The exam consists of 200 multiple choice questions written against the PMBOK specification and the PMP Code of Ethics. The exam is closed book; no reference materials are allowed. Twenty-five of the 200 questions on the exam are "sample" questions used to fine-tune the degree of difficulty and precision of the exam and as such are not counted for or against a test taker. These questions are placed randomly throughout the exam. The test taker is only graded on their proficiency on 175 questions. The numbers in parentheses describe the percentage of questions for each domain. Announced in June 2019, the PMP Examination Content Outline will undergo significant re-categorization, effective January 2021, which prescribe 3 all new performance domains:
People
Process
Business Environment
Item references
Each exam item has at least two references to standard books or other sources of project management. Most of the questions reference the PMI A Guide to the Project Management Body of Knowledge. The PMBOK Guide is currently in its sixth edition, and the PMP exam changed in March 2018 to align with the updated guide. The Project Management Framework embodies a project life cycle and five major project management Process Groups:
Initiating
Planning
Executing
Monitoring and Controlling
Closing
encompassing a total of 49 processes. Mapped to these five process groups are ten project management Knowledge Areas:
The processes of these knowledge areas are described by their inputs, tools and techniques, and outputs. The PMBOK also emphasizes the interaction and interdependence between different process groups. For example, the outputs from one process may be used by one or more other processes as inputs.
Purpose
Government, commercial and other organizations employ PMP certified project managers in an attempt to improve the success rate of projects in all areas of knowledge, by applying a standardized and evolving set of project management principles as contained in PMI's PMBOK Guide. In December 2005, the PMP credential was number 7 of ZDNet's10 best IT certifications. In 2012 the PMP credential was ranked as a top certification by CIO. In 2015, the PMP credential was ranked as the #4 certification by Global Knowledge, behind 3 Security certifications.
Examination process
The global network of Pearson VUE testing centers provides the PMP exam as a computer-based test. They also offer a paper-based option for locations with no nearby Prometric testing centers. The exam consists of 200 questions. 25 are pre-release items, which are not included in exam scoring. Prometric calculates the score based on the other 175 items. Each multiple-choice item has one correct answer and three incorrect answers. Candidates who take the computer-based test receive their results immediately upon completion. PMI also evaluates proficiency levels in each project management process group in 4 levels. Above Target, Target, Below Target, and Needs Improvement. Examiners provide these results to the candidate on a score report after the examination. Candidates who take paper-based tests receive their test results and score reports typically within 4 weeks. Research shows that the most difficult Knowledge areas of the PMP® exam are Quality Management, Integration Management, and Time Management.
PMI Audit
PMI conducts application audits to confirm the experience and/or education documented on certification applications. The purpose of the audit is to enhance the credibility of the certification program and of the certification holders. For each certification, a specified percentage of applications are randomly selected for audit.
Item writing
Item writing is an ongoing process at PMI, and they periodically add new four-choice questions and remove others. Item writers use the PMP Examination Specification to identify item contents and references to verify correctness. Individuals who are active in the field of PMP exam preparation may not participate in item writing.
Prerequisites to become eligible
Candidates must meet the prerequisites in one of the following groups to be eligible for PMP Certification:
Group A
Secondary degree
7,500 hours leading and directing projects
35 hours of project management education
Group B
Four-year degree
4,500 hours leading and directing projects
35 hours of project management education
Continuous credential requirements
Continuous credential requirements are also called CCRs. To maintain the PMP qualification, 60 professional development units must be earned over a three-year cycle, from activities such as researching, authoring articles, speaking on project management-related topics, or being engaged full-time in project management. Credential holders may earn PDUs towards the maintenance of their credential through formal academic courses or courses offered by a provider. However, these are only two of the five categories of PDU earning opportunities in which a credential holder may participate. Effective 1 December 2015, CCRs will be updated to align with the employer-identified skills depicted in the PMI Talent Triangle, a combination of technical, leadership, and strategic and business management expertise, to ensure credential holders are equipped with skills relevant in a continually changing business environment.
Credential value
The US Department of Education and the National Science Foundation have deemed all United States professional certifications to be at level 50 in the Mapping The World of Education, Comparable Database System. The Level 50 code addresses "Postsecondary Programs and Awards of No More Than 2 Years. Programs and awards that are designed to represent no more than 2 years of study; constitute postsecondary education as operationally defined in CDS; and are not second programs and awards."
certifications could be seen as a competitor of Project Management Professional. In general, the US and American countries prefer PMP, and UK, Australia and Europe prefer PRINCE2. Asia, Africa and the Middle East area have no strong preference for one or the other. The organizations behind these two certifications acknowledge each other's existence in their advertising material and attempt to position themselves as complementary products – PRINCE2 as a methodology, and the subject of the PMP certification as a guide or standard – which can be used alongside each other. In practice, companies and practitioners choose one system or both due to the project environment, their geographical location and costs involved.