Line 5 (São Paulo Metro)


Line 5 is one of the six lines that make up the São Paulo Metro and one of the 13 lines that make up the Metropolitan Rail Transportation Network. The line transports about 600,000 people every business day, and since August 2018 it is operated by the private company ViaMobilidade.
The southern section of the line, between Largo Treze and Capão Redondo was completed in 2002 and was envisioned as a railway line of the CPTM called Line G. The project was transferred to the São Paulo Metro and renamed to Line 5 - Lilac. A northern extension connecting it with the rest of the São Paulo Metro network started construction 2009 with a completion deadline of 2013. The project stalled due to issues with property acquisition and restarted in 2011. The completion deadline of the extension has been delayed several times, but it has been reached on 8 April 2019.

train in Line 5

Stations

Operational

There are currently 17 operational stations on the Capão Redondo ↔ Chácara Klabin stretch:
Extensions from Chácara Klabin station to Ipiranga and from Capão Redondo to Jardim Ângela are planned.

Technical specifications

As of 2019, the line operates with 24 trains and 17 stations, and transports about 600,000 people every business day. Eight additional trains are expected to be added to the line in 2019, after CBTC installation and other enhancements are completed.
It was the first line in the Sao Paulo Metro to utilize the tension 1500 V, Standard Gauge, traction IGBT and 1,60 m wide doors. Santo Amaro station was the first in Brazil to be built on a cable-stayed bridge.
During the extension between Largo Treze and Chacara Klabin stations, three TBMs were used and 26 CAF trains were added to the line in addition to the eight Alstom trains originally available.

Gallery