Statue of Unity


The Statue of Unity is a colossal statue of Indian statesman and independence activist Sardar Vallabhbhai Patel, who was the first Deputy Prime Minister and Home minister of independent India and adherent of Mahatma Gandhi during the non-violent Indian Independence movement. Patel was highly respected for his leadership in uniting 562 princely states of India with a major part of the former British Raj to form the single Union of India. The statue is located in the state of Gujarat, India. It is the world's tallest statue with a height of 182 metres. It is located on the Narmada River in the Kevadiya colony, facing the Sardar Sarovar Dam southeast of the city of Vadodara and from Surat.
The project was first announced in 2010 and the construction of the statue started in October 2013 by Larsen & Toubro, with a total construction cost of ₹2,989 crore. It was designed by Indian sculptor Ram V. Sutar, and was inaugurated by Indian Prime Minister Narendra Modi on 31 October 2018, the 143rd anniversary of Sardar Patel's birth.

History

first announced the project to commemorate Vallabhbhai Patel on 7 October 2013 at a press conference to mark the beginning of his 10th year as The Chief Minister of Gujarat. At the time, the project was dubbed, "Gujarat's tribute to the nation".
A separate Society named Sardar Vallabhbhai Patel Rashtriya Ekta Trust was formed under the chairmanship of the Chief minister, Government of Gujarat, to ensure seamless execution of the entire project.
An outreach drive named the Statue of Unity Movement was started to support the construction of the statue. It helped collect the iron needed for the statue by asking farmers to donate their used farming instruments. By 2016, a total of 135 metric tonnes of scrap iron had been collected and about 109 tonnes of it was used to make the foundation of the statue after processing. A marathon titled Run For Unity was held on 15 December 2013 in Surat and Vadodara in support of the project.

Design and construction

Design

The statue depicts Vallabhbhai Patel, one of the most prominent leaders of the Indian independence movement, the first home minister as well as the first Deputy Prime Minister of independent India, and responsible for the integration of hundreds of princely states into the modern Republic of India.
.
After studying numerous statues of Patel across the country, a team of historians, artists, and academics chose to proceed with a design submitted by the Indian sculptor, Ram V. Sutar. The Statue of Unity is a much larger replica of a statue of the leader installed at Ahmedabad International Airport. Commenting on the design, Ram Sutar's son, Anil Sutar explains that, "the expression, posture and pose justify the dignity, confidence, iron will as well as kindness that his personality exudes. The head is up, a shawl flung from shoulders and hands are on the side as if he is set to walk". Three models of the design measuring,, and were initially created. Once the design of the largest model was approved, a detailed 3D-scan was produced which formed the basis for the bronze cladding cast in a foundry in China.
Patel's dhoti-clad legs and the use of sandals for footwear rendered the design thinner at the base than at the top thereby affecting its stability. This was addressed by maintaining a slenderness ratio of 16:19 rather than the customary 8:14 ratio of other tall buildings. The statue is built to withstand winds of up to and earthquakes measuring 6.5 on the Richter scale which are at a depth of 10 km and within a radius of 12 km of the statue. This is aided by the use of two 250 tonne tuned mass dampers ensuring maximum stability.
The total height of the structure is, with a base of and the statue measuring. The height of 182 metres was specifically chosen to match the number of seats in the Gujarat Legislative Assembly.

Funding

The Statue of Unity was built by a Public Private Partnership model, with most of the money raised by the Government of Gujarat. The Gujarat state government had allotted for the project in its budget from 2012 to 2015. In the 2014–15 Union Budget, was allocated for the construction of the statue. Funds were also contributed by Public Sector Undertakings under the Corporate Social Responsibility scheme.

Construction

A consortium comprising Turner Construction, Michael Graves and Associates and the Meinhardt Group supervised the project. The project took 57 months to complete – 15 months for planning, 40 months for construction and 2 months for handing over by the consortium. The total cost of the project was estimated to be about by the government. The tender bids for the first phase were invited in October 2013 and were closed in November 2013.
Narendra Modi, then serving as the Chief Minister of Gujarat, laid the statue's foundation stone on 31 October 2013, the 138th anniversary of Patel's birth.
Indian infrastructure company Larsen & Toubro won the contract on 27 October 2014 for its lowest bid of for the design, construction and maintenance of the statue. L&T commenced the construction on 31 October 2014. In the first phase of the project, ₹1,347 crore was earmarked for the main statue, ₹235 crore for the exhibition hall and convention centre, ₹83 crore for the bridge connecting the memorial to the mainland and ₹657 crore for the maintenance of the structure for a duration of 15 years after its completion. The Sadhu Bet hillock was flattened from 70 metres to 55 metres to lay the foundation of the statue.
L&T employed over 3000 workers and 250 engineers in the statue's construction. The core of the statue used 2,10,000 cubic metres of cement and concrete, 6,500 tonnes of structural steel, and 18,500 tonnes of reinforced steel. The outer façade is made up of 1,700 tonnes of bronze plates and 1,850 tonnes of bronze cladding which in turn consists of 565 macro and 6000 micro panels. The bronze panels were cast in Jiangxi Tongqing Metal Handicrafts Co. Ltd in China as facilities large enough for such casting were unavailable in India. The bronze panels were transported over sea and then by road to a workshop near the construction site where they were assembled.
Local tribals belonging to the Tadvi tribe opposed the land acquisition for the development of tourism infrastructure around the statue. They have been offered cash and land compensation, and have been provided jobs. People of Kevadia, Kothi, Waghodia, Limbdi, Navagam, and Gora villages opposed the construction of the statue and demanded the restitution of the land rights over of land acquired earlier for the dam as well as for the formation of a new Garudeshwar subdistrict. They also opposed the formation of Kevadia Area Development Authority and the construction of the Garudeshwar weir-cum-causeway project. The government of Gujarat accepted most of their demands.
Construction of the monument was completed in mid-October 2018; and the inaugural ceremony was held on 31 October 2018, and was presided over by Prime Minister Narendra Modi. The statue has been described as a tribute to Indian engineering skills.

Features

The Statue of Unity is the world's tallest statue at. It rises higher than the previous record holder, the Spring Temple Buddha in China's Henan province. The previous tallest statue in India was the tall statue of Hanuman at the Paritala Anjaneya Temple near Vijayawada in the state of Andhra Pradesh. The statue can be seen within a radius.
The monument is constructed on a river island named Sadhu Bet, away from and facing the Narmada Dam downstream. The statue and its surroundings occupy more than, and are surrounded by a long artificial lake formed by the Garudeshwar weir downstream on the Narmada river.
The statue is divided into five zones of which only three are accessible to the public. From its base to the level of Patel's shins is the first zone which has three levels and includes the exhibition area, mezzanine and roof. The first zone also contains a memorial garden and a museum. The second zone reaches up to Patel's thighs, while the third extends up to the viewing gallery at a height of 153 metres. The fourth zone is the maintenance area while the final zone comprises the head and shoulders of the statue.
The museum in the first zone catalogues the life of Sardar Patel and his contributions. An adjoining audio-visual gallery provides a 15-minute long presentation on Patel and also describes the tribal culture of the state. The concrete towers which form the statue's legs contain two elevators each. Each lift can carry 26 people at a time to the viewing gallery in just over 30 seconds. The gallery is located at a height of and can hold up to 200 people.

Tourism

Over 1,28,000 tourists visited the statue in the 11 days after its opening to the public on 1 November 2018. The daily average tourist footfall at Statue of Unity during November 2019 reached 15,036, outpacing the Statue of Liberty. It has been included in the Shanghai Cooperation Organisation’s ‘8 Wonders of SCO’ list.