Rupsha Rail Bridge


Rupsha Railway Bridge is a railway bridge on Rupsha River under construction. This bridge will connect Khulna with Port of Mongla by railway network. Bangladesh Railway and Indian Larsen & Toubro Limited signed an agreement to construct the bridge. The bridge will be long.

Project details

was passed by ECNEC on 21 December 2010. This project is divided into three parts. First one is to construct the railway, second one is to build a bridge over Rupsha and third one is to construct the signaling system. Estimated cost of this project is 1,076.445 crore taka. The bridge has 7 nos. of 102.4m long Double Warren Open-web Truss Girders with 136 nos. of 32.2 m long Composite Plate Girders for Viaducts on either side. This project will be finished in 2021. STUP Consultants P Limited of India is the Engineering Consultants for Design and Construction Supervision Services. STUP Consultants got associated with this Project since 1 January 2018.

Features