Slurry wall


A slurry wall is a civil engineering technique used to build reinforced concrete walls in areas of soft earth close to open water, or with a high groundwater table. This technique is typically used to build diaphragm walls surrounding tunnels and open cuts, and to lay foundations.

Construction

While a trench is excavated to create a form for a wall, it is simultaneously filled with slurry. The dense but liquid slurry prevents the trench from collapsing by providing outward pressure, which balances the inward hydraulic forces and also retards water flow into the trench.
Slurry walls are typically constructed by starting with a set of guide walls, typically deep and thick. The guide walls are constructed on the ground surface to outline the desired slurry trench and guide the excavation machinery. Excavation is done using a special clamshell-shaped digger or a hydromill trench cutter, suspended from a crane. The excavator digs down to design depth for the first wall segment. The excavator is then lifted and moved along the trench guide walls to continue the trench with successive cuts as needed. The trench is at all times kept filled with slurry to prevent its collapse, but the liquid filling allows the excavation machinery and excavation spoil to be moved without hindrance.
Once a particular length of trench is reached, a reinforcing cage is lowered into the slurry-filled pit and the pit is filled with concrete from the bottom up using tremie pipes. The heavier concrete displaces the bentonite slurry, which is pumped out, filtered, and stored in tanks for use in the next wall segment, or recycled.
Slurry walls are successively extended to enclose an area, blocking water and softened earth from flowing into it. Once the concrete has hardened, excavation within the now concrete-wall-enclosed area can proceed. To prevent the concrete wall from collapsing into the newly open area, temporary supports such as tiebacks or internal crossbeams are installed. When completed, the structure built within the walled-off area supports the wall, so that tiebacks or other temporary bracing may be removed.
Stability of the trench is essential in trench cutting.
Usage of bentonite with precise density prevents collapse of trench walls

History

The slurry wall technique was first introduced during the excavation of Line 1 on the underground rapid transit system of Milan, Italy by the company ICOS just after the end of World War II. This new technology became an important component of the top-down tunnelling method also known as Metodo Milano.
Slurry wall construction was used to construct the "bathtub" that surrounded the foundations of most of the World Trade Center site in New York City. In the 1980s, the Red Line Northwest Extension project in Boston was one of the first projects in the US to use the modern form of the technology, with hydromill trench cutters and the "Milan method". Slurry walls were also used extensively in Boston's later Big Dig tunnel project.

Design

The design of a slurry wall includes the design of wall thickness and reinforcements. Thickness of a slurry wall in preliminary design is generally set to about 4-8% of the excavation depth. Slurry wall design is undertaken based on bending moment and shear envelope obtained from the stress analysis. In the design of such underground walls, width of the unit is considered as one meter, and the wall is analyzed under plane strain condition. Since the length-to-width ratio of excavations is generally large, plane strain conditions can be assumed.