Santiago Metro Line 1
Santiago Metro Line 1 is the oldest of the seven existing rapid transit lines that make up the Santiago Metro system. Being its busiest, it has a total of 27 stations along its 19.3 kilometre length, constructed almost entirely underground, and is located primarily along the axis formed by the Avenida Libertador General Bernardo O'Higgins, Providencia Avenue and Apoquindo Avenue.
In 2015, Line 1 accounted for 39.5% of all trips made on the metro system with a daily ridership of 705,200, making it the busiest line in the system. It currently connects with five of the six other lines – with Line 2 at Los Héroes station, with Line 3 at Universidad de Chile station, with Line 4 at Tobalaba station, with Line 5 at both San Pablo station and Baquedano station and line 6 at Los Leones. There are plans for connections with the future Line 9 at Santa Lucía station, the future Line 7 at Baquedano and Pedro de Valdivia and the future Line 8 at Los Leones. Its distinctive colour on the network map is red.
During the 2019 Chilean protests, several of the stations were burned and looted, with the closure of the entire system following soon afterwards. Since then, all of the stations have reopened.
History
The line was inaugurated on September 15, 1975, with an initial 8.3 km of track running from San Pablo station to La Moneda station. In 1977, the line was extended 3.2 km to the east to Salvador station. Then, in 1980, seven more stations opened to the east between Salvador and Escuela Militar. On January 7, 2010, three final stations opened to the east of Escuela Militar: Manquehue, Hernando de Magallanes and Los Dominicos.train in Tobalaba metro station
1986 terrorist attack
One of the most memorable and tragic events in the history of the Santiago Metro was the June 16, 1986 terrorist attack, which took place on Line 1. At 6:56 a.m., the Manuel Rodríguez Patriotic Front, a group opposed to the government of General Pinochet, attacked Tobalaba station with C4 bombs. The bombs exploded and caused the death of one passenger, injured another six, and left one NS-74 train destroyed. Because of this, Metro S.A. decided to replace that trainset, however Alsthom Groupe Brissonneau wasn't producing trains at a fast enough rate, so the company turned their attention towards Concarril, who supplied the Santiago Metro with one NS-88 trainset as a replacement. The destroyed train remained out of service until it was rebuilt by Santiago Metro workers between February 27, 1989 and December 14, 1990, going back into circulation in 1990. The train now bears a commemorative plaque for the attack and its reconstruction.October 2019 protests
A series of protests in October 2019 resulted in major damage to the metro network. Line 1 was closed on the weekend of October 18 of that year, and resumed partial service two days later between Pajaritos and Los Dominicos; full service was expected to resume in the first half of 2020. San Pablo, Neptuno, and Baquedano stations suffered moderate damage in the protests, and as a result those three stations would temporarily close. However, the Baquedano station has remained closed to the public since the beginning of the protests, however On April 8, 2020, the combination of both lines was enabled, with their accesses closed until May 4 of the same year. Finally, Line 1 was fully operational again on July 25, 2020, with the reopening of the San Pablo and Neptuno stations.Future
After the announcement of the line 7, it is proposed to extend the line 1 northwards to connect with the line 7 and ending at this point.Requests have been made by local residents, authorities and the communal mayor for an extension to the commune of Cerro Navia towards Avenida Carrascal and the hospital planned for construction in this commune. Although no expansion project has yet begun, studies are being carried for an extension through Cerro Navia.
Requests have been made by local residents, authorities and the communal mayor for an extension to the commune of Las Condes towards Avenida El Alba and the extension for construction in this commune.
Communes">Communes of Chile">Communes served by Line 1
Line 1 serves the following Santiago communes from west to east:- Lo Prado
- Estación Central
- Santiago
- Providencia
- Las Condes
Stations
The Line 1 stations are:Stations | Transfers | Location | Opening | Commune | Notes |
San Pablo | Av. Neptuno/Av. San Pablo | September 15, 1975 | Lo Prado | ||
Neptuno | Av. Neptuno/Av. Dorsal | September 15, 1975 | Lo Prado | ||
Pajaritos | Av. General Oscar Bonilla/Santa Marta | September 15, 1975 | Lo Prado/Estación Central | ||
Las Rejas | Av. Lib. Bdo. O'Higgins/Av. Las Rejas | September 15, 1975 | Lo Prado/Estación Central | ||
Ecuador | Av. Lib. Bdo. O'Higgins/Radal | September 15, 1975 | Estación Central | ||
San Alberto Hurtado | Av. Lib. Bdo. O'Higgins/Ruta 5 Av. General Velasquez | September 15, 1975 | Estación Central | ||
Universidad de Santiago | Av. Lib. Bdo. O'Higgins/Jotabeche | September 15, 1975 | Estación Central | ||
Estación Central | Av. Lib. Bdo. O'Higgins/Av. Matucana | September 15, 1975 | Estación Central/Santiago | ||
Unión Latinoamericana | Av. Lib. Bdo. O'Higgins/Unión Latinoaméricana | September 15, 1975 | Santiago | ||
República | Av. Lib. Bdo. O'Higgins/Av. Ricardo Cumming | September 15, 1975 | Santiago | ||
Los Héroes | Av. Lib. Bdo. O'Higgins/Ruta 5 Av. Jorge Alessandri Rodriguez | September 15, 1975 | Santiago | ||
La Moneda | Av. Lib. Bdo. O'Higgins/Amunategui | September 15, 1975 | Santiago | ||
Universidad de Chile | Av. Lib. Bdo. O'Higgins/Paseo Ahumada | March 31, 1977 | Santiago | ||
Santa Lucía | Av. Lib. Bdo. O'Higgins/Av. Santa Rosa | March 31, 1977 | Santiago | This station will be future combination with the line in 2026 | |
Universidad Católica | Av. Lib. Bdo. O'Higgins/Av. Portugal | March 31, 1977 | Santiago | ||
Baquedano | Av. Lib. Bdo. O'Higgins/Av. Vicuña Mackenna | March 31, 1977 | Santiago/Providencia | This station will be future combination with the line in 2026 | |
Salvador | Av. Providencia/Av. Salvador | March 31, 1977 | Providencia | ||
Manuel Montt | Av. Providencia/Av. Manuel Montt | August 31, 1980 | Providencia | ||
Pedro de Valdivia | Av. Nueva Providencia/Av. Pedro de Valdivia | August 31, 1980 | Providencia | This station will be future combination with the line in 2026 | |
Los Leones | Av. Nueva Providencia/Av. Ricardo Lyon | August 31, 1980 | Providencia | This station will be future combination with the line in 2026 | |
Tobalaba | Av. Providencia/Av. Tobalaba | August 31, 1980 | Providencia/Las Condes | ||
El Golf | Av. Apoquindo/Av. El Golf | August 31, 1980 | Las Condes | ||
Alcántara | Av. Apoquindo/Alcántara | August 31, 1980 | Las Condes | ||
Escuela Militar | Av. Apoquindo/Circ. Américo Vespucio | August 31, 1980 | Las Condes | ||
Manquehue | Av. Apoquindo/Av. Manquehue | January 7, 2010 | Las Condes | ||
Hernando de Magallanes | Av. Apoquindo/Hernando de Magallanes | January 7, 2010 | Las Condes | ||
Los Dominicos | Av. Apoquindo/Av. Padre Hurtado | January 7, 2010 | Las Condes |
Line 1 data sheet
- Terminal Communes:Lo Prado – Las Condes
- Track:
- * Neptuno Avenue: 2 Stations
- * General Oscar Bonilla Avenue: 1 station
- * Libertador Bernardo O'Higgins Avenue: 13 stations
- * Providencia Avenue: 2 stations
- * Nueva Providencia Avenue: 2 stations
- * Apoquindo Avenue: 7 stations
- Construction Method:
- * San Pablo: open-cut.
- * San Pablo - Neptuno section: underground.
- * Neptuno: open-cut.
- * Neptuno - Pajaritos section: underground.
- * Pajaritos: open-cut.
- * Pajaritos – Los Dominicos: Underground.
- Opening Dates:
- * San Pablo – La Moneda: September 1975.
- * La Moneda – Salvador: March 1977.
- * Salvador – Escuela Militar: August 1980.
- * Escuela Militar – Los Dominicos: January 2010.