Florida High Speed Corridor


The Florida High Speed Corridor is a cancelled taxpayer-funded high-speed rail project in the U.S. state of Florida. Initial service would have run between the cities of Tampa and Orlando, with plans to then extend service to South Florida, terminating in Miami. Trains with a top speed of to would run on dedicated rail lines alongside the state's existing highway network.
Construction of the line was slated to begin in 2011, with the initial Tampa-Orlando phase completed by 2014. On February 16, 2011, Florida Governor Rick Scott formally announced that he would be rejecting federal funds to construct the high-speed railway, thereby killing the Florida High Speed Rail project. Governor Scott said the project was that it would be "far too costly to taxpayers" and that "the risk far outweigh the benefits".
In the wake of the project's cancellation, a private sector express passenger service running across much of the proposed route has been proposed by All Aboard Florida, a subsidiary of Florida East Coast Industries. This project, Brightline, began operations on January 13, 2018.

Proposal

After the original federal proposal in the 1960s, U.S. federal and state governments revisited the idea of fast trains from time to time. The Passenger Railroad Rebuilding Act of 1980 led to funding of high-speed corridor studies in 1984. Private-sector consortia intending to build high-speed lines were created in Florida, Ohio, Texas, California, and Nevada. Maglev trains became a new field of interest. They were officially added to the definition of "railroad" in 1988, and were studied repeatedly. Five high-speed corridors were officially endorsed in October 1992 following passage of the Intermodal Surface Transportation Efficiency Act of 1991. TEA-21 and other legislation continued to be passed with mentions of high-speed rail, but lacking funding or real direction.

Planning

Original referendum

In November 2000, Florida voters approved an amendment to Florida's constitution mandating the state establish a system of high speed trains exceeding 120 mph to link its five largest urban areas, with construction to commence by November 1, 2003. The Florida Legislature enacted the Florida High Speed Rail Authority Act in March 2001, creating the Florida High Speed Rail Authority. The HSRA established a Vision Plan for the system which proposed construction in several phases. Preliminary assessments and environmental studies were begun to develop an initial phase of the system between Orlando and Tampa.
The first phase, planned for completion in 2009 under the original referendum, would have connected Orlando to Tampa, with a later extension to St. Petersburg. Later phases might have extended the network to Miami, Fort Myers, Jacksonville, Tallahassee and Pensacola.
The Florida HSRA issued a Request for Proposal to Design, Build, Operate, Maintain and Finance the Orlando to Tampa Phase In October 2002. Two of the four received in February 2003 were reviewed further, one from a consortium of Fluor Corp. and Bombardier Transportation and one from Global Rail Consortium. The proposals showed cost of the Orlando-Tampa route to be approximately $2.4 billion. Both proposals offered private equity contributions to support operations of the system and show willingness of the private sector to share risk associated with projected ridership revenues. In June 2003 Florida Governor Jeb Bush vetoed funding for the project that the Florida Legislature had approved. The HSRA continued moving forward with the project, using funds already authorized by the federal government, and in October 2003 ranked the Fluor Bombardier proposal first.
In early 2004, Governor Jeb Bush endorsed an effort to repeal the 2000 amendment that mandated the construction of the High Speed Rail System. On October 27, 2004, the authority voted to prefer the consortium of Fluor Corp. and Bombardier Transportation to build and operate the system, using Bombardier's JetTrain technology. However a month later in November, Florida voters repealed the 2000 amendment, removing the constitutional mandate for the system. Although the amendment was repealed, no action was taken by the state legislature in regard to the Florida High Speed Rail Authority Act. With the law still in effect, Florida's HSRA continued to meet, and completed the environmental impact statement for the Tampa-Orlando segment in 2005. With the constitutional mandate gone, however, funding for the project came to a halt and very little action was taken over the next several years.

Plans revived in 2009

Passage of the American Recovery and Reinvestment Act of 2009 designated $8 billion for the development of a high-speed intercity passenger rail system. The Federal Railroad Administration named Florida one of ten high speed rail corridors potentially eligible for the federal funding. The HSRA met on February 26, 2009, to begin planning their application for these funds. Due to the passage of time, potential legal issues, and new federal funding criteria rendering the earlier bids from 2003 inapplicable, the decision was made in May 2009 that a new bidding process would be necessary. A first round application was submitted in August 2009 for $30 million to conduct a two-year environmental study on the Orlando-Miami route. In October 2009, the authority submitted an application during the second round for the entire Tampa - Orlando - Miami corridor, broken into two components: Orlando-Tampa and Orlando-Miami. Connect Us, a political action committee, was launched on August 18, 2009, to rally public support for these applications.
On December 16, the Florida Legislature passed a bill authorizing FDOT move forward with the purchase from CSX of the Central Florida Rail Corridor for the SunRail commuter rail project, and providing much needed additional funding for South Florida's Tri-Rail commuter rail system. Funding of these initiatives was vital to the state's hopes to win federal HSR funding, as it showed the state of Florida was committed to creating a comprehensive rail network allowing connectivity between high speed rail and local mass transit systems. The legislation also replaced the Florida High Speed Rail Authority with the Florida Rail Enterprise, a new agency created under the FDOT, responsible for construction, maintenance, and promotion of the state's high-speed rail system, as well as development and operation of publicly funded passenger rail systems in general.
On January 28, 2010, the White House announced that Florida would receive $1.25 billion of its request, about half of the cost of the Tampa-Orlando segment. The state's efforts towards high speed rail between 2000 and 2005 put Florida ahead of the field in terms of the level of planning already completed, and this proved to be a major factor in winning the funds. The preservation of the I-4 corridor by the FDOT, and completion of the environmental impact studies in 2005 meant that the project could have proceeded to construction in a very short time frame for a relatively affordable cost. In March 2010 the Florida Rail Enterprise was still seeking to refine cost estimates based on advanced engineering, finish development of possible Early Works and contract for bid in 2010 and finally initiate a new bid procurement process specific to the Tampa to Orlando phase. In June 2010, the Federal Railroad Administration issued its record of final decision, the final stage of approval for the design, purchase of land and construction of phase one. Tendering was thus able to begin. In October 2010, Florida received $800 million more towards construction from the FY 2010 High Speed Rail allocations.
In December 2010 the US Department of Transportation redistributed approximately $1.2 billion in HSR funds that had been rejected by governors elect in Wisconsin and Ohio. Florida was projected to receive as much as $342.3 million of the reallocated rail funds which would have closed the gap of the entire projected cost of project. Construction of the line was to begin in 2011, with the initial phase completed by 2014.

Cancellation

On February 16, 2011, Governor Rick Scott formally announced that he would be rejecting federal funds to construct the project, attempting to kill Florida High Speed Rail. On March 4, 2011, the Florida Supreme Court unanimously turned down the request of two state senators to force Scott to accept the federal funding for the project. Shortly thereafter, U.S. Transportation Secretary Ray LaHood announced that he would be redirecting the funds intended for Florida to other states and on May 9, awarded $2.02 billion to 22 projects in 15 states.

Extant construction

In July 2010, the Florida Department of Transportation began geotechnical sampling along the Orlando-Tampa corridor. The soil would have been tested every along the route to check soil conditions and allow proper foundation planning, had the project not been cancelled.

Route

Phase 1: Tampa to Orlando route

In early planning stages, all routes but the one along the median of Interstate 4 were dropped from consideration; alternates used the CSX tracks to the south of I-4. Stations would have been provided at downtown Tampa, northern Lakeland, Walt Disney World, possibly at the Orange County Convention Center, and at Orlando International Airport.

Orlando area route selection

Two routes were considered in the Orlando area. One would have split from I-4 at the interchange with SR 536, World Center Drive, and run east along SR 536 and SR 417, the Central Florida GreeneWay, to the south entrance to Orlando International Airport, from which it would head north to end at the planned South Terminal. The other route would continue along I-4 to SR 528, the Beachline Expressway, with an extra stop at the Orange County Convention Center and International Drive, and then run east along SR 528 and a new right-of-way east and southeast to the south entrance of the airport.

Journey times

The trains would have been capable of reaching speeds of "" but due to the number of proposed stations, a "bullet train would beat a car by only 30 minutes." Proposed journey times for some routes:
RouteDistance Distance Current avg. travel time
Current avg. travel time
Proposed avg. travel time
High Speed Rail
Convention Center – Orlando Airport11 miles18 km16 minutes21 minutes11 minutes
Disney – Orlando Airport19 miles30 km25 minutes34 minutes21 minutes
Downtown Tampa – Orlando Airport84 miles135 km1 hour 22 minutes1 hour 31 minutes1 hour 4 minutes
Lakeland – Downtown Tampa31 miles50 km39 minutes40 minutes22 minutes

Planned stops

The Orlando International Airport was planned to be the Orlando terminus of the initial Orlando-Tampa route. The airport had already invested considerably to accommodate the station, such as the extra length of the taxiway bridge over the southern access road. This station would have provided access for airport passengers and for Orlando's Lynx local bus service.
The Orange County Convention Center is the second largest in the United States, located on International Drive, a major tourist strip connecting SeaWorld Orlando and Universal Orlando Resort. The planned intermodal station here would have also provided access to Orlando's Lynx local bus service, and to International Drive's I-Ride trolley.
Walt Disney World was planning to donate a site for the station, although the exact location was never determined. The station would have linked into the extensive Disney Transport bus system. Also, the Walt Disney Company initially announced that if the SR 417 route was built, they would direct tourists to take the train from the airport to Walt Disney World. They would keep busing tourists if the SR 528 route was built. The SR 417 route was initially selected by a 7-1 vote on October 27, 2004. However, in November 2004 the Florida High Speed Rail Authority dropped the SR 417 from consideration and selected the SR 528 route due to a lack satisfactory progress on the agreements with The Walt Disney Company and Orlando Orange County Expressway Authority.
Two locations were under consideration for a station near Lakeland, Florida. The top choice was near USF Polytechnic followed by a location near Kathleen Road.
A site in downtown Tampa had been cleared for a multi-modal station at the terminus of the route. The station would have been located next to the Marion Transit Center, the main hub of the Hillsborough Area Regional Transit system. A connection to Tampa International Airport was also being considered

Phase 2: Orlando to Miami route

The second phase of the project would have been an Orlando-Miami link. As of the Regional Rail Briefing in Lakeland, Florida, on March 24, 2010, two routes were under consideration. One route followed SR 528 past the Orlando International Airport toward Cape Canaveral, before joining and following Interstate 95 down to Miami. The other route traveled south along Florida's Turnpike to Miami. The environmental impact study for the corridor began in 2010 and would have taken approximately two years to complete.
The higher-speed rail route of Virgin Trains USA being developed between Orlando and Miami closely follows the Cape Canaveral route.