Rail gauge in Australia


Rail gauges in Australia display significant variations, which has presented an extremely difficult problem for rail transport on the Australian continent for over 150 years., there is of narrow-gauge railways, of standard gauge railways and of broad gauge railways.
In the 19th century, each of the Colonies of Australia adopted their own gauges. However, with Federation in 1901 and the removal of trade barriers, the short sightedness of three gauges became apparent. It would be 94 years before all mainland state capitals were joined by one standard gauge.

Rail gauges and route kilometres

A report by the Australian Government’s Bureau of Infrastructure, Transport and Regional Economics, and the Australasian Railway Association, estimated that as of September 2019 there were 32,894 km of heavy rail lines open and operational throughout the nation.
The three main railway gauges in Australia are 1067 mm narrow, 1435 mm standard, and 1600 mm broad; a slow progression towards unification to standard gauge has taken place since the 1930s.
About 4,000 km of 610 mm light railways in Queensland support the sugar-cane industry; they are not included in the following table.

History

Pre-construction uniformity

In 1845, a Royal Commission on Railway Gauges in the United Kingdom was formed to report on the desirability for a uniform gauge. As a result, the Regulating the Gauge of Railways Act 1846 was passed which prescribed the use of in England, Scotland and Wales and in Ireland.
In 1846, Australian newspapers discussed the break of gauge problem in the United Kingdom, especially for defence. In 1847, South Australia adopted the gauge as law.
In 1848, Governor of New South Wales, Charles Fitzroy, was advised by Secretary of State for the Colonies in London, Earl Grey, that one uniform gauge should be adopted in Australia, this being the British standard gauge. The recommendation was adopted by the then three colonies. Grey notes in his letter that South Australia has already adopted this gauge.
At this stage Victoria and Queensland were still part of New South Wales.
Since the Australian Overland Telegraph Line and under-sea cable communications with England did not open until 1872, communications between Britain and Australia before then were hampered by having to be conducted via sailing ship. The journey varied from about seven months on slower ships to about two and a half months on fast clipper ships. This had particular consequences for the selection of railway gauge in Australia.

Origins of the gauge muddle

At that time the private Sydney Railway Company had begun planning its railway line to Parramatta. The chief engineer of the company was Irish-born Francis Webb Sheilds. After his appointment in 1849, Shields initially stated a preference for but in 1850 he persuaded the company, which in turn asked the NSW legislature, to change to the Irish standard gauge of. This decision was endorsed by the NSW Governor, and Colonial Secretary Earl Grey in London agreed in 1851.
However, Sheilds and his three subordinates resigned in December 1850 when the company cut their salaries for financial reasons. After the interim appointment of Henry Mais, in July 1852 the company selected a new Scottish engineer, James Wallace, who preferred the British standard gauge. The Government was persuaded to make the change back to and in January 1853 they advised the company that the Act requiring would be repealed.
In February 1853 the other colonies were sent a memorandum advising them of the pending change and recommended they likewise adopt. In Victoria the memorandum was distributed to three railway companies and their responses were sought, with two replying and only one showing a distinct preference for. However the Melbourne and Hobson's Bay Railway Company asked for a determination from the government as it had prepared plans for both gauges and was due to send an order for locomotives and rolling stock to England by boat at the start of April. In reply at the end of March, the companies were told the colonial Victorian government preferred and the order was subsequently placed.
In July 1853, the Government of Victoria advised New South Wales that it would use the broader gauge and later appealed to the British Government to force a reversal of New South Wales' decision. Subsequently, the Melbourne and Hobson's Bay Railway Company opened the first railway in Australia in 1854, as a broad gauge line, and the South Australian Railways used the same gauge on its first steam-hauled railway in 1856.
Despite a request by the Secretary of State for the Colonies to reconsider this alteration, in 1855 the NSW Governor William Denison gave the go-ahead for the Sydney to Parramatta railway, which opened in September of that year.
Concerns over the gauge difference began to be raised almost immediately. At a Select Committee called in Victoria in September 1853, a representative of the railway company which had not replied to Charles La Trobe's earlier memorandum, reported a preference for, but when asked if Victoria should follow NSW he answered: "We must, I conclude of necessity, do so". In 1857, the NSW railway engineer John Whitton suggested that the short length of railway then operating in New South Wales be altered from gauge to to conform with Victoria but, despite being supported by the NSW Railway Administration, he was ignored. At that time there were only of track, four engines and assorted cars and wagons on the railway. However, by 1889, New South Wales, under engineer Whitton, had built almost 1,950 miles of standard gauge line.

Extension of the gauge muddle

The narrow gauge was introduced to Australia in 1865, when the Queensland Railways opened its first railway from Ipswich to Grandchester. The gauge was chosen on the supposition that it would be constructed more cheaply, faster and on tighter curves than the wider gauges. This was the first narrow gauge main line in the world.
South Australia first adopted this gauge in 1867 with its line from Port Wakefield to Hoyleton. J. T. Bagot was one of the advocates. The main reasons for choosing this were reduced cost, and the expectation that the narrow gauge would never connect to broad gauge lines. Overbuilt English railways were criticised. The Wakefield line was also envisaged as a horse-drawn tramway.
Later narrow gauge lines went towards Broken Hill and to Oodnadatta and from Mount Gambier. The Port Lincoln system was always isolated by geography.
The Western Australian Government Railways adopted it in 1879 for its first line from Geraldton to Northampton.
The Tasmanian Government Railways opened its first railway from Launceston to Deloraine in 1871 using broad gauge, but converted to narrow gauge in 1888.

Towards a network

Until the 1880s the gauge issue was not a major problem, as there were no connections between the separate systems. The focus of railway traffic was movement from the hinterland to the ports and cities on the coast so governments were not concerned about the future need for either inter-city passenger or freight services. It was not until 1883 when the broad and standard gauge lines from Melbourne and Sydney met at Albury, and in 1888 narrow and standard gauge from Brisbane and Sydney met at Wallangarra that the break of gauge became an issue. The issue of rail gauge was mentioned in an 1889 military defence report authored by English army officer Major General James Bevan Edwards, who said that the full benefit of the railways would not be attained until a uniform gauge was established. It needs to be remembered, however, that until federation the benefits of a uniform gauge were not immediately apparent, as passengers would have to pass through customs and immigration at the intercolonial border, meaning that all goods would have to be removed for customs inspection. It was only with Federation in 1901, and the introduction of free trade between the states, that the impediment of different gauges became apparent.
At the time of Federation, standard gauge was used in only NSW, but was favoured for further work. Work on gauge conversion was assisted by section 51 of the Constitution of Australia, which made specific provisions for the Commonwealth Parliament to make laws with respect to railway acquisition and construction. An agreement was made with the South Australian and Western Australian state governments for the Trans-Australian Railway from Port Augusta to Kalgoorlie, with work started in 1911 and completed in 1917. However, with the different gauges, to ship goods from Queensland to Perth required four transhipments.
In 1921 a royal commission into rail gauge was delivered, recommending gauge conversion of large areas of the country. It stated "that the gauge of 4-ft. 8.5-in. be adopted as the standard for Australia; that no mechanical, third rail, or other device would meet the situation, and that uniformity could be secured by one means only, viz., by conversion of the gauges other than 4-ft. 8.5-in." Following the royal commission, agreements were made for the standard gauge NSW North Coast line to be extended from Kyogle to South Brisbane and for the Trans-Australian Railway to be extended from Port Augusta to Port Pirie.
By the outbreak of World War II in 1939, there were 13 break-of-gauge locations, with upwards of 1,600 service personnel and many more civilians employed to transfer 1.8 million tons of freight during the period. The breaks of gauge were at:
LocationStateNarrowStandardBroad
South BrisbaneQueenslandxx
WallangarraQueenslandxx
AlburyNew South Walesxx
OaklandsNew South Walesxx
TocumwalNew South Walesxx
Broken HillNew South Walesxx
Mount GambierSouth Australiaxx
ServicetonSouth Australiaxx
TerowieSouth Australiaxx
PeterboroughSouth Australiaxxx
GladstoneSouth Australiaxxx
Port PirieSouth Australiaxxx
Port AugustaSouth Australiaxx
KalgoorlieWestern Australiaxx

In 1922, 273 inventions to solve the break-of-gauge had been rejected, and none adopted. In 1933, as many as 140 devices were proposed by inventors to solve the break-of-gauge problem, none of which were adopted.
Even dual gauge with a third rail for combining Irish gauge and standard gauge was rejected as too reckless, as the gap between these gauges of was considered to be too small. Dual gauge combining Irish gauge and narrow gauge where the gap was was also rejected.

Opposition to a third rail

While Prime Minister Billy Hughes had expressed support for the idea of a third rail solving the break of gauge difficulty, the predominant opinion of senior officers of the railways was to oppose it.

Clapp Report

After the wartime experience, a report into the Standardisation of Australia's rail gauges was completed by former Victorian Railways Chief Commissioner Harold Clapp for the Commonwealth Land Transport Board in March 1945. It included three main proposals:
The report wrote that if only main trunk lines were converted, it would introduce a multitude of break of gauge terminals and result in greatly increased costs. It also recommended abandoning part of the existing Perth to Kalgoorlie narrow gauge line, and build a flatter and straighter route using third rail dual gauge, as modernisation was just as important as standardisation.
South Australia was unhappy with the report, as the link to the Northern Territory would not run through its state. Western Australia and Queensland both saw no advantage in the report, as they already had a common gauge in their states, and only one main break of gauge. NSW entered into the agreement to advance gauge standardisation in Victoria and South Australia, but did not ratify it.
Gauge conversion did continue, with the South Australian Railways' Mount Gambier line from Wolseley to Mount Gambier and associated branches converted to broad gauge in the 1950s, on the understanding it would again to standard gauge at a later date making it the first ever only railway in Australia to have successfully been converted to all three gauges. Standard gauge lines were also built, with the line between Stirling North and Marree opened in July 1957.

Wentworth Committee

In 1956 a Government Members Rail Standardisation Committee was established, chaired by William Wentworth MP. It found that while there was still considerable doubt as to the justification for large scale gauge conversion, there was no doubt that work on some main trunk lines was long overdue. Both the committee and the government strongly supported three standardisation projects at a cost of £41.5 million:
The Commonwealth, NSW and Victorian governments were first to start work, with the first freight train operating on the converted North East line to Melbourne operating in January 1962 and the first through passenger train in April 1962. Over the next 12 months net freight tonnage was up 32.5% and to 1973 there was an average increase of 8.6%.
The work in Western Australia was predicated by an agreement entered into in November 1960 between the State Government and BHP for a standard gauge line to be built to allow iron ore from Koolyanobbing to be shipped to a new steel mill at Kwinana. A new dual gauge line was built through the Avon Valley from Midland to Northam on 1 in 200 grades instead of 1 in 40; and a new line was built from Southern Cross to Kalgoorlie though Koolyanobbing. The first wheat train ran from Merredin to Fremantle in November 1966 and the first iron ore train from Koolyanobbing to Kwinana in April 1967, with the line opened in full in August 1969. Kalgoolie to Perth freight train times were reduced from 31 hours to 13 hours, and passenger train times from 14 hours to eight hours. A new line was built from Woodbridge to Kwinana and one of the tracks on the Fremantle line converted to dual track from Cockburn Junction to Fremantle Harbour. The Midland line in Perth was converted to dual gauge and a new terminus station built.
In November 1971, following the discovery of rich nickel deposits, work commenced on converting the 640 kilometre line from Leonora to Esperance including 90 kilometres of track on a new alignment. The work was completed in September 1974.
In South Australia work on Port Pirie to Broken Hill did not start until 1963. The narrow gauge lines from Gladstone and Peterborough were not converted, with triple gauge yards provided. Standard gauge access to Adelaide was not provided. From Cockburn to Broken Hill a new railway was built on an improved alignment, avoiding the private Silverton Tramway route. The completion of this link enabled the first Indian Pacific to run across the nation in March 1970 from Sydney to Perth.

Whitlam Government

A new line between Tarcoola and Alice Springs was given the go ahead by the Whitlam Government in 1974. Built to replace the narrow gauge Central Australia Railway, the 831 kilometre long line was completed in 1980.

Fraser Government

Work on standard gauge access to Adelaide started in 1982, with conversion of the broad gauge south of Red Hill, a new line north of there to Crystal Brook where it met the standard gauge line from Port Pirie to Broken Hill. Freight trains began using the line in 1983 with passenger trains following the next year when Keswick Terminal opened. With benefits exceeding the cost by 2.8 times over 25 years, Australian National was able to obtain a loan for the funding of the work.

One Nation project

As part of the Keating Government's One Nation project, the Melbourne-Adelaide railway line was converted to standard gauge in 1995. The Hopetoun, Portland and Yaapeet lines in Victoria, and the Pinnaroo, Loxton and Apamurra lines in South Australia were also gauge converted. The remaining isolated broad gauge and narrow gauge lines were closed with the Mount Gambier and Mount Barker lines being the most controversial. The Fishermans Island line was converted to dual gauge in 1997 to serve the Port of Brisbane.

21st century projects

of 2,000 kilometres of track in Victoria was announced by the State Government in May 2001 but did not proceed due to the difficulty of achieving any agreement with then track manager, Freight Australia. In 2010, 200 kilometres of the North East line in Victoria was gauge converted between Seymour and Albury. In the same year standard gauge access was provided to the Port of Geelong, 13 years after the conversion to standard gauge of the Western standard gauge line between Melbourne and Adelaide, which runs through the northern suburbs of Geelong.
The Oaklands branch line was converted in 2009 to standard gauge as part of the project to standardise the North East line, to prevent that branch becoming isolated.
To allow the creation of the Nucleus Transmodal Hub at Bromelton, Queensland, the Acacia Ridge to Bromelton section of the NSW North Coast line was converted to dual gauge in 2009, however it was not used until 2017.
In November 2012, Brookfield Rail completed an upgrade on the Morawa to Geraldton line with gauge convertible sleepers installed to allow for conversion in the future.

Future projects

In Adelaide, the Belair, Gawler and Outer Harbor lines have been relaid with gauge convertible sleepers with plans to gauge convert the entire Adelaide Metro network in the future.
In Victoria, the Mildura line was scheduled to be converted in 2016. However, the project was put on hold to be completed as part of the Murray Basin Rail Project. The standardisation of the remaining North East lines was a recommendation by Infrastructure Victoria as a future project in its 30 Year Infrastructure Strategy