Availability-based tariff
Availability Based Tariff is a frequency based pricing mechanism applicable in India for unscheduled electric power transactions. The ABT falls under electricity market mechanisms to charge and regulate power to achieve short term and long term network stability as well as incentives and dis-incentives to grid participants against deviations in committed supplies as the case may be.
Introduction
ABT Mechanism in Electricity sector in India is adopted since the year 2000 and in a few other countries for pricing bulk power across various stakeholders. ABT concerns itself with the tariff structure for bulk power and is aimed at bringing about more responsibility and accountability in power generation and consumption through a scheme of incentives and disincentives. As per the notification, ABT was initially made applicable to only central generating stations having more than one SEB/State/Union Territory as its beneficiary. Through this scheme, the Central Electricity Regulatory Commission looks forward to improve the quality of power and curtail the following disruptive trends in power sector:- Unacceptably rapid and high frequency deviations causing damage and disruption to large scale industrial consumers
- Frequent grid disturbances resulting in generators tripping, power outages and power grid disintegration.
Bulk power purchasers can buy electricity on daily basis for short, medium and long term duration from reverse e-auction facility. In reverse e-auction, availability based tariff /Deviation Settlement Mechanism is applied to settle the failed commitments by the electricity sellers or buyers The electricity prices transacted under reverse e-auction facility are far less than the prices agreed under bilateral agreements.
For those power generators who have made power purchase agreements with Discoms and need not participate in day ahead market trading on daily basis, the pecking order among the power generators in a state is called merit order power generation where the lesser variable generation cost electricity producer is selected out of the available generators to maintain the normal grid frequency. IEX is also implementing real-time round the clock trading or one hour ahead trading which will take care of intra day market dynamics. GoI also permitted electricity trading on exchanges with forward and derivatives contracts.
ABT details
- What is availability?
- How is availability calculated?
- Is unified electric grid of India, a smart grid?
- What is the effectiveness criteria of a smart grid?
With an installed capacity of proper mix of base load and variable load generation capability equivalent to the unrestricted annual maximum peak load, the most effective and economical smart grid shall be able to cater more than 99 percentile duration unrestricted load/demand on daily basis with 100% stable operation of the grid. The purpose of smart grid is to supply required electricity at optimum cost with reliability to the final consumers.
Scheduling
- Each day of 24 hrs starting from 00.00 hours be divided into 96 time blocks of 15 minutes each.
- Each generating station is to make advance declaration of its capacity for generation in terms of MWh delivery ex-bus for each time block of the next day. In addition, the total ex-bus MWh which can actually be delivered during the day will also be declared in case of hydro stations. These shall constitute the basis of generation scheduling.
- While declaring the capability, the generator should ensure that the capability during peak hours is not less than that during other hours.
- The Scheduling as referred to above should be in accordance with the operating procedures in force.
- Based on the above declaration, the Regional Load Dispatch Centre shall communicate to the various beneficiaries their respective shares of the available capability.
- After the beneficiaries give their requisition for power based on the generation schedules, the RLDC shall prepare the generation schedules and drawal schedules for each time block after taking into account technical limitations and transmission constraints.
- The schedule of actual generation shall be quantified on ex-bus basis, whereas for beneficiaries, scheduled drawals shall be quantified at their respective receiving points.
- For calculating the drawal schedule for beneficiaries, the transmission losses shall be apportioned in proportion to their drawals.
- In case of any forced outage of a unit, or in case of any transmission bottleneck, RLDC will revise the schedules. The revised schedules will become effective from the 4th time block, counting the time block in which the revision is advised by the generator, to be the 1st one.
- It is also permissible for the generators and the beneficiaries to revise their schedules during a day, but any such revisions shall be effective only from the 6th time block reckoned in the manner as already stated.
ABT features
- ABT brings about enhanced grid discipline
- Economically viable power with right pricing
- Promote competition and efficiency
- Encourage use of Merit Order Dispatch / Economic Dispatch in India.
- Addressing grid disturbance issues
- Gaming and avoiding the same
- Requires special meters, remote metering with open protocols and communication mechanisms to read meters timely
- Software that is comprehensive to do calculations, address regulatory issues and modifications as per different Regulatory Commission requirements.
- Interface options to various stakeholders in the ABT mechanism on line to enable effective implementation and benefits to all* Capability of power producers to be able to control their cost of production as well as flexibility in operations
ABT drawbacks
- As per DSM / UI procedure, the incentives and penalty to the grid participants are charged based on the average grid frequency in a time block of 15 minutes duration. During a time block, it is normal that frequency goes above rated 50 Hz frequency and comes down below rated frequency as the number of frequency excursions above 50 Hz are more than 100 in a day. Thus the average frequency in a time block remains close to the 50 Hz without giving much benefit in the applicable UI tariff for a Discom who is consuming the surplus power available in the grid or generators with valid scheduling who is reducing the generation when frequency is above 50 Hz. Similarly, the generators and Discoms who are not adhering to grid discipline are not penalised with UI tariff in excess of normal tariff when average grid frequency in a time block is used for fixing UI/DSM charges. Each time block is further needs to be separated into two parts for application of UI charges. One for the duration the frequency is more than 50 Hz whose average frequency is considered for fixing UI/ DSM charges to consume the excess power in the grid or reduce excess power generation. Another for the duration the frequency is less than 50 Hz whose average frequency is considered for fixing UI/DSM charges to reduce over drawl and encourage additional power generation.
- Whenever distribution feeders from a substation are switched on after a break down or scheduled power cut, it should be done only when grid frequency is above 50 Hz such that it does not lead to steep drop in the frequency. The total numbers of feeders switching on, in a day are substantial at national level to cause load increase on the grid to cause wide fluctuations.
- The incentives and disincentives are prefixed by the electricity regulator for the variation in the grid frequency which may not reflect the actual situation temporally and spatially on day-to-day basis. There is a need to decide the electricity tariff by the grid participants on day-to-day basis for achieving further fine tuning. To correct these anomalies, CERC has proposed 100% sale and purchase of power produced in day ahead market.
- The ABT mechanism aims to maintain grid frequency at 50 Hz but does not permit the grid participants to decide the optimum frequency within the permitted frequency band on day-to-day basis. This is required not to impose additional load shedding/power cuts when frequency is within the safe variation limits.
- Transmission system operator is obliged to provide non-discriminatory transmission access to electricity generators and consumers in order to promote competition. ABT mechanism does not bring at par all the grid participants whether in private or central sector or state sector ownership. ABT mechanism does not encourage to install the generating units at advantageous locations to offer least cost electricity to the final electricity consumers. ABT mechanism is suitable in an electricity grid suffering from perennial power shortages to prevent overdrwals but it is not suitable for the grid with surplus electricity generation with non-discriminatory responsibility. CERC regulation on ancillary services operations, are permitting only inter state power generating stations to provide these services which are discriminatory by not allowing rest of electricity generators.
- Every state is conducting independently load management to avoid overdrawal from other states by using mix of generation sources to adhere to their power drawal commitments on 15 minutes period basis in ABT mechanism. Thus hydro power stations are ending up to cater base load instead of peak load in non-monsoon months also. TSO is responsible to ensure the provision of reserves that will allow for sudden contingencies by determining the optimal combination of generating stations and reserve providers for each grid trading block. The available hydro power stations in a region/grid should be used to cater peaking load only at regional/national level. Using hydro power stations to cater peak load, would improve the peaking load capability of a regional/national grid and maintain safe grid frequency and network stability. The 24 hours duration of a day should be divided into four parts only instead of 96 number 15 minutes periods for commercially settling the power transactions to cater better to the peak load requirements within the safe frequency range.
- Many gas turbine power stations are not operating due to perennial natural gas shortage. Recently, many DG sets are also idling throughout the year due to better availability of grid power. Alternatively, these power generation units can be put to use for grid reserve service either with liquid / gas fuels when there is unexpected tripping of operating power plants or tripping of a high voltage transmission line to prevent the grid operation below safe limit. This would also allow all the available transmission lines at their full capacity in service without the need to maintain n+1 reserve capacity for meeting any break down and thus accruing savings in high voltage transmission losses. The unified national grid stability can also be enhanced further by converting the existing back to back HVDC links into HVAC links bypassing the existing converter stations. These are Chandrapur back to back HVDC converter station, Vizag back to back HVDC converter station, Sasaram back to back HVDC converter station, Vindhyachal back to back HVDC converter station and HVDC Sileru–Barsoor link. The yearly cost of ensuring grid safety would be less than 2 paisa per Kwh for the total electricity generation in India.
Natural gas transmission
Indian Gas Exchange is starting first online gas trading platform for physical delivery of natural gas. Initially, the company has identified Dahej, Hazira and Kakinada as delivery points and will subsequently include Dhabol, Kochi, Ennore and Mundra terminals.