Space Station Processing Facility


The Space Station Processing Facility is a three-story, industrial building
located in the Kennedy Space Center industrial area, just east of the Operations and Checkout Building.
It was constructed in 1992 for the manufacture and processing of International Space Station modules, flight hardware, equipment, structural components and solar arrays.
The SSPF includes two processing bays, an airlock, operational control rooms, laboratories, logistics areas, office space, a ballroom and conference halls, and a cafeteria.
The processing areas, airlock, and laboratories were designed to support non-hazardous Station and Space Shuttle payloads in 100,000 class clean work areas.

History and construction

During the re-designing phase of Space Station Freedom in early 1991, Congress approved new plans for NASA to lead the project and begin manufacturing its components for the future International Space Station. Kennedy Space Center was selected as the ideal launch processing complex for the ISS, as well as hosting all the internationally manufactured modules and station elements.
However the Operations and Checkout Building was insufficient in size to accommodate all the components. On March 26th 1991, engineers at Kennedy Space Center; along with contractor Metric Constructions Inc. of Tampa Florida, broke ground on a new $56 million Space Station Processing Facility, situated adjacent to the O&C. The design called for a 457,000-square-foot multifunction building housing an enormous processing bay, laboratories, control rooms, staging areas, communications and control facilities, and office space for some 1,400 NASA and contractor employees.
KSC Deputy Director Gene Thomas described the construction: "The skyline around here is really going to change. This will be the biggest facility that we have built since the Apollo days". The SSPF used reinforced concrete and some 4,300 tons of steel. The building was structually completed and topped out by mid 1992. After three years of construction, interior fitting and equipment set-up, the SSPF formally opened on June 23, 1994.

Station Integration Testing

Regarding the launch of modules of the International Space Station, there had been philosophical differences for years between designers and payload processors whether to ship-and-shoot or perform integration testing prior to launch. The former involved building a station module and launching it without ever physically testing it with other modules. The integration testing was not originally in the ISS plan, but in 1995 Johnson Space Center designers began to consider it and embedding KSC personnel at module factories. Multi-Element Integration Testing of ISS modules at KSC was officially in the books in 1997.
"Three MEIT and one Integration Systems Test tests were conducted for the ISS," taking about three years from planning to completion and closure:
After the launch of the Destiny, an emulator was built for MEIT testing, since the lab controlled many other modules. Among the items checked were mechanical connections, the ability to flow power and fluids between modules, and the flight software.
Numerous issues were found from these on the ground tests, many of which could not have been fixed in orbit. Many of the builders accompanied their modules from around the world and worked at KSC for months to years during testing. Many of the modules were renamed after successfully launching.

Processes

At the SSPF, space station modules, trusses and solar arrays are prepped and made ready for launch. The low and high bays are fully air conditioned and ambient temperature is maintained at at all times. Workers and engineers wear full non-contaminant clothing while working. Modules receive cleaning and polishing, and some areas are temporarily disassembled for the installation of cables, electrical systems and plumbing. In another area, shipments of spare materials are available for installation. International Standard Payload Rack frames are assembled and welded together, allowing the installation of instruments, machines and science experiment boxes to be fitted. Once racks are fully assembled, they are hoisted by a special manually operated robotic crane and carefully maneuvered into place inside the space station modules. Each rack weighs from 700 to 1,100 kg, and connect inside the module on special mounts with screws and latches.
Cargo bags for MPLM modules are filled with their cargo such as food packages, science experiments and other miscellaneous items on-site in the SSPF, and loaded into the module by the same robotic crane and strapped in securely.

Building Specifications

The SSPF's High Bays provide maximum flexibility for manufacturing, assembly, testing and processing payloads and elements destined for space. The bays are enormous cleanrooms equipped with overhead cranes, commodities-servicing equipment and a secure backup-power supply. The facility also has 15 offline labs.

Intermediate Bay (I-bay)

Office floor area: of office/work space

Station components currently in the SSPF

When the lights in the building are on, most of these components can be seen on the live webcam from the facility.
The building itself is open to the public and tours are offered free of charge by the employees.

Events

When the high bay area is less busy at times, a variety of events and conferences are held in various places within the SSPF building.
Starting in 2016, many small science companies that utilize the ISS have set up scientific equipment to study the feasibility of growing vegetables in space, such as the Veggie plant growth system, and the Advanced Plant Habitat. There are occasional STEM exhibitions where visitors can visit the SSPF and its ballroom to learn about the building's history, manufacturing acitivies, biological and chemical sciences, and the future vision of space operations at Kennedy Space Center, including the Lunar Gateway mockup module. The ballroom also doubles as a lecture hall for presentations. On rare occasions the high bay was once used for the National Space Council's second revived meeting on February 21, 2018.
Tenants including Northrop Grumman, Lockheed Martin and Airbus have also moved facilities into the SSPF.

Gallery