Apalachia Dam


Apalachia Dam is a hydroelectric dam on the Hiwassee River in Cherokee County, in the U.S. state of North Carolina. The dam is the lowermost of three dams on the river owned and operated by the Tennessee Valley Authority, which built the dam in the early 1940s to provide emergency power for aluminum production during World War II. While the dam is in North Carolina, an underground conduit carries water from the dam's reservoir to the powerhouse located downstream across the state line in Polk County, Tennessee. The dam and associated infrastructure were listed on the National Register of Historic Places in 2017.
Apalachia Dam is named for the crossroads community of Old Apalachia, located near the dam site in North Carolina, and the community's L&N railroad stop, known simply as Apalachia, which was further downstream on the Tennessee side of the state line.

Location

Apalachia Dam is located nearly upstream from the mouth of the Hiwassee River, which flows northwestward through Northern Georgia and Western North Carolina before emptying into Chickamauga Lake in East Tennessee. The dam is situated near the center of a scenic and relatively isolated valley sliced by the river as it winds its way through the southwestern fringe of the Blue Ridge Mountains. The Unicoi Mountains rise to the north of the dam, and the Nantahala National Forest surrounds the dam and its reservoir on all sides.
Apalachia Dam's powerhouse is located downstream from the dam at the base of a steep-walled gorge formed as the river flows between two mountain formations. The dam's conduit— all but of which is underground— passes behind the cliffs on the south side of the river.

Capacity

Apalachia Dam is a concrete gravity diversion-type dam high and long, and has a generating capacity of 93,600 kilowatts. The dam's spillway is controlled by 10 radial gates with a combined discharge of. Apalachia Lake stretches for to the base of Hiwassee Dam, and contains of shoreline and of water surface.
A steel penstock connects the reservoir intake at the dam site to the conduit. The conduit emerges from a cliffside overlooking the dam's powerhouse, where it splits into two smaller tunnels which carry the water to a valve house. From the valve house, the water drops through two steel penstocks to the powerhouse turbines below. The total elevation drop from lake surface to power house discharge is to, depending on the lake level.

Background and construction

Private and public entities had been aware of the hydroelectric potential of the Hiwassee River since the early 1900s. The U.S. Army Corps of Engineers identified several potential dams sites, including Apalachia, in the 1920s, and by the time the Tennessee Valley Authority was formed in 1933, several companies had bought up land and flowage rights in the Hiwassee Valley. TVA took the initiative in the valley, however, with the construction of Hiwassee Dam in the late 1930s. By 1941, the outbreak of World War II in Europe brought a drastic increase in the demand for electricity— especially to support aluminum production in the Tennessee Valley— and TVA quickly put together a plan to build several new dams, including Apalachia, all of which were authorized July 16, 1941. Work began on Apalachia the following day.
The construction of Apalachia Dam and its reservoir required the purchase of of land, most of which was in possession of three private entities— the Union Power Company, the Hiwassee-Nolichucky Power Company, and the Hiwassee River Power Company, with Union holding nearly half of the. After the initial purchase, the Hiwassee-Nolichucky Power Company sold TVA an additional, nearly tripling the reservation size. Land for the conduit was transferred by the U.S. Forest Service. Since most of the land was in possession of private companies, only 22 families and of roads had to be relocated.
The construction of the conduit was necessary to exploit the stretch of river immediately downstream from the dam site in which the river drops on average per mile. The conduit's tunnel was built using blasting and a drill jumbo, and its surge tank was excavated into the rock near the valve house.
Apalachia Dam was completed September 15, 1942, and its gates were closed February 14, 1943. The tunnel was completed April 1, 1943. The dam's first generator went online September 22, 1943, and a second went online November 17 of the same year. The total cost of the project was just over $24 million.

Ecology

The construction of the Apalachia Dam eliminated the natural water flow on the Hiwassee River, causing the decline of Ruth's golden aster, a major reason why the plant was placed on the Endangered Species List in 1985.