Tappan Zee Bridge (2017–present)
The Tappan Zee Bridge, officially named the Governor Mario M. Cuomo Bridge after former New York Governor Mario Cuomo, is a twin cable-stayed bridge spanning the Hudson River between Tarrytown and Nyack in the U.S. state of New York. It was built to replace the original Tappan Zee Bridge, which was located just to the south. The new bridge's north span carries the northbound and westbound automobile traffic of the New York State Thruway, Interstate 87 and I-287; it also carries a shared use path for bicycles and pedestrians. The south span carries southbound and eastbound automobile traffic.
The process to replace the original bridge kicked off in 2012, and Tappan Zee Constructors began construction on the new spans in 2013. The Left Coast Lifter was instrumental in the construction of the bridge. The north span officially opened to westbound traffic on August 26, 2017, and eastbound traffic temporarily began using the north span on October 6, 2017. Tappan Zee Constructors then began demolishing the old bridge. An opening ceremony for the south span was held on September 8, 2018, and traffic started using the new span three days later.
The bridge's official name has been controversial since its announcement. A petition and proposed legislation have opposed the attachment of Mario Cuomo's name to the bridge.
History
Background
The Tappan Zee river crossing was named by 17th century Dutch settlers. The Tappan Zee Bridge and the smaller Bear Mountain Bridge are the only crossings of the stretch of the Hudson between Westchester and Rockland counties, both of which are part of New York City's populous northern suburbs.The original Tappan Zee Bridge was a cantilever bridge built from 1952 to 1955. The bridge was long and spanned the Hudson at its second-widest point. It was the longest bridge in New York State, at a length of including approaches. Built immediately after the Korean War, the bridge had a low construction budget of only $81 million and a designed life-span of only 50 years. During its first decade, the bridge carried fewer than 40,000 vehicles per day.
By the 2000s, the bridge was "decaying" and "overburdened". The deteriorating structure bore an average of 140,000 vehicles per day, substantially more traffic than its designed capacity. The collapse of Minnesota's I-35W Mississippi River bridge in 2007 raised worries about the Tappan Zee Bridge's structural integrity. These concerns, together with traffic overcapacity and increased maintenance costs, escalated the serious discussions already ongoing about replacing the Tappan Zee with a tunnel or a new bridge. Six options were identified and submitted for project study and environmental review.
Planning
The Federal Highway Administration issued a report in October 2011 designating the Tappan Zee's replacement to be a dual-span twin bridge. The new bridge was built a few yards to the north of the existing bridge, and connects to the existing highway approaches of the New York State Thruway on both river banks. The New York State Thruway Authority requested design proposals from four companies in 2012 and eventually received three project proposals. The authority awarded a $3.142 billion contract to Tappan Zee Constructors, whose proposal was not only the least expensive but also promised the shortest construction timeline and included plans to minimize environmental impact. Construction began as scheduled in October 2013, with completion targeted for 2017.Originally, some motorists thought that bridge tolls could more than double, rising to those of New York City's Hudson River crossings. However, the state passed legislation freezing the toll on the bridge at $5 through 2020 in its 2016 legislative session.
The new Tappan Zee Bridge was proposed to include four vehicle lanes on each span, for a total of eight lanes, as well as a shared-use bicycle and pedestrian path. Like its predecessor, the new Tappan Zee Bridge is to be administered by the New York State Thruway Authority. The authority is the project co-sponsor, along with the state Department of Transportation.
Construction
The New York Metropolitan Transportation Council added the Tappan Zee Bridge to its list of projects eligible for federal funds in August 2012. The United States Department of Transportation approved the plan on September 25, 2012. The approval process took fewer than 10 months as opposed to the traditional multi-year process as a result of being placed on a "fast track" for approval by the Obama Administration. On December 17, 2012, New York state officials dropped their proposal for a 45 percent increase on the state Thruway toll for trucks, while advancing a $3.14 billion project to replace the bridge. The project was funded through a public-private partnership.The new Tappan Zee Bridge was designed and built by Tappan Zee Constructors, LLC consortium of design, engineering, and construction firms including Fluor Corporation, American Bridge Company, Granite Construction Northeast and Traylor Bros. The Left Coast Lifter was used to install groups of pre-assembled girders one full span at a time. By the end of 2013, General Electric had completed four seasons of dredging to remove contaminants from the river bottom. Approximately 70 percent of the sediments targeted for dredging were removed.
On July 19, 2016, a crane used for the construction of the bridge collapsed onto the existing older bridge. Five people were injured, including three drivers and two bridge workers; no one was killed or critically injured.
Completion
The project timeline originally indicated that the old bridge would be closed in 2016 and that the demolition of the old bridge would begin in February 2017. The new northbound/westbound span opened on August 26, 2017. Southbound/eastbound traffic remained on the existing span until October 6, 2017, when it was shifted to the new northbound/westbound span to allow for the completion of the new southbound/eastbound span. The northbound/westbound span of the new Tappan Zee Bridge temporarily carried four lanes in both directions until the new southbound/eastbound span was completed.After some delays, the project was later expected to be completed by June 15, 2018, at a cost of $3.98 billion. However, the scheduled opening was later pushed back to mid-September. The new southbound/eastbound span was supposed to open to traffic on September 8, 2018. An opening ceremony was held on that date, but the traffic shift itself was delayed when a piece of the old bridge came loose on September 7 while being demolished. The opening of the eastbound span, which was away from the old bridge, was delayed until the old bridge could be stabilized. After the old bridge was stabilized, all lanes were opened on September 11, 2018.
Upon completion, the new Tappan Zee Bridge became one of the widest cable-stayed bridges in the world, having a combined width across both decks of. The new spans equal the width of the relatively short-span, cable-stayed Leonard Zakim Bridge in Boston. Turkey's 3rd Bosphorus bridge, completed in 2016, has a single deck about wide. The bridge is intended to last at least 100 years.
The demolition of the old bridge started in November 2017 with the removal of the first steel section from the Rockland County approach. The work continued to April 2018 including removal of the truss sections. In May 2018, the 10-million-pound main span was removed, leaving only the east and west approaches. The original plan was to complete the remaining demolition by taking down spans piece by piece in order to minimize the environmental impacts. However, when the instability of the eastern span was discovered in September 2018, it was decided to destroy it outright. The explosive demolition of the eastern approach took place on January 15, 2019, while the western approach was lowered onto a barge on May 12, 2019 and hauled away.
Tolls
The Tappan Zee Bridge charges tolls in the southbound/eastbound direction only. On weekdays, tolls are variable based on the New York State Thruway's vehicle classification system and the time of day, and are collected using a cashless toll system. On weekends, each vehicle class pays a flat rate. E-ZPass users pay the lowest rate possible, the rate normally charged from 12:00 midnight to 6:14 a.m., while other users are charged using the highest rate possible, the rate normally charged from 7:00 a.m. to 8:59 a.m. Class 2L vehicles, which have a height of less than and contain two axles, pay a flat rate of $5.00 at all times, or $4.75 with a New York-issued E-ZPass.Bicycle-pedestrian path
On June 15, 2020, the bicycle-pedestrian path on the northern span of the bridge opened. The path has six scenic overlooks known as "belvederes." Each belvedere is named after a local point of interest and provides Wi-Fi and a seating area.Lighting
The bridge is equipped with LED lights for the roadways and structures. The lights can be changed to a variety of colors for decorative purposes on major holidays such as Memorial Day and Christmas, traditional dates such as Mother's Day, Father's Day and St. Patrick's Day, and special commemorations throughout the year. The lighting system reputedly has the ability to be synced to music, although it has yet to be demonstrated.Public transportation
West of the Tappan Zee, the 680,000 residents of Rockland and Orange counties currently have very limited mass transit to New York City via NJ Transit's Port Jervis Line and Pascack Valley Line commuter rail services or Coach USA's Rockland Coaches bus services. The bridge plan includes as an objective merely, "Providing a crossing that does not preclude future trans-Hudson transit services."A proposed bus rapid transit system using the new bridge was shelved as too expensive. However, the bridge was structurally built for expansion with BRT and/or commuter rail at a later date. The existing Tarrytown station of the Metro-North Railroad's Hudson Line is located about from the new bridge's eastern landing. In 2011, the state estimated that a bus connector to the station would cost about $151 million, about 3 percent of the bridge's projected cost. Responding to widespread concerns about the lack of new public transit service, bridge planners agreed only to build one "dedicated express bus lane" in each direction for use during rush hour.
Naming
During construction, the project's website referred to the crossing as the "New NY Bridge". However, other sources referred to the crossing as the "New Tappan Zee Bridge".Governor Andrew Cuomo was successful in passing legislation to name the bridge after his late father, former Governor Mario Cuomo, on June 29, 2017. This has been met with significant opposition from residents of nearby localities. Many, including the daughter of former New York Governor Malcolm Wilson, were vocal in their opposition to the name change. A Reclaim New York Initiative poll of Rockland and Westchester county residents found only 14.7% of respondents supported the new name. Many have cited the timing of the New York State legislature vote at the last session before the summer term ended and the last chance to enact a state budget. As of November 29, 2017, over 100,000 people had signed a Change.org petition called "Return the Cuomo Bridge its original name: The Tappan Zee. That bridge is our history." Despite the official name, "Tappan Zee Bridge" remains a common name for the structure.
On December 6, 2017, State Assemblyman Kevin Byrne, a Republican from Mahopac in Putnam County, announced that he would introduce legislation to revert the name of the bridge to the "Malcolm Wilson Tappan Zee Bridge". The old Tappan Zee Bridge had been named for Wilson from 1994 to June 2017. A compromise bill to rename the bridge the "Governor Mario M. Cuomo Tappan Zee Bridge" was later introduced and sponsored by both Senate Deputy Majority Leader John DeFrancisco and Assemblyman Byrne. On June 20, 2018, the State Senate voted 40–20 in favor of renaming the bridge. However, the effort failed after the Assembly's legislative session ended without the bill being put to a vote.