Centennial Bridge, Panama


's Centennial Bridge is a major bridge crossing the Panama Canal. It was built to supplement the overcrowded Bridge of the Americas and to replace it as the carrier of the Pan-American Highway. Upon its opening in 2004, it became the second permanent crossing of the canal.

Description

The Centennial Bridge is the second major road crossing of the Panama Canal, the first being the Bridge of the Americas.
The Centennial Bridge is located north of the Bridge of the Americas and crosses the Culebra Cut close to the Pedro Miguel locks. New freeway sections, connecting Arraijan in the west to Cerro Patacon in the east via the bridge, significantly alleviate congestion on the Bridge of the Americas.

History

The Bridge of the Americas, which opened in 1962, was the only major road crossing of the Panama Canal. The traffic over this bridge was originally around 9,500 vehicles per day; however, this expanded over time, and by 2004 the bridge was carrying 35,000 vehicles per day.
Since the bridge represented a major bottleneck in the Pan-American Highway, Panama's Ministry of Public Works requested tenders for a second canal crossing in October 2000. The contract to build a replacement bridge was awarded in March 2002. An ambitious schedule of just 29 months was set for construction, so that the bridge could open on the 90th anniversary of the first ship transit of the Panama Canal by the cargo ship Ancon, on 15 August 1914. The bridge was named for Panama's centennial, which occurred on 3 November 2003.
The new bridge was designed by a joint venture between T.Y. Lin International and the Louis Berger Group Inc, and constructed by German-based Bilfinger Berger using resources from its Australian subsidiary Baulderstone Hornibrook. Boston-based transportation architect Miguel Rosales from Rosales + Partners created the concept and initial aesthetic designs for the Panama-Centennial Bridge. Structural engineering contracts were awarded to Leonhardt, Andrä and Partner.
The bridge was inaugurated on schedule on 15 August 2004, although it was opened for traffic on 2 September 2005, when the new highways leading to it were finished.
Part of the access to the Centennial Bridge collapsed in December 2010, following heavy rain and flooding. In November 2011 full traffic was restored.

Construction

The bridge is a cable-stayed design with a total span of 1,052 m. The main span is 420 m and clears the canal by 80 m, allowing large vessels to pass below it. The bridge is supported by two towers, each 184 m high. The deck carries six lanes of traffic across the canal.
The Centennial Bridge is designed to withstand the earthquakes which are frequently recorded in the canal area. It was built by the German construction firm Bilfinger.
The West Tower was built about 50 m inland to allow space for the future widening of the Panama Canal.