Trojan Nuclear Power Plant


Trojan Nuclear Power Plant was a pressurized water reactor nuclear power plant in the northwest United States, located southeast of Rainier, Oregon, and the only commercial nuclear power plant to be built in Oregon. There was public opposition to the plant from the design stage. The three main opposition groups were the Trojan Decommissioning Alliance, Forelaws on the Board, and Mothers for Peace. There were largely non-violent protests from 1977, and subsequent arrests of participants.
The plant was connected to the grid in December 1975.
After only 16 years of service, the plant was closed in 1992 by its operator, Portland General Electric, after cracks were discovered in the steam-generator tubing. Decommissioning and demolition of the plant began the following year and was completed in 2006.
While operating, Trojan represented more than 12% of the electrical generation capacity of Oregon. The site lies about north of St. Helens, on the west bank of the Columbia River.

History

The Trojan Powder Company had formerly manufactured gunpowder and dynamite on a site on the banks of the Columbia River, from the town of Rainier, Oregon.
In 1967 Portland General Electric chose the site for a new nuclear power plant.
Construction began on February 1, 1970; first criticality was achieved on December 15, 1975, and grid connection eight days later on December 23. Commercial operation began on May 20, under a 35-year license to expire in 2011. At the time, the single 1130 megawatt unit at Trojan was the world's largest pressurized water reactor; it cost $460 million to build
Environmental opposition dogged Trojan from its inception, and the opposition included non-violent protests organized by the Trojan Decommissioning Alliance. Direct action protests were held at the plant in 1977 and 1978, resulting in hundreds of arrests.
In 1978, the plant went offline on March 17 for routine refueling and was idle for nine months while modifications were made to improve its resistance to This followed the discovery of both major building construction errors and the close proximity of a previously unknown fault. The operators sued the builders, and an undisclosed out-of-court settlement was eventually reached.
The Trojan steam generators were designed to last the life of the plant, but it was only four years before premature cracking of the steam tubes was observed. In October 1979, the plant was shut down through the end of the year
In the 1980 election, a ballot measure to ban construction of further nuclear power plants in the state without federally approved waste facilities was approved by the voters 608,412 to 535,049. In 1986, a ballot measure initiated by Lloyd Marbet for immediate closure of the Trojan plant failed 35.7% yes to 64.3% no. This proposal was resubmitted in 1990, and again in 1992 when a similar proposal to close the plant was also included. Each measure was soundly defeated by vote margins over 210,000 votes. Although all closure proposals were defeated, the plant operators committed to successively earlier closure dates for the plant.
In 1992, PGE spent $4.5 million to successfully defeat ballot measures seeking to close Trojan immediately, rather than within four years, as PGE had At the time, it was the most expensive ballot measure campaign in Oregon history. A week after the election, the Trojan plant suffered another steam generator tube leak of radioactive water, and was It was announced that replacement of the steam generators would be necessary. In December 1992, documents were leaked from the U.S. Nuclear Regulatory Commission showing that staff scientists believed that Trojan might be unsafe In early January 1993, PGE chief executive Ken Harrison announced the company would not try to

After 1993 decision not to restart

The spent fuel was transferred from cooling pools to 34 concrete and steel storage casks in 2003.
In 2005, the reactor vessel and other radioactive equipment were removed from the Trojan plant, encased in concrete foam, shrink-wrapped, and transported intact by barge along the Columbia River to Hanford Nuclear Reservation in Washington, where it was buried in a pit and covered with of gravel, which made it the first commercial reactor to be moved and buried whole. It was awaiting transport to the Yucca Mountain Repository until that project was canceled in 2009.
The iconic cooling tower, visible from Interstate 5 in Washington and U.S. Route 30 in Oregon, was demolished in 2006 via dynamite implosion at 7:00 a.m. PDT on Sunday, This event marked the first implosion of a cooling tower at a nuclear plant in the United States. Additional demolition work on the remaining structures continued through 2008. The central office building and the reactor building were demolished by Northwest Demolition and Dismantling in 2008. Remaining are five buildings: two warehouses, a small building on the river side, a guard shack, and offices outside the secured facility. It is expected that demolition of the plant will cost approximately $230 million, which includes the termination of the plant possession-only license, conventional demolition of the building and continuing cost for storage of used nuclear fuel.
A number of the air raid sirens that were originally installed within a radius of Trojan, to warn of an incident at the plant that could endanger the general public, continue to stand in the Washington cities of Longview, Kelso, and Kalama. Some of the other sirens, which have been removed, have been repurposed as tsunami warning sirens along the Oregon coast. While there are no plans to remove the remaining sirens, the city of Longview has removed a few of the sirens on an as-needed basis to make way for other projects.

Heliport

Trojan Heliport was a 60 x 60 ft. private turf heliport located at the power plant. It appears to be defunct at this time.