newly exposed and blast-fractured rocks within the proposed mine.
- seismic risks to the impoundment systems designed to contain the tailings and intended to control their chemical behavior in perpetuity.
- the effects of road and bridge construction on fish habitat.
The federal Environmental Protection Agency began conducting a scientific review of the Bristol Bay watershed in 2011 focused on the Nushagak and Kvichak river drainages, in response to petitions from tribes, commercial fishing organizations, and other organizations opposed to Pebble. As of February 2011, the report was expected to reach the public-comment stage in late 2011.
The U.S. Army Corps of Engineers released its final environmental impact statement for the Pebble Mine project in July 2020, concluding that the project would not lead to "long-term changes in the health of the commercial fisheries in Bristol Bay," under normal conditions. After a preliminary draft of this final statement was sent to federal and state agencies, many other scientific and administrative groups critiqued this conclusion. The U.S Fish and wildlife Service scientists stated that the E.I.S. did not consider habitat destruction that could lead to destruction of salmon stocks in Bristol Bay. The legal director of Trustees for Alasa, a nonprofit public interest law first, indicated that the report was "lacking and thoroughly inadequate." Other critics noted that the Corps of Engineers did not account for earthquake or volcanic risks, a significant omission due to Alaska's status as the most seismically active state. A 2019 failure of an iron mine in Brazil killed over 250 people under similar conditions.
Possible mining plan
The mine itself would be an open-pit mine a mile square in area and a third of a mile deep. Ponds would be dammed to contain tailing, including some toxic materials. A 165-mile natural gas pipeline would be constructed to provide power for the operation, as well as 80 miles of road and pipeline to transport the mined concentrate to Cook Inlet. Operating the mine would use and impound large amounts of surface water. The roads would carry fuel, industrial chemicals and supplies.Pebble East would most likely be an underground mine.
Pebble would be similar to existing large copper porphyry mines such as Chuquicamata, Bingham Canyon and Ok Tedi, although the environmental setting and various technical considerations of Pebble distinguish it from these desert and tropical examples.
Development and construction would consume years and cost billions of dollars. Required infrastructure includes miles of roads, bridges and powerlines with pipelines for fuel and rock slurries.
Design possibilities include: construction of a port on Iniskin Bay of Cook Inlet with a two-lane freight road roughly long built along the north side of Lake Iliamna between the mine and the new port; trucks hauling ore concentrate to the port; pipelines along the road to carry fuel to the mine and a slurry of metal concentrate to the port. The slurry would be dewatered at the port before being shipped to a smelter, with a pipeline returning the water to the mine. Power to operate the mine would possibly come from a combination of overhead powerlines and a submarine cable across Cook Inlet.
Feasibility studies were prepared by Pebble Mines Corp. The company expected to apply for permits in 2012 at the earliest.
Project Timeline
In reaction to the mine proposal, ‘Save Bristol Bay,’ started by the local community and environmentalists, has been underway for 10 years.2010: Nine Bristol Bay Tribes, commercial fisherman, and sportsman requested the US Environmental Protection Agency to enact the 404c Environmental Assessment study under the Clean Water Act. The EPA states, “Section 404 authorizes EPA to prohibit, restrict, or deny the discharge of dredged or fill material at defined sites in water of the United States whenever it determines, after notice and opportunity for public hearing, that use of such sites for disposal would have an unacceptable adverse impact on one or more of various resources, including fisheries, wildlife, municipal water supplies, or recreational areas.”
2012:Due to the above request, the EPA issued two drafts of the Environmental Assessment, concluding that the proposal for the Pebble Mine would negatively impact the Bristol Bay salmon. Public input strongly agreed, with over 1 million comments supporting the EPA’s findings and scientists further verifying the data.
2013: The Alaska Department of Natural Resources signed and adapted a Determination of Reclassification and Plan Amendment to the Bristol Bay Area Plan. This plan increased the amount of land classified Wildlife Habitat and Public Recreation in the region.
Also this year, the final Bristol Bay Watershed Assessment was released, confirming that the Pebble Mine could not be operated without impacting Bristol Bay and harming salmon. With this news, Anglo American, one of the first and major investors of the Pebble Mine, pulled out its investment in the project.
2014: The global mining giant Rio Tinto gifted its stake in the mine to two Alaskan Charities, pulling its investments from the project.
2015: EPA released its Proposed Determination suggesting to limit mining in the Bristol Bay region due to the irreversible and detrimental impacts it will have to the local salmon ecosystem. After its release, 89.5% of the country was in support of strong protections for Bristol Bay.
2016: The Inspector General came out in support of the EPA’s Watershed Assessment findings, ultimately encouraging limiting mining due to its unavoidable impact on the salmon wildlife in Bristol Bay, affecting both the natural ecosystem and the economic wellbeing of the area.
2017: After a meeting between the EPA Administration and the CEO of Northern Dynasty, litigations are settled and the EPA agrees to begin proceedings to withdrawal the Proposed Determination act. Developers move forward with a plan for permits. In July, after the EPA proposes to withdrawal Proposed Determination, the Pebble Limited Partnership submits permits to the United States Army Corps of Engineers, the key agency in charge of reviewing the permit, laid out in a 3-4 timeline. EPA announces to not withdrawal the BBWA.
2018: Due to increased input of concerns for the Bristol Bay fishery because of Pebble Project, EPA decides to suspend withdrawal of Proposed Determination. USACE decides to gather more information regarding the impact to area's fish and natural resources.
2019: EPA submits comments to the USACE Environmental Impact Statement saying that the document underestimates the environmental impacts.More than 700,000 comments are posted in opposition to the Pebble Project. Later, the Proposed Determination is revoked, saying the five-year old document does not fully consider all information, including the Pebble Limited Partnership's project plan and the additional information considered during the USACE permit process.
2020: In July, the U.S. Army Corps of Engineers finds in a final environmental analysis that the operation of a Pebble Mine "would not be expected to have a measurable effect on fish numbers" in the Bristol Bay watershed.
Controversy
The controversy over the proposed Pebble mine centers largely on the potential risk to the watershed, salmon and other fisheries. Mining opponents claim that the mine poses a significant and unacceptable risk to downstream fish stocks, and could cause an environmental disaster if built. Mining proponents claim that the mine can be developed and operated without significantly harming Bristol Bay area fish.A steady stream of electoral, legislative, and legal challenges to possible future Pebble mine development are lodged in Alaska. Some of these assert that even the drilling and other scientific investigations conducted to date have caused significant adverse effects to the land and wildlife near the Pebble site.
Pebble has been a major issue in Alaska politics since the mid-2000s; national environmental and sport-fishing organizations are involved, while national publications cover the issue.
The New York Times reports that, as of 2020, public opinion polls in Alaska indicate more opposition than support for the mine. In the local area near the proposed mine location, anti-mine sentiment is even stronger. In 2006 one poll reported 28% of Alaskans in favor of and 53% opposed to Pebble and another reported 45% of Alaskans in favor and 31% in opposition. A poll of Bristol Bay residents reported 20% in favor and 71% opposed.
Fifty-seven percent of Alaskan voters in a 2008 statewide election voted against a ballot measure that would have essentially outlawed the project and perhaps similar developments elsewhere in Alaska.
Organizations including the Resource Development Council, Alaska Mining Association, and the Alaska Chamber of Commerce support the project. The proposal has strong support among statewide elected officials.
Opposition to the proposal was led by organizations including; the Renewable Resources Coalition, local native groups, commercial and sport fishing organizations, and conservationist groups. Deceased Senator Ted Stevens, a strong proponent of other resource extraction projects, in 2007 expressed opposition to the Pebble proposal.
In April 2009, a Native delegation from the Bristol Bay region attended the annual shareholder's meeting of Anglo American, the major mining company behind the Pebble project. The delegation met with Cynthia Carroll, CEO of Anglo American, claiming that the Bristol Bay watershed is no place for an open-pit mine.
Multiple UK jewelers pledged not to buy gold from the Pebble mine if it is built, joining several American jewellery retailers and manufacturers who had done the same in 2008.
The Natural Resource Defense Council and other well known groups and figures have opposed the construction of the mine. In an effort to stop or pause the construction of the mine, the NRDC has created a petition that now has more than a million signatures. The environmental justice nonprofit, Earthworks, has more than 100 gold buyers who have agreed to boycott gold found in the Pebble Bay Mine. These retailers include Tiffany & Co, Jostens, and Zales along with others.
Arguments against the proposal
- Opponents to the mine point out that it is about jobs—current sustainable fishing versus the time-limited mining employment that the mine will generate.
- The fish in the watershed, and the wildlife that depend on them, are too important to risk in exchange for the mine's economic benefits.
- Accidental discharge of process chemicals and byproducts, heavy metals, and acid mine drainage to the environment are concerns in mine design and operation. Heavy metals are mobilized by acids. Downstream salmon and freshwater fish species are vulnerable to mine-generated pollutants. A threat to the fisheries would amount to a threat to the regional subsistence lifestyle.
- Hard-rock mining already has a notable track record in terms of the permanent and costly legacy of heavy-metal-laden acidic leachate that continuously flows from inactive, depleted old mine sites. According to the EPA, mining has contaminated portions of the headwaters of over 40 percent of watersheds in the western continental U.S., and reclamation of 500,000 abandoned mines in 32 states could cost tens of billions of dollars.
- A recent study of 25 modern large hard-rock metal mines compared water quality outcomes with environmental impact statement predictions from the permitting stage. 76 percent of the 25 mines violated water quality standards in releases to either surface or groundwater. In this study "violated water quality standards" does not necessarily mean that the mines failed to abide by their permits. When the 15 mines with high-acid drainage, high-contaminant leaching potential and proximity to ground water are considered separately, this number is 93%.
- A report commissioned by opponents criticizes for community, worker safety, public health, and environmental problems at their mining operations in South Africa, Zimbabwe, Ghana, Mali, Ireland, and Nevada and notes the difference between the previous owner's stated corporate goals and their actual corporate performance.
- Groundtruthtrekking.org claimed that earthquake hazards in the area are poorly known.
Economic
Arguments for the proposal
Economic
- The mine and supporting activities would provide significant tax revenue to the state. The State of Alaska predicts that direct mining tax revenue, even without Pebble, will be one of the most important sources of non-oil tax revenue.
- The mine will create well-paying jobs in an increasingly poverty-stricken region—a 2007 estimate indicated roughly 2,000 jobs for construction, dropping to 1,000 permanent jobs during the 30- to 60-year expected lifespan of the mine. However, the current expected mine life has been decreased to 20 years following changes to the development plan in 2018. Also, the recent and well-documented trend towards automation of mining means that actual employment figures will be substantially lower than those quoted in 2007. Automation of mines will further increase in the future.
- The mine would provide a domestic resource of raw materials lowering the United States reliance on foreign sources.
Environmental
- Protection of the environment and fisheries will be ensured by the stringent environmental review and permitting process, including an EIS, that is required before development is allowed.
- Much of the poor environmental track record of mining occurred before current technologies and regulations.
- Northern Dynasty has a "no net loss" policy for fisheries.
Legal challenges
EPA action
In April 2013, EPA issued a draft assessment of the impact of proposed mining plans on the fisheries, wildlife and Alaska native tribes in the region.In January 2014, the final assessment was released. It questioned the future of salmon habitat should the mine be opened, but the agency did not use its authority to stop the mine. Pebble Partnership CEO John Shively severely criticized the EPA assessment, saying it was unscientific and that it sought a predetermined outcome. A few days after the release, Democratic U.S. Senator Mark Begich openly opposed the mine, breaking with the other members of the Alaska congressional delegation, Republican Senator Lisa Murkowski and Republican Representative Don Young.
In July 2014, before the project had submitted its EIS, EPA Region 10 proposed restrictions employing Section 404 of the Clean Water Act, restrictions that would effectively prohibit the project. This was the twelfth time the clause has been employed since the Act's passage in 1971.
On July 18, 2014, in a published statement, Pebble Partnership CEO Tom Collier said that the project would continue its litigation against EPA; noted that the EPA's action was under investigation by the Office of the EPA Inspector General and by the House Committee on Oversight and Government Reform; and also noted that two bills were pending in the US House and Senate seeking to clarify that EPA did not have the authority to preemptively veto or otherwise restrict development projects prior to the onset of federal and state permitting. Collier's statement also said that EPA's proposal was based on outdated mining scenarios that were not part of the project's approach.
On December 18, 2009, an appeal was filed in Alaska Superior Court contending that a decision in November 2009 by the Alaska Department of Natural Resources’ commissioner rejecting their challenge of a 2009 exploration permit was inappropriate. The suit contends that ADNR failed to give Alaskans adequate notice and opportunity to comment on the permit and that it failed to consider the appeal. Trustees for Alaska is pursuing the suit for Nunamta Aulukestai and two Bristol Bay residents.
In May 2017 the Pebble Partnership and EPA jointly announced they had reached a settlement agreement to end the legal dispute regarding the EPA's Proposed Determination issued under CWA 404 in July 2014. The Agreement called for the EPA to withdraw the regulatory action while the Pebble Partnership agreed to terminate outstanding lawsuits brought against the EPA.
In July 2017, the EPA sought comments on a proposal to withdraw its objections to the Pebble Mine based on the 1974 Clean Water Act.
In February 2018, the EPA changed plans to withdraw restrictions on the Pebble Mine on the basis of the Clean Water Act. Instead, Administrator Pruitt offered support of the fishery. The decision is not final and is open to further public comments.
On July 30, 2019, the EPA withdrew their preemptive proposed determination to restrict use of the pebble deposit area as a disposal site.
Nondalton Tribal Council et al. v. State of Alaska DNR
Six federally recognized tribes filed Nondalton Tribal Council et al. v. State of Alaska DNR with the Alaska Superior Court on May 5, 2009. The suit challenged the validity of the 2005 Bristol Bay Area Plan, one of many Area Plans created and administered by the State of Alaska that, along with other State and Federal rules, define land status and the appropriate and legal uses of State land within the plan boundaries.The Bristol Bay Area Plan applies to about of state-owned uplands and lands beneath rivers and lakes in the Bristol Bay drainages, including lands at and in the vicinity of the proposed mine. The plan also covers about of state-owned tide and submerged lands.
The suit alleged that the 2005 BBAP, which replaced the original 1984 version, drastically altered, without legal justification, the land-use designations, classifications and acreages defined in the 1984 plan; and that the 2005 plan failed to provide adequate protection for subsistence resources, sport hunting and fishing, wildlife habitat and other renewable resources. If successful, the suit will require ADNR to write a new area plan, a many months-long process involving much public input and review of draft versions, although ultimately, approval of an area plan is decided by the Commissioner of Natural Resources, an appointee of the Governor. As of Aug. 7, 2009, DNR had not filed an answer to the complaint.
Nunamta Aulukestai et al. v. State of Alaska DNR
Nunamta Aulukestai et al. v. State of Alaska DNR, was filed in Alaska Superior Court on July 29, 2009, by Trustees for Alaska on behalf of the Bristol Bay Native organization Nunamta Aulukestai, former Alaska First Lady Bella Hammond, original Alaska Constitutional Convention delegate Victor Fischer and other individuals. The suit seeks "Declaratory and Injunctive Relief," asserting that the Alaska Department of Natural Resources repeatedly violated Section VIII of the Alaska Constitution, which specifically provides that there shall be, "...no disposals or leases of state lands...without prior public notice and other safeguards of the public's interest..."The plaintiffs are seeking, among other things, an injunction voiding the project's existing permits, including water-use permits. The requested injunction was specific to Pebble permits and would not directly apply to other mining projects. The suit alleges that ADNR's "pattern of permitting," is defective because it was not sufficiently rigorous in determining that issuing a permit would best serve public interest, as demonstrated by a lack of documented scientific studies and by lack of public review and input, prior to issuing permits. A Declaration by one of the plaintiffs references the Commentary on Article VIII on State Lands and Natural Resources of December 15, 1955; "As requirements change and many tasks become routine, appropriate modifications can be made in procedures if rigid requirements are not specified in the Constitution itself."
The suit also alleges that significant, and documented, adverse effects on land, water, and wildlife have already occurred as a result of drilling and other exploration activities at Pebble since 1989. In late 2009 the presiding judge rejected a State of Alaska motion to dismiss the case and also denied a motion for a preliminary injunction to stop mining exploration. A Petition for Review on the preliminary injunction decision was filed with the Alaska Supreme Court.
In July 2010, the Alaska Superior Court ruled that Nunamta Aulukestai et al. v. State of Alaska DNR would proceed to a non-jury trial in December 2010. The ruling dismissed one of the six claims in the lawsuit and limited the scope of the upcoming trial to the Pebble permits, rather than to the Alaska mineral exploration permitting system in general.
Political actions
Two bills designed to outlaw large-scale mining in the Pebble area were introduced in the Alaska state legislature in 2007; both stalled in committee. A third attempted piece of legislation was the Alaska Clean Water Initiative, 2008. It was voted down after months of high-profile public debate, heavy advertising, and a series of judgements by the Alaska State Supreme Court. The measure remained an active public issue; in June 2009 the state of Alaska's Alaska Public Offices Commission reported violations of campaign funding laws during the contest.Then-Governor Sarah Palin was a strong supporter of the project and faced criticism about her opposition to the initiative, the involvement of state government and the intended use of a $7 million federal earmark to facilitate it. Ethics questions were raised about her and her husband Todd's participation.
Jay Hammond State Game Refuge
A proposal to the Alaska Department of Fish and Game to create a fish refuge in the Koktuli and Talarik watersheds was supported by mine opponents and opposed by Northern Dynasty. The Alaska Board of Fisheries voted to create a panel to study the proposal. Both sides claimed this as a victory. In March 2007 the Board voted to take no action on the proposal due to pending legislation.In January, 2007 Senate Bill 67, introduced by Senator Gary Stevens, of Kodiak, proposed the establishment of a State Fish and Game Refuge covering about of state land in the Kvichak and Nushagak drainages. It proposed that no uses incompatible with: fish and wildlife populations; commercial or subsistence food gathering; or recreation would be allowed in the refuge. The bill sought to close the refuge to new mining claims. Most significantly, the bill would have made illegal the storage or disposal of any quantity of, "industrial waste," thereby making it impossible to develop any industry, including mines, within the refuge. The bill died in the Senate Resources Committee.