Welland By-Pass


The Welland By-pass, completed in 1973, was a massive construction project on the Welland Canal in Ontario, Canada.
A new channel long was constructed, providing a shorter, more direct alignment between Port Robinson and Port Colborne and by-passing downtown Welland. The project helped improve navigation along the canal and alleviated problems the presence of a busy ship canal was causing in Welland.

Background

Although the city of Welland had originally grown around the canal, by the 1960s the constant interruptions in the flow of the vehicular and rail traffic through the city became bothersome. A single ship would hold up traffic for at least ten minutes as it travelled under a vertical lift bridge. In periods of heavy ship traffic, a bridge might stay raised for multiple ships to pass, and long lines of cars, trucks and buses could be delayed more than 30 minutes. Additionally, many railroad yards and lines originally built on Welland's outskirts now found themselves in the middle of a growing city; the heavily used rail lines from Toronto to Buffalo were suffering delays, as well.
The old route, established in 1932 with the building of the fourth Welland Canal, was also inconvenient to the ships since it was twisting and narrow. The five vertical lift bridges and a railroad swing bridge, all within close distance of one another, made the manoeuvring tricky and the journey stressful. Captains complained of bulky buildings on the canal's edge blocking the line of sight. One of them commented, "The main thing every Lakes captain used to dread was Bridge 15 , a railway bridge in the town of Welland with an abutment in the middle... I think every captain on the Lakes must have at one time or another."

Construction

The by-pass project was a massive undertaking: 16.2 km² of land was expropriated for the construction. Approximately 50 million cubic metres of material was excavated. The new channel is wide, as compared to the width of the old channel. The channel's minimum depth is. Two tunnels, the Main Street Tunnel and the Townline Tunnel, were constructed to allow vehicles and trains to pass beneath the canal.
To complement this, an aqueduct, to convey the Welland River under the new canal alignment, was built. The aqueduct's design is what is known as a four-tube inverted-syphon culvert, long, wide, and extending below the navigation channel. It was constructed from 30,000 cubic metres of concrete. Approximately of new river channel was constructed to route the river into the aqueduct. The creation of the syphon culvert lowered ground water levels for miles around, the project making many dug wells run dry. The St. Lawrence Seaway Authority denied responsibility, but paid many residents to have a drilled well installed to supply their water.
In compensation for the loss of canal banks through the city of Welland, parts of which were being used as a docking area by local industries, the project incorporated a dock, separated from the main travel route.
Many of the area's rail lines, which had previously been constructed to fit around the existing alignment, had to be dramatically altered for the new alignment. An estimated of new track was laid at a cost of CAD$50 million. A Google map is available which shows the changes to the rail network as a result of the canal relocation, as well as changes made since. This map also details the old and new routes of the canal.
The construction started with the sinking of the first shovel on June 9, 1967, and continued for six years. In a symbolic event watched by many residents, on a snowy night, Bridge #13 on Welland's East Main Street came up for the last time, lighted by floodlights, on December 15, 1972, the new bypass would be open to shipping for the next season.
The Main Street Tunnel was officially opened on May 20, 1972, with the Townline Tunnel following on July 13. Rail traffic through the Townline Tunnel was inaugurated on January 31, 1973. The new canal was first traversed by the Canadian Coast Guard cutter Griffin on March 27, 1973. The first commercial ship to pass through the by-pass was the M.V. Senneville on March 28, 1973. It carried a cargo of 1,063,868 bushels of barley in transit from Duluth, Minnesota to Port Cartier, Quebec. The official opening ceremony for the Welland By-pass took place on July 14, 1973.
Overall, the project cost approximately CAD$188 million. The new channel reduced the length of the canal by and replaced six bridge crossings with the two new tunnels. It reduced the transit time through the Welland Canal by about 30 minutes as compared to the old alignment.

Outcomes

The Welland By-pass markedly simplified ship passage along the Welland Canal. The city was no longer dependent on often erratic ship schedules.
A decision had to be made as to the use of the old alignment. Originally, one of the proposed ideas was for it to be filled in and an extension to Highway 406 be run in it. That never came to be, and instead the old canal was turned over to the city and renamed the Welland Recreational Waterway.
Recently, the city has seen the construction of a new Civic Centre, including the city hall and the public library downtown by the old canal.
Since the opening of the by-pass, Welland's east side has become a virtual island; separated from the rest of the Niagara Peninsula by the old canal channel to the west and by the by-pass channel to the east.