Rooppur Nuclear Power Plant


The Rooppur Nuclear Power Plant will be a 2.4 GWe nuclear power plant in Bangladesh. The nuclear power plant is being constructed at Rooppur, adjoining Paksey, in the Ishwardi Upazila of Pabna District, on the bank of the river Padma, west of Dhaka, in the northwest of the country.
It will be the country's first nuclear power plant, and the first of two units are expected to go into operation in 2023. It is being built by India's Atomic Energy Commission and the Russian Rosatom State Atomic Energy Corporation.

History

Planning

The plan to establish a nuclear power plant in the then East Pakistan was made in 1961. In 1963, the Rooppur village of the Pabna district was selected for the proposed plant and of land was acquired. The plan was to establish a 200MW nuclear power plant in the selected site. Discussions took place with the Government of Canada from 1964 to 1966. Discussions with the governments of Sweden and Norway were also going on in those years. However, no real progress was made. In 1970, the project was scrapped.
After the independence of Bangladesh, the Government of Bangladesh started discussion with the Soviet Union in 1974, however no agreement was reached. In 1976-77, French company Sofratom conducted a feasibility study and found the project at Rooppur feasible. In 1980, a 125 MW nuclear power plant project was approved. But, this effort did not materialized too. In the 1987-88 period, another feasibility study was conducted and decision was taken to construct a 300 to 500 MW nuclear power plant. In 1998, steps were taken to construct a 600 MW power plant. Nuclear action plan was approved in 2000.
In 2005, Bangladesh signed a nuclear cooperation agreement with China. In 2007, the Bangladesh Atomic Energy Commission proposed two 500 MW nuclear reactors for Rooppur by 2015. In 2008, China offered funding for the project. Instead, the Bangladesh government started discussion with the Russian government a year later and on 13 February the two governments signed a memorandum of understanding. Rosatom said they would start construction by 2013.
In 2011, International Atomic Energy Agency conducted IAEA Integrated Nuclear Infrastructure Review mission in Bangladesh. Later on, IAEA approved a technical assistance project for the Rooppur nuclear power plant. In 2013 a group of Bangladeshi scientists and the global diaspora voiced profound concern over the safety and economic viability of the plant. Several separate issues were raised, from the unsuitability of the site to the obsolescence of the VVER-1000 model proposed, questionable financing arrangements and a lack of agreement with Russia over nuclear waste disposal.
In 2015 the proposal was delayed by a year. Rosatom offered a two VVER-1200 reactor power plant, increasing output to 2.4 GWe. By December 2015 The Daily Star reported that the estimated cost of the plant had climbed to US$13 billion, from statements of around US$4 billion made earlier in the same year. German based Transparency International expressed concern on 28 December 2015 about the safety of the proposed plant.

Construction

In 2016 ground preparation work commenced. The $12.65 billion contract is 90% funded by a loan from the Russian government. The two units generating 2.4 GWe are planned to be operational in 2023 and 2024. Rosatom will operate the units for the first year before handing over to Bangladeshi operators. Russia will supply the nuclear fuel and take back spent nuclear fuel.
On 4 November 2017, Bangladesh Atomic Energy Commission received, from Bangladesh Atomic Energy Regulatory Authority, the design and construction license of Unit 1, paving the way for the nuclear island first concrete pour. At the 61st general conference of the global nuclear watchdog International Atomic Energy Agency, Mr. Shekhar Basu mentioned that India is also involved in this project with Russia, however, the level of Indian involvement in this project has not been established yet, as India is not a member of the Nuclear Supplier Group, which controls the export of materials, equipment and technology that can be used to manufacture nukes. On 30 November 2017, first concrete was poured for the nuclear island basemat of Unit 1. A ceremony was held, attended by Rosatom's director-general Alexey Likhachev and the prime minister of Bangladesh Sheikh Hasina.
On 14 July 2018, first concrete was poured for Unit 2. The following month, Rosatom began installing a 200-tonne core catcher as the first large piece of equipment in the reactor building of Rooppur 1, describing it as "a unique protection system".
When the COVID-19 pandemic struck Bangladesh in early 2020, many projects such as the Dhaka Metro Rail were stalled, but the Rooppur Nuclear Power Plant remained on track to be completed by 2023. Progress in this period includes Rosatom's engineering company Atommash completing hydraulic tests for Rooppur unit 1.

Planned nuclear power reactors

Research

Bangladesh's development strategy sees the country becoming a middle-income nation by 2021, in large part by emphasis on its science and technology sector to drive economic growth. The ministry of science and technology estimated in 2014 that US$6.2 billion will be needed in the next decade to achieve the goals of Vision 2021. The Science and Technology Act 2010 is helping to boost this, and MoST is now allocating over $150 million per year to nuclear technology development as gas reserves become depleted. The power plant will also promote the local economy of Rooppur, Pabna.
The country has had a TRIGA 3 MW research reactor operational since 1986.