Ground-level power supply, also known as surface current collection and Alimentation Par le Sol, is a modern method of third-rail electrical pick-up for street trams instead of more common overhead lines, thus it is one of the methods that could allow construction of catenary-free light rail system. It was invented for the Bordeaux tramway, which was constructed from 2000 and opened in 2003. From 2011, the technology has been used as part of other systems around the world, with Reims Tramway, Rio de Janeiro VLT, Angers tramway and Dubai Tram all having adopted the technology.
Technology
Ground-level power supply is used, primarily for aesthetic reasons, as an alternative to overhead lines. It is different from the conduit current collection system as it involves burying a third and fourth rail in an underground conduit between the running rails. Conduit current collection was used in historic tram systems in Washington, Manhattan, Paris, Berlin, Marseilles, Vienna, Budapest and London. It fell into disuse because overhead wires proved much less expensive and troublesome for street railways and because in Manhattan, Paris, Washington and West Berlin, all trams were replaced by buses for reasons unrelated to the power supply issue. In Prague on the Charles Bridge, a system invented by František Křižík was used, similar to today's APS.Unlike the track-side third rail used by most metro trains and some main-line railways, APS does not pose a danger to people or animals and so can be used in pedestrian areas and city streets.
APS uses a third rail placed between the running rails, divided electrically into ten-metre rail segments with three-metre neutral sections between. Each tram has two power collection shoes, next to which are antennas that send radio signals to energise the power rail segments as the tram passes over them. At any one time, two consecutive segments under the tram will be live.
Use in Bordeaux
Modern ground-level current collection was pioneered by the Bordeaux tramway in France. The public had assumed that the new system would use a traditional conduit system, like that of the Bordeaux trams which ran prior to 1958 and objected when they learned that it was not considered safe and that overhead wires were to be used instead. Facing complaints both from the public and the French Ministry of Culture, planners developed APS as a modern way of replicating the conduit system.APS was developed by Innorail, a subsidiary of Spie Enertrans but was sold to Alstom when Spie was acquired by Amec.
There are 12 km of APS tramway in the three-line network of 43.3 km as of 2008. Bordeaux Citadis trams use pantographs and electric overhead lines in outlying areas.
Before use in Bordeaux, APS was tested and proved viable on a short section of reserved-track in the French city of Marseille. Nevertheless, Bordeaux has experienced problems, with APS being so temperamental that, at one stage, the Mayor issued an ultimatum that if reliability could not be guaranteed, it would have to be replaced with overhead wires.
Problems have included water-logging, when the water does not drain quickly enough after heavy rain.
In other cities
In July 2006, it was announced that two new French tram systems would be using APS over part of their networks. These are located in Angers and Reims, with both systems opening in 2011. A couple of months later, it was announced that Orléans would use APS on a section of its second tram line, which opened in 2012, and that Tours would use APS on sections of its new network which began service in 2013.APS is also in use in three other tram systems outside France. The first of these, the Dubai Tram opened in 2014, is fully equipped with APS over its entire passenger route length, and thus trams do not use their pantographs unless travelling within the depot area. In June 2016, the first phase of the VLT Carioca network opened in Rio de Janeiro, Brazil. This system mainly uses APS, however where this was deemed impractical, the trams employ SRS, Alstom's proprietary supercapacitor-based energy storage system. The CBD and South East Light Rail in Sydney, Australia, opened in 2019, uses APS within the Sydney CBD and conventional overhead wires elsewhere
Alstom is also currently installing APS in the Tranvía Cuatro Ríos de Cuenca in Cuenca, Ecuador, which also use APS in certain regions only and conventional overhead wires elsewhere.
In 2017, another ground-level power supply technology, TramWave, developed by Italian company Ansaldo, successfully entered commercial application via the opening of Zhuhai tram Line 1 first phase in China, and it is said to be the first 100% low-floor tram system adopting ground level power supply technology. Later in the year, Western Suburb Line in Beijing will also be opened with the same technology from Ansaldo. The technology have been licensed to CRRC Dalian and all the technologies were transferred to China.
Other cities that have previously, or are in the process of proposing the use of APS and similar systems include:
- Nice, France
- TRAMMET, Barcelona, Spain
- Gestione Servizio tramviario, Florence, Italy
- Tramway de Marseille, Marseille, France
- Environmentally Friendly Linkage System, Hong Kong - proposal by opponents of the monorail system to use APS instead.
Similar systems
Stud contact
The predecessors of APS were developed around 1900, and used by several tramway companies in Paris and in England. Associated with these systems were the inventors Dolter and Diatto.There were two main differences from APS:
- Power was supplied not from rails but from studs, set in the road at intervals
- Switching in of the contacts was done by strong electromagnets beneath each car. Each contact contained a fuse, which would be blown by an earthed safety shoe on the rear of the tram should the contact not have switched out. This proved to be unsatisfactory because the strong currents melted down the switch contacts, resulting in contacts frequently remaining 'live'.
Prague
In 1905, a similar system by František Křižík was used on the Charles Bridge. This section was the last one with horse-drawn trams, due to disapproval of overhead lines there. Ground-level supply made it possible to electrify this track. However, the weight of the trams caused damage to the bridge due to vibrations, which is why they were replaced by rail buses in 1908. These were stopped in 1909. In 1932–1939, classic buses on tyres were operated there. Since 1965, Charles Bridge has been a pedestrian-only zone.
Budapest
Another system of ground-level power supply was used by Budapest trams from 1887. Overhead lines were considered an eyesore, so builder Siemens developed the following system: on the inner side of one rail, a powered third rail was hidden underground in a half-covered ditch, with a narrow slit opening upwards, through which a trolley pole reached downward from the trams. The Budapest system was generally safe and water-protected. However, there was no defence against snow and ice, dirt filled up the ditches and trolley poles suffered intense wear. Overhead wire replaced the "Budapest system" everywhere by the 1920s.Conduit
Conduit current collection has the power supply carried in a channel under the roadway between the running rails, much in the same fashion as the cable for cable cars.Stream system
is an acronym that stood for "Sistema di TRasporto Elettrico ad Attrazione Magnetica".The channel made of composite material was thus insulating the vehicle equipped with a special shoe on the passing magnetic channel raised the band allowing contact with the copper strip and then the electrical connection.