Pune Metro


Pune Metro is a metro rail based rapid transit system under construction to serve Pune Central and the areas of Pimpri & Chinchwad. As of December 2019, the system comprises 3 lines with a total length of 54.58 km. The 16.59 km Line 1 PCMC BhavanSwargate will be elevated between PCMC Bhavan to Range Hills, from where it will run underground. Line 2 will run from Vanaz to Ramwadi covering a distance of 14.66 km on an elevated viaduct. Lines 1 and 2 are expected to be operational in 2021. The 23.33-km elevated Line 3 will run from the Rajiv Gandhi Infotech Park in Hinjawadi via Balewadi to Civil Court. All three lines will align at the Civil Court interchange station.
As of December 2019, the foundation stone for Lines 1,2,3 are laid by Prime Minister of India. The first two lines with a combined length of 31.25 km and are being implemented by the Maharashtra Metro Rail Corporation Limited, a 50:50 Joint Venture of the State and Central Governments. Line 3 will be implemented by the Pune Metropolitan Region Development Authority and the Joint Venture between Tata Realty and Siemens on a Public–Private Partnership basis. On 18 December 2018, PM Modi laid the foundation stone for Line 3. Construction on line 3 was started in January 2020.

Background

has witnessed enormous industrial growth since 2000. Rapid urbanisation in the recent past has put the city's travel infrastructure to stress. With an increase in small scale, medium scale as well as heavy industries, the traffic in the city is rising at alarming rates. The roads in the city, while being narrow, cater to various kinds of vehicles simultaneously. Such roads, at an optimum can carry 8,000 peak hour peak direction traffic. Being a densely populated area, Pune's traffic needs cannot be met by road-based system and additional flyovers. Pune Mahanagar Parivahan Mahamandal Ltd., the public transport provider that operates buses and BRT services in Pune and Pimpri & Chinchwad, has failed to meet the transport needs of the twin cities. This has mainly contributed to an unhealthy growth of vehicles on roads. According to reports published in April 2018, the number of vehicles registered in the city stands at 3.62 million surpassing the population of the city. Such a high density of traffic has put the urban transport system in Pune under severe stress leading to longer travel time, increased air pollution and rise in number of road accidents. In light of this, a strong public transport system has been discussed in Pune since the early 2000s. Initially, Skybus Metro, a prototype suspended railway system developed by the Konkan Railways, was being considered on a 7.5-km route between Swargate and Pune Railway Station. However, following a tragic mishap in September 2004, the project took a back seat.
On 15 August 2008, the preparation of detailed project report work was undertaken by the Delhi Metro Rail Corporation and submitted their report. In 2010, the Pune Municipal Corporation delayed submitting the proposal to the Union government to make provisions in the annual budget for the project. The initial project consisting of two lines with a combined length of 31.25 km was approved by the State in June 2012. However, it received the final approval from the Central Government only on 7 December 2016, almost 4.5 years later. PM Narendra Modi laid the foundation stone on 24 December 2016. MahaMetro is implementing the two lines, viz. the partly elevated and partly underground Line 1 from Pimpri & Chinchwad to Swargate and the completely elevated Line 2 from Vanaz to Ramwadi. MahaMetro expects to complete the project in 2021. Days after the foundation stone for the MahaMetro lines was laid, PMRDA approved Line 3 on 29 December 2016. The project will be implemented by PMRDA on a PPP basis. It was approved by the State on 2 January 2018 and by the Centre on 7 March 2018.

PMRDA">Pune Metropolitan Region Development Authority">PMRDA and MahaMetro">Maharashtra Metro Rail Corporation Limited">MahaMetro

The Pune Metropolitan Region Development Authority had proposed to take over the Metro project, which was declined by the PMC and PCMC. The opposing representatives said that the Metro rail is going to be implemented by Special Purpose Vehicle. Instead, the civic bodies suggested inclusion of PMRDA in the SPV to increase the reach of the Metro rail. PMRDA will execute only Line 3 i.e. Shivajinagar to Hinjewadi line. They will follow PPP model for the project. For the implementation of the initial two lines, the former Nagpur Metro Rail Corporation was reconstituted to form Maharashtra Metro Rail Corporation Limited.

Network

In August 2019, Mahametro announced that the Vanaz to Ramwadi corridor would be called the Aqua Line as it passes through the Mula-Mutha riverbed. The PCMC Bhavan to Swargate corridor would be named the Purple Line. The agency stated that the colour purple was chosen because it represents happiness.

MahaMetro lines

Purple Line (PCMC Bhavan">Pimpri-Chinchwad Municipal Corporation">PCMC Bhavan – [Swargate])

Line 1 will run from PCMC Bhavan in Pimpri to Swargate. The 16.59-km line will be elevated till Range Hills with 9 stations and will further go underground up to Swargate with 5 stations. This route will go via Nashik Phata, Khadki and Shivajinagar. The maintenance depot for Line 1 will be located near the Range Hills station on the land acquired from the College of Agriculture.
The 5.09-km long underground section of line 1 from Agriculture College to Swargate is being carried out in two packages: 1. Agriculture college to Budhwar Peth; 2. Budhwar Peth to Swargate. Mahametro has invited separate tenders for these two packages each involving the design and construction of the stations and associated tunnels. Following firms have submitted the bids: L&T, Tata projects-Gulermark JV, Shanghai Tunnel Engineering, J Kumar, Afcons.
The underground station at Swargate will be a part of a multimodal transit hub integrating intra- and inter-city bus services run by PMPML and MSRTC, autorickshaws, as well as parking facility for private vehicles. The project is being undertaken by MahaMetro on a PPP basis at a cost of. In August 2018, J Kumar Infraprojects was awarded the contract for the hub.

Alignment revision

In April 2018, MahaMetro began construction in the Kharalwadi and Morwadi area on the elevated stretch of the line between PCMC Bhavan and Range Hills. For the construction, the barricades on the newly built BRTS lane were removed. MahaMetro claimed it to be temporary and revealed that an earlier plan to construct the pillars on the footpath was dropped due to utility lines running below the surface. However, the PCMC conducted trials on the BRTS route in April 2018 and intended to launch services soon and therefore ordered MahaMetro to stop construction. As a result, MahaMetro revised the alignment in May 2018, one year after construction began on the line.

Proposed extensions

Ever since the Centre gave its nod for the first two metro corridors, there has been a demand for extending Line 1 from PCMC Bhavan to Bhakti Shakti Chowk, Nigdi. In light of these demands, PCMC decided to prepare DPRs for the extensions in their respective jurisdictions and bear the cost for it. However, on 18 January 2018, MLA and Pune's Guardian Minister Girish Bapat announced in his speech at the ground-breaking ceremony for the first metro station at Sant Tukaram Nagar that work on the extension would be taken up only in the "second phase" of the project without mentioning a timeline. As a result, confusion ensued and social organizations in Pimpri & Chinchwad held a token hunger strike in February 2018 to press their demand for extension. In April 2018, PCMC earmarked a sum of so that MahaMetro could prepare a DPR for the Nigdi extension. In October 2018, MahaMetro submitted the DPR for the 7-km long extension to the PCMC. The 7-km long extension is estimated to cost between and.
There have also been demands for extending the line from Swargate to Katraj. The PMC decided to prepare a DPR for the extension on 4 January 2018. The DPR is being prepared by MahaMetro. However, due to the presence of several flyovers on Pune-Satara road, the extension might be diverted via Market Yard on an elevated viaduct.

Aqua Line (Vanaz">Kothrud">Vanaz - Ramwadi">State Highway 27 (Maharashtra)">Ramwadi)

Line 2 will run from Ramwadi to Vanaz via Mangalwar Peth and Deccan Gymkhana. The elevated line will cover a distance of 14.66 km and will have 16 stations. It will connect with Lines 1 and 3 at the Civil Court interchange station. The maintenance depot for Line 2 will be located near the Vanaz station on the former garbage depot land.

Alignment revisions

In November 2015, a revised proposal submitted to the PMC by the DMRC suggested realigning the route along the Mutha river as against the earlier alignment along the Jangali Maharaj Road, Pune to reduce the project cost. The route length now is 14.66 km, reducing the length by 260 m. The alignment of Line 2 was once again revised in January 2018 due to Indian Railways' expansion plans.
In September 2018, the National Monument Authority rejected permission sought by MahaMetro to build near Aga Khan Palace in the prohibited area of the monument. No construction is permitted within 100 m of a monument under AMASR Act, 1958. This led to a third revision in the alignment of line 2, for which MahaMetro has suggested the PMC three alternative alignments for the Civil Court to Ramwadi section of Line 2 near the monument:
  1. A diversion from Kalyani Nagar which would increase route length by 0.06 km and the cost by. However, this would involve rehabilitation of several people as it is a densely populated are as well as defence and acquisition which is a time-consuming process.
  2. A diversion from Bund Garden station along the southern bank of the Mutha river increasing the length of the route by 0.563 km and the cost by. However, this route would hit the ridership from the northern parts of Kalyani Nagar and would also raise environmental concerns as the route will pass along the river.
  3. Given the possible difficulties in implementing the first two option, MahaMetro has recommended the third alternative involving a diversion from Gunjan Chowk which would increase the route length by 0.92 km and the cost by.

Proposed extensions

Although the currently under construction line will terminate at Vanaz in the west, it was decided to extend the line till Chandani Chowk. The decision came in February 2018, when a longstanding dispute over the erstwhile garbage depot land in Kothrud was resolved by allotting it to MahaMetro for the development of a metro depot for Line 2. A permanent exhibition depicting the life of Shivaji - the Shivsrushti project - which was also planned at the same location, will instead be built on the land reserved for a biodiversity park near Chandani Chowk. The station at Chandani Chowk will bear the name of the Shivsrushti project. A DPR is being prepared for the 2-km long extension and an additional station between Vanaz and Shivsrushti at Bhusari Colony is being contemplated. MahaMetro will bear the costs for this extension. There have been demands for the extension of the line from Ramwadi to Wagholi as well as a connection to the Pune International Airport.

Rolling stock

for the metro will be procured by floating competitive international tenders. The company bidding the lowest will be awarded the contract. The company will manufacture 104 coaches to form 26 trains each with four coaches. The rolling stock will have the following specifications:
In August 2019, Mahametro announced that Titagarh Firema had won the bid to supply 102 aluminium bodied coaches for the project.

Cost

The MahaMetro lines were estimated to cost, a hike of from the 2014 estimate. The PMC and PCMC will each bear 5% of the cost, while the state government and the central government will each bear 20% of the cost. The remaining 50% will be obtained as loans. The state government's share of 20% includes the expenses of acquiring land, including government land, at market price. The delay in the execution of the project has resulted in an upward revision of ₹ 700 crores in the draft civic budget for 2015-16 presented by Municipal Commissioner Kunal Kumar.
On 17 September 2016, the central government had approved a proposal seeking loan of from the World Bank and China-based Asian Infrastructure Investment Bank for the project. However, as of March 2018, MahaMetro was negotiating loans worth and from the European Investment Bank and the French Development Agency. On 28 January 2019, the Department of Economic Affairs on behalf of the Centre and the AFD signed a facility framework agreement to extend bilateral funding of.

Budgetary allocations

Line 3 [Hinjawadi] (Hinjewadi Phase-I,II,III. Including [Maan, Pune] & [Bhoirwadi]) – Civil Court">Shivajinagar, Pune">Civil Court

Line 3 will run from Civil Court, Pune to Megapolis Pune in Hinjawadi. The 23.3-km line will be completely elevated and will have 23 stations and will align with the MahaMetro lines at the Civil Court interchange station. The construction will be taken up in two phases, the section between Hinjawadi and Balewadi is expected to be taken up first followed by the section between Balewadi and Civil Court, Shivajinagar. A metro car shed will be built in Hinjewadi. The MIDC will provide 55 acres of land in Hinjewadi for setting up a Metro rail depot.
The line will also connect to the multimodal transit hub planned along the National Highway 48 in Balewadi which will integrate the inter- and intra-city bus services and BRTS operated by the MSRTC and PMPML. The hub will be constructed on a PPP basis under the Smart City mission and is expected to cost. The hub will comprise a built-up space of including of commercial office space, parking space for 80 buses, 1942 cars and 3884 two-wheelers. As of October 2018, offers from international and national real estate developers have been invited for the hub and the PMC is in the process of land transfer to the executing agency, Pune Smart City Development Corporation Ltd..

Proposed extension

PMRDA has announced that the line would be extended from the Civil Court intersection up to Phursungi IT Park via Hadapsar. The DPR for the extension is being prepared by DMRC. This would add another 11.8 km of elevated corridor to the network and 12 additional stations.

Cost

The line is estimated to cost and will be implemented by PMRDA on a PPP basis. The private partner will bring in 60% of the funds, 30% in equity and 70% in debt, while the rest 40% will be provided together by the Centre, State and PMRDA. The Centre has already approved a sum of as viability gap funding, while the State will provide and PMRDA will come up with the rest. The private partner will build, operate and maintain the line for 35 years.
On 31 July 2018, the State government allotted 5.1 hectares of land with a market value of for Line 3. This land located in Balewadi will be monetized by the bidder for financial viability and forms a part of the costs to be borne by the State.

Fares

An integrated fare system has also been planned to facilitate seamless transfers, however, exact fares for the same travel distance will vary based on the operator. MiCard, the smart card currently being used on the bus and BRTS services run by the PMPML, will be used as the common mobility card on the metro services as well as parking facilities.

Issues

Delay in implementation

The citizens and city-based NGOs have regularly raised questions over the intention of the State governments as to whether they actually want to implement the project. The project was proposed way back in 2007 by the Chief Ministers of Maharashtra, but did not move ahead due to many reasons. The DPR was itself approved only on 12 June 2012. At an event in 2013 during his tour of the city, the Metroman E. Sreedharan blamed the people involved in planning and implementing the project for the long delay, stating that "Pune lost five valuable years in unnecessary discussions instead of executing the project."

Alignment issue

Initial plans were to build a few sections underground and the rest elevated. However, citizens of Pune did not want elevated routes as they felt that the roads could not bear the increased traffic that would result from the construction. Most roads were too narrow to accommodate the pillars of elevated routes. It was decided that all the routes in the city would be underground, although the map and the details of phases showed elevated routes. In November 2011, the State government declared that all the routes would be underground. However, in April 2012, the PMC declared that all routes will be as per the DMRC report, mostly elevated and partially underground in core city areas. On 27 May 2015, the then Minister of Housing and Urban Affairs stated that underground metro was not a feasible option and that Pune, like other cities, will have to get an elevated metro as suggested by the DMRC. But as per the city activists, elevated metro is not possible due to presence of some flyovers along the route of metro and narrow roads on the metro corridor, which will cause traffic congestion and interruption. To alleviate the confusion, Chief Ministers of Maharashtra announced that Pune will get "mixed-metro", as the alignment of some routes does support elevated sections.
Metro phase I was criticized by Pimpri-Chinchwad Citizens’ Forum, believing that the project will not benefit nearly 70 per cent area of Pimpri-Chinchwad, as it will not serve the Akurdi, Chinchwad and Nigdi stretch. Adding further, the citizens group supported their cause by stating that it would take another 5 years after phase II gets approval from Union Cabinet for metro to reach core PCMC area. Since infrastructure projects take a lot of time to get approvals, they fear metro will not reach Nigdi before 2025. Many architects and urban planners also vouch for Nigdi's role in transport management.

Environment interest litigation

In May 2016, an environment interest litigation was filed in the western zone bench of the National Green Tribunal against the realignment of Line 2 from Jangali Maharaj Road to the Mutha river bed. The litigants MP Anu Aga, Sarang Yadwadkar, Arti Kirloskar and Dileep Padgaonkar expressed concerns over free flow of the river being obstructed by the pillars supporting the 1.7-km stretch of the metro viaduct. In October 2016, the Biodiversity Monitoring Committee of the PMC reported that the metro project could be catastrophic for the riverbed ecology, corroborating the EIL. The NGT put an interim stay on metro construction in the river bed on 2 January 2017, days after the foundation stone was laid on 24 December 2016. The stay, however, was put on hold by the Supreme Court. Subsequently, after the MahaMetro was formed and became a respondent in the EIL, it unsuccessfully moved SC challenging the NGT's jurisdiction on the case. In October 2017, the NGT resumed the hearing and appointed an expert committee convened by the National Environmental Engineering Research Institute to study the impact of the metro project on the river bed. In January 2018, the report was submitted and stated that the construction would not damage the river. However, the case is still pending in the NGT. Since 1 February 2018, the NGT's western zone bench in Pune is unable to function following an SC order restricting single-member benches of the NGT from hearing cases. The case is expected to be heard in July 2018, when the circuit bench of the NGT will hear cases for three weeks in Pune. On 3 August 2018, the principal bench of the NGT cleared metro construction on the river bed. The clearance is subject to MahaMetro complying with the recommendations made by the three-member expert committee, which had concluded that the construction would not damage riverbed hydrology.

FSI debate

The DMRC had proposed 4 FSI on either side of the corridor to achieve greater population densification through vertical development of residential and commercial properties. The PMC will raise money for the metro and needed civic amenities to support the higher density. Furthermore, PMC hopes to increase the use of metro.
Some members of the planning committee have suggested that three FSI be granted not only within a 500-m radius along the metro corridor but also in the entire city. Members have suggested that the amount collected through the premium on additional FSI should be turned into an urban development fund. A 60% share of this fund should be used for the metro project, while 15% for the PMPML and high capacity mass transit road and monorail and 25% for developing basic infrastructure.
But as per several urban planners, NGOs and experts, the FSI introduction will have more drawbacks than benefits for the city.
  1. Even if half of the landowners along the metro corridor take advantage of the 4 FSI proposal, it will lead to 20 km2 of built up area in coming years, which is more than the total housing needs of Pune for the next 20 years.
  2. The PMC would raise from the sale of FSI whereas it needs just.
  3. In the area studied, most of the plots which could consume the 4 FSI were at the edge of the corridor away from the stations, while many plots next to the tracks and the stations would remain as they are, since they are too small to accommodate the extra FSI. This plan might backfire as the distance of these plots from the nearby metro corridor might encourage the residents to use private vehicles and thus, defeat the purpose of metro.
  4. Given the prevailing land costs, the new development that comes up will be of the "premium" category. Thus any new housing that comes up through this extra FSI will cater to the more affluent segment, which is the group least likely to use the Metro.
  5. The open space per capita in the city will be reduced to half or less of what it is at present. The space required for other public amenities like hospitals, schools, clinics etc. will also fall short since very few plots are large enough to come under the "amenity" space rules under which the landowners have to give small portion to the city for providing amenities.
In July 2018, the Department of Defence of the MoD notified height restrictions in a six-kilometer radius of the National Defence Academy and the Lohegaon airport. This area accounts for approximately 50% of the city's area. The notification restricts the construction of high-rise buildings and has made 4 FSI along the metro corridor under the transit-oriented development policy impossible.

Status updates

MahaMetro Lines

Project status updates on 16.59-km part elevated and part underground Line-1 from PCMC to Swargate and 14.66-km elevated Line-2 from Vanaz to Ramwadi.
Project status updates on 23.3-km elevated Line-3 from Hinjawadi to Civil Court.
The following routes have been proposed:
  1. Ramwadi - wagholi - Pune Airport
  2. Civil Court - Fursungi -Loni Kalbhor
  3. Swargate - Hadapsar
  4. Swargate - Khadakwasla
  5. SP Infocity Fursungi - Chhatrapatri Sambhaji Maharaj International Airport, Purandar, Pune