The Kiel Canal was built between 1887 and 1895 cutting through existing traffic lines including the railway line between Neumünster and Flensburg for which two parallel swing bridges were built. In 1907 it was decided to enlarge the canal and in the course of this expansion major obstacles were also to be removed. Main railway lines had right of way over ships on the canal and ships had to stop, losing about half an hour when a train passed. This was considered the major obstacle as the ships were unable to overtake and could pass each other at dedicated enlarged areas so that the traffic on the entire canal was hampered. Especially the navy pressed for a separation of traffic flows as closed bridges could delay flotillas by several hours. In order to allow the railway line to pass above the canal, the new bridge was to have a clearance of 42 metres over the canal's mean water level. The existing tracks crossed the canal about 7 metres above the canal's water level, so the tracks had to be elevated by about 36.5 metres including additional 1.5 metres to accommodate the thickness of the lower girder. The required maximum incline of 1:150 made it necessary to build elevated embankments and access bridges of about 5.5 km at each side.
Design and construction
The bridge was erected between 1911 and 1913 to a design by Friedrich Voss and replaced the earlier swing bridges. The steel viaduct has a length of and is supplemented by embankments that bring the overall length of the structure to about. The cantilever main bridge is long, has a main span of and provides a clearance of above the canal's water level. To serve Rendsburg station, situated at ground level only a couple of hundred metres from the main bridge, the railway line is routed through a large 360-degree loop on the north bank of the canal. The total cost of the construction, including the relocation of railway lines but excluding work related to the elevation of Rendsburg station, was 13.4 million Mark. This figure includes 5.7 million Mark for bridges, 2.7 million Mark for the mounds and 1.3 million Mark for underpasses and the relocation of roads.
Transporter bridge
The "Schwebefähre" runs daily every 15 minutes from early morning until late at night. It covers a distance of within 1½ minutes and provides the shortest connection between the municipality of Osterrönfeld and the city of Rendsburg. As this mean of transportation is especially useful to students on their way to school, larger maintenance work that requires suspension of service is coordinated with school holidays. The gondola is fourteen metres long and six metres wide, and travels six metres above the canal. In recent years the nominal transport capacity has been reduced from six to four automobiles in order to factor in increased car size and weight. While the gondola is equipped with nautical equipment such as radio, radar and life-rafts, there is no prerequisite for the operator to hold a master's licence for inland navigation. During a storm in January 1993, the unmanned and unlit gondola broke loose at night, was blown over the canal and collided with a ship. Both ship and gondola suffered only minor damage. On 8 January 2016 the transporter bridge collided with general cargo shipEvert Prahm. The transporter bridge was heavily damaged. It was demounted and moved to a shipyard on March 15, 2016 for damage assessment, but was found to be irreparably damaged. Construction of its replacement began in April 2020 and is expected to be completed in 2021.