Te Uku Wind Farm


Te Uku Wind Farm is a wind farm at Te Uku near Raglan, New Zealand. It has a capacity of 64MW using 28 wind turbines. Construction was completed in March 2011, at a cost of $200 million. The farm covers an area of approximately. The wind farm is jointly owned by WEL Networks and Meridian Energy.
Resource consent was granted in May 2008 and appeals were resolved by November 2008. Construction of the wind farm began in 2010. Hick Bros Civil and Spartan Construction won an award for outstanding technical and environmental planning. The wind farm was officially opened by the Prime Minister in February 2011. Te Uku was fully operational on 10 March 2011.
Te Uku Windfarm is controlled from Wellington where Meridian has its control center for running all of their New Zealand Hydro and Wind generation assets.
The windfarm is linked to the national grid's Te Kowhai substation by about of 33kv lines on 159 steel poles built on concrete pile foundations and an underground cable from just west of Waitetuna Valley Rd to Cogswell Rd, a total of about.

Construction

Each 130.5 m. high, 318 tonne, turbine took 2 or 3 days to build using 4 cranes, the largest a 600 tonne KR Wind/NZ Crane Group Alliance crane. Towers were formed in 3 sections, and topped by Siemens components - a 3.5 m circumference, 81 tonne nacelle, hub and 3 turbine blades. Barge transport was considered, but rejected in favour of road transporters running from September 2010 to January 2011.

Pipiwharauroa Way

One of the mitigation measures was this walking and cycling track. The track climbs from a car park on Kawhia Rd, near Bridal Veil, runs about 6 km and climbs 280m to the windfarm on Wharauroa Plateau. Over 2 km of less interesting walking can be saved if the walk is started from the gate at the end of the driveable part of Plateau Rd. From this point Lake Disappear can be seen to the south after wet weather. The track peters out into the partly formed paper road. It follows an ancient Maori track which was often used by warriors on raids between Waikato and Kawhia.
The road access to the windfarm largely followed the paper road, which was started around 1900 and seemingly abandoned a few years later, though Bob Vernon also wrote, "about 1919 the Public Works Department cut a six-foot track through solid bush, from the south-eastern end of the plateau to the head of the Makomako valley".
In 2013 there was controversy between a local farmer and Waikato District Council about whether Pipiwharauroa Way could be closed for the lambing season.

Microwave tower

From the mid 1950s a microwave tower has been on the crest of the hill overlooking Te Uku. It is now also part of a smart metering network. There is also a VHF repeater near the tower.