Regina Bypass


The Regina Bypass is a four-lane twinned highway connector road in Regina, Saskatchewan. The route connects Highway 1 with Highway 11, forming a partial ring road around the city of Regina.
It serves as a replacement bypass route for the existing Regina Ring Road. The Ring Road was originally constructed as an urban bypass route around Regina's city centre, however urban growth since Ring Road's construction effectively turned it into an arterial road with high traffic congestion along some portions of the route.
Phase one, east of Regina from Balgonie to Highway 33, finished on-schedule in October 2017. The remainder was finished October 2019.
The project, slated to cost $1.8 billion overall, is the largest single infrastructure project in the history of Saskatchewan. The bypass is owned on behalf of the public by the Ministry of Highways and Infrastructure with design, construction, operations, and long-term maintenance performed by the Regina Bypass Partners.
The bypass opened to traffic on October 29, 2019.

Scope

The full project scope encompasses 464 single-lane kilometres of work, roughly the distance between Regina and Medicine Hat. It consists of:
The project is being built in three distinct sections: "Area 1", which will upgrade and extend the city's existing Pinkie Road into a full connection between Highway 1 and Highway 11 in the west of the city; "Area 2", which will construct a new route south of the city between Highway 1 and Highway 33; and "Area 3", which will complete the connection from Highway 33 back to Highway 1 in the east of the city adjacent to Tower Road, as well as further upgrades to the existing route of Highway 1 easterly to Highway 46.
The route runs west of the Regina International Airport.

History

Plans for the Pinkie Road segment of the route were announced in 2009, with the remainder of the bypass loop finalized in 2014.
Pinkie Road will be a primary access highway with access points for the Global Transportation Hub. The project is undertaken by the City of Regina, Sherwood No. 159 rural municipality Ministry of Highways and Infrastructure and Transport Canada to provide an Intermodal freight transport center and the road infrastructure between two National Highway System routes. C$27 million will be contributed by the Government of Canada as part of the Asia-Pacific Gateway and Corridor Initiative towards this $93 million project. The provincial government will commit about $27 million to the project. Former Highways and Infrastructure Minister Wayne Elhard discussed expanding the Government's role in the next phase of the development project. The average vehicles per day on both Hwy 1 and Hwy 11 were examined in 5 year, and 25 year projections. The traffic on Hwy 1 is expected to have an average of 10,140 to 11,210 vehicles per dat on the west and east side of the proposed interchange in five years. This amount in 25 years is expected to increase to 21,040 vehicles per day on the west and 31, 340 vehicles per day on the east side of the proposed interchange respectively. Hwy 11 is projected to increase from 13,060 to 23870 vehicles per day in 25 years. The new connector road across Dewdney Avenue will carry 5,500 vehicles per day projected in 5 years increasing to 33,000 vehicles per day in 25 years. Currently the Average Annual Daily Traffic on Hwy 1 is 9,280 vehicles per day west of Pinkie Road, and 11,680 on the east side of Pinkie Road. On Hwy 11 east of the interchange the AADT is 8,840. On Pinkie Road south of the interchange the traffic volume is 7,740 vehicles per day. John Law, Deputy Minister of Highways and Infrastructure estimated that it will cost about $45 million to upgrade service roads to Pinkie Road and the intermodal facility to support approximately 1,400 commercial trucks per week in the area. The current proposal is looking at a 4 lane twinned highway with service roads. It will become part of the long term bypass route around Regina, and will accommodate future growth of the city to a population of 300,000. Pinkie Road will be approximately in length. The annexation of land by the city from the RM of Sherwood is being negotiated and the city will pay about $1,500,000 and supply water to the RM for the land segment.
The city initially considered four industrial land options for development Argyle Park - IPSCO lands, Regina Airport, Ross Industrial Park and the Pinkie Road and Trans-Canada Highway areas. In November 2007, Regina City Council examined a report which studied projected industrial growth for the city of Regina until 2027. The study proposed a new industrial area west of the Regina airport. The major roads would be constructed by the Ministry of Highways and Infrastructure and they would be supported by a $7 million payment by the City of Regina. The city also examined at this concept plan the cost of $54 million for infrastructure servicing of facilities. Regina's general manager of corporate services is looking at servicing fees and development levies to help repay the loan. A 20-year time frame will extend land use to also include a light industrial park. A number of open houses were held with the public to determine planning, road alignments, access points and general location of the new connector road. Following the advisement of two consultation firms the City of Regina has determined to proceed with the land development and water, drainage, and wastewater management procedures outlined for the Regina Inland Port. There will be two phases of land development the land development west of Pinkie Road will constitute phase 1 and east of Pinkie Road will be Phase 2.
The first overpass of the Trans-Canada Highway section of the bypass was partially finished and into operation in July 27, 2017 in the town of Balgonie. The second overpass of this section of the bypass was partially finished and put into operation in August 10, 2017 in the town of White City. CBC stated that the Balgonie overpass would be fully functional by Labour Day and the White City overpass would be fully functional by the third week of September, since the ramps need finishing touches. In 2016, construction began on a diverging diamond interchange at the Pilot Butte Access Road ; completed on March 9, 2018, it is the first DDI in Saskatchewan and the second in Canada.

Cost

In 2015, the Government of Saskatchewan committed $1.88 billion for design, construction, and 30 years of operations and maintenance. Of this, the construction budget is approximately $1.2 billion.
The first concept of a bypass, in 2013, was considerably smaller in scope and focused only on a route to divert traffic south of the city. The Ministry of Highways had two other, related projects under consideration at that time: overpasses east of Regina to improve safety for White Butte communities, and a project west of the city to divert traffic of Dewdney Avenue. Each of these small projects were estimated at roughly $400 million. A decision was made to combine these individual components into one project, the Regina Bypass, with a cost estimate of $1.2 billion.
The project is being undertaken as a public-private partnership. Financial analysis from Ernst & Young determined the P3 option was $380 million cheaper than a typical government-led build.
Other benefits attributed to the P3 include a faster construction schedule, better technology, and protection against cost overruns.

Economic benefits

The Regina Bypass is Saskatchewan's single largest single job creator since the railroad crossed western Canada in the 1880s. Construction alone is expected to create 8,200 jobs, in addition to spin-off effects generated by capital spending. In the long-term, the bypass will enhance the productivity of local businesses by providing cheaper, faster access to major trade routes including Highway 1 east-west and the Highway 6 connections to Edmonton and the United States.
As of March 2017, construction had involved 95 Saskatchewan companies including Graham, the Broda Group, Brandt, Clifton Associates, Crestview Chrysler, Fraser Strategy, Inland Aggregates, Lonesome Prairie, Urban Systems, and Noremac.

Environmental and heritage impact

The proposal is studying the impact the new roadway will have on protected species of fauna in Saskatchewan such as the burrowing owl, loggerhead shrike, Sprague's pipit '', peregrine falcon, yellow rail, monarch butterfly and northern leopard frog. Flora of Saskatchewan which may be impacted would be the prairie ragwort and Geyer's onion. The Presbyterian Indian Residential School Cemetery is also located in this vicinity north of Dewdney Avenue and east of Pinkie Road. The project is being planned to meet any requirements set forth under the Building Canada Plan as well as evaluation of project procedures for environmental concerns as set out by the Canadian Environmental Assessment Act.

Exit list

Excludes the section of existing Saskatchewan Highway 1 that was upgraded as part of the project.
;Footnotes